HomeMy WebLinkAboutCHANGE ORDER 1 AIA Document G701 - 2001
Change Order
OWNER 0 Mayor Mike Moore
ARCHITECT 0 file 1834.01/F-11
CONTRACTOR 0 Cristiani Excavating Co.,Inc.
FIELD 0
PROJECT: Chapel Lake Park CHANGE ORDER NUMBER: 01
City of Jeffersonville
Jeffersonville,IN DATE: January 30,2019
TO CONTRACTOR: ARCHITECTS PROJECT NUMBER: 1834.01
Cristiani Excavating Co.,Inc.
1221 Old Hwy.31 E. CONTRACT DATE: December 19,2018
Clarksville,IN 47130
CONTRACT FOR: General Construction
THE CONTRACT IS CHANGED AS FOLLOWS:
See attached summary sheet
The original Contract Sum was $3,229,000.00
The net change by previously authorized Change Orders $0.00
The Contract Sum prior to this Change Order in the amount of $3229,000.00
The Contract Sum will be Increased deereasest aashanged
by this Change Order In the amount of 867,268.00
The new Contract Sum including this Change Order will be $4,096,268.00
The Contract Time will be increased decreased unchanged by 0 days
The date of Substantial Completion prior to this Change Order was March 19,2019
The date of Substantial Completion as of the date of this Change Order therefore is March 19,2019
NOTE: This Change Order does not include changes in the Contract Sum,Contract Time or Guaranteed Maximum Price which
have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the Owner and
Contractor,in which case a Change Order is executed to supercede the Construction Change Directive.
NOT VALID UNTIL SIGNED BY THE ARCHITECT,CONTRACTOR AND OWNER
Kovert Hawkins Architects Cristiani Excavating Co.Inc. Board of Public Works.City of Jeffersonville
ARCHITECT CONTRACTOR OWNER
630 Walnut Street 1221 Old Hwy.31 E. 500 Quartermaster CL
Jeffersonville,IN 47130 Clarksville,IN 47130 Jeffersonville,IN 47130
ADDRESS ADDRESS ADDRESS
BY BY BY
Matthew D.Guilo,RLA Chris Jackson Mayor Mike Moore ( 1 ----
Name Name Name
30-Jan-19 �3 1 47
Date Date
AIA DOCUMENT G701-2001.Copyright®1979,1987,2000 and 2001 by The American Institute of Architects. Ali rights reserved.
AIA License Number 109187
•
CHANGE ORDER-Contingency Summary
Change Order 01 Summary:
Item Description Amount RFP# Claim#
1 Alternate Structure Castings 1,120.00 NA CP-02
2 Additional Silt Fence 1 1,124.00 NA CP-03
3 Additional Silt Fence 2 2,200.00 NA CP-04
Subtotal 4,444.00
Adjust Contingency Allowance (4,444.00)
Total this Change Order
Contingency Allowance Adjustment Log
Original Contingency Amount/Cash Allowance 210,000.00
Adjustment to Contingency Allowance from Previous Change Orders 0.00
Contingency Allowance Amount Prior to this Change Order 100,000.00
Cash Allowance 110,000.00
Adjustment to Contingency Allowance this Change Order
Balance Remaining in Contingency Allowance 205,556.00
•
CHANGE ORDER-Contract Summary
Change Order 01 Summary:
Item Description Amount RFP# Claim#
1 Basebid Deduct (281,921.00) RFP 1 CP-01
Chapel Lake Bridge Crossing
Lentzier Creek Demo
Lentzier Creek Parking Reduction
Lentzier Creek Playground
Lentzier Creek Lawn Space
Lentzier Ceek Concrete Work
Lentzier Creek Landscape
Lentzier Creek Utilities
Lentzier Creek Site Furniture
2 Alternate 1:Chapel Lake Shelter House 615,535.00 RFP-1 CP-01
3 Alternate 4: Landscape at Chapel Lake 14,457.00 RFP-1 CP-01
4 Alternate 9: Rubber Surface at Chapel Lake Playground 99,956.00 RFP-1 CP-01
5 Alternate 12:Lentzier Creek Restoration-South 187,092.00 RFP-1 CP-01
6 Alternate 15:Multi-use Trail 232,149.00 RFP-1 CP-01
Subtotal 867,268.00
Total this Change Order 3+7 r .31;
Contingency Allowance Adjustment Log
Original Contract Sum 3,229,000.00
Adjustment to Contract Sum from Previous Change Orders 0.00
Contract Sum Amount Prior to this Change Order 3,229,000.00
Adjustment to Contract Sum this Change Order 867,268.00
New Contract Sum 4.096,268.00