HomeMy WebLinkAboutCHAPEL LAKE PARK AI WIP/4 0 Document A101TM - 2017 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AGREEMENT made as of the Nineteenth day of December in the year Two Thousand Eighteen ADDITIONS AND DELETIONS: (In words, indicate day, month and year.) The author of this document has added information needed for its BETWEEN the Owner: completion.The author may also (Name, legal status, address and other information) have revised the text of the original AIA standard form.An Additions and City of Jeffersonville Deletions Report that notes added 500 Quartermaster Court,Suite 200 information as well as revisions to Jeffersonville IN 47130 the standard form text is available Telephone Number:(812)285-6413 from the author and should be reviewed.A vertical line in the left and the Contractor: margin of this document indicates (Name, legal status, address and other information) where the author has added necessary information and where Dan Cristiani Excavating Co.,Inc. the author has added to or deleted 1221 Old Highway 31 E from the original AIA text. Clarksville IN 47129 This document has important legal Telephone Number: 812.282.9866 consequences.Consultation with an attorney is encouraged with respect for the following Project: to its completion or modification. (Name, location and detailed description) The parties should complete 2018 Chapel Lake Park A101 Tm-2017,Exhibit A, Insurance and Bonds,contemporaneously with Community Conservation Park this Agreement.AIA Document New Chapel Road A201 TM-2017,General Conditions Jeffersonville,Indiana 47130 of the Contract for Construction,is adopted in this document by The Architect: reference.Do not use with other (Name, legal status, address and other information) general conditions unless this document is modified. Kovert Hawkins Architects,Inc. 630 Walnut Street Jeffersonville,IN 47130 Telephone Number: 812.282.9554 Fax Number: 812.282.9171 The Owner and Contractor agree as follows. Init. AIA Document A101 T"'-2017.Copyright©1915,1918,1925,1937,1951,1958, 1961,1963,1967,1974,1977,1987,1991,1997,2007 and 2017 by The American Institute of Architects.All rights reserved.WARNING:This AIA' Document is protected by U.S.Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA`' Document,or any portion of it,may result in severe civil and criminal penalties,and will be prosecuted to the maximum extent possible under the law.This document was produced by AIA software at 09:35:45 ET on 12/12/2018 under Order No. 5571159570 which expires on 06/26/2019,and is not for resale. User Notes: (3B9ADA4D) TABLE OF ARTICLES 1 THE CONTRACT DOCUMENTS 2 THE WORK OF THIS CONTRACT 3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION 4 CONTRACT SUM 5 PAYMENTS 6 DISPUTE RESOLUTION 7 TERMINATION OR SUSPENSION 8 MISCELLANEOUS PROVISIONS 9 ENUMERATION OF CONTRACT DOCUMENTS EXHIBIT A INSURANCE AND BONDS ARTICLE 1 THE CONTRACT DOCUMENTS The Contract Documents consist of this Agreement,Conditions of the Contract(General,Supplementary,and other Conditions),Drawings,Specifications,Addenda issued prior to execution of this Agreement,other documents listed in this Agreement,and Modifications issued after execution of this Agreement,all of which form the Contract,and are as fully a part of the Contract as if attached to this Agreement or repeated herein.The Contract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations,representations,or agreements,either written or oral.An enumeration of the Contract Documents,other than a Modification,appears in Article 9. ARTICLE 2 THE WORK OF THIS CONTRACT The Contractor shall fully execute the Work described in the Contract Documents,except as specifically indicated in the Contract Documents to be the responsibility of others. ARTICLE 3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION §3.1 The date of commencement of the Work shall be: (Check one of the following boxes.) [ ] The date of this Agreement. [X ] A date set forth in a notice to proceed issued by the Owner. [ ] Established as follows: (Insert a date or a means to determine the date of commencement of the Work) If a date of commencement of the Work is not selected,then the date of commencement shall be the date of this Agreement. §3.2 The Contract Time shall be measured from the date of commencement of the Work. §3.3 Substantial Completion §3.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents,the Contractor shall achieve Substantial Completion of the entire Work: (Check one of the following boxes and complete the necessary information.) Inst. AIA Document A1011'—2017.Copyright®1915,1918,1925,1937,1951,1958,1961,1963,1967,1974,1977,1987,1991,1997,2007 and 2017 by The American Institute of Architects.All rights reserved.WARNING:This AIA Document is protected by U.S.Copyright Law and International Treaties. 2 Unauthorized reproduction or distribution of this AIA5 Document,or any portion of it,may result in severe civil and criminal penalties,and will be prosecuted to the maximum extent possible under the law.This document was produced by AIA software at 09:35:45 ET on 12/12/2018 under Order No. 5571159570 which expires on 06/26/2019,and is not for resale. User Notes: (3B9ADA4D) [X J Not later than Four Hundred Forty(440)calendar days from the date of commencement of the Work. [ J By the following date: §3.3.2 Subject to adjustments of the Contract Time as provided in the Contract Documents,if portions of the Work are to be completed prior to Substantial Completion of the entire Work,the Contractor shall achieve Substantial Completion of such portions by the following dates: Portion of Work Substantial Completion Date Chapel Lake Shelter September 2,2019 §3.3.3 If the Contractor fails to achieve Substantial Completion as provided in this Section 3.3,liquidated damages, if any,shall be assessed as set forth in Section 4.5. ARTICLE 4 CONTRACT SUM §4.1 The Owner shall pay the Contractor the Contract Sum in current funds for the Contractor's performance of the Contract.The Contract Sum shall be Three Million Two Hundred Twenty Nine Thousand Dollars and.00/$1.00 ($ 3,229,000.00 ),subject to additions and deductions as provided in the Contract Documents. §4.2 Alternates §4.2.1 Alternates,if any,included in the Contract Sum: Item Price §4.2.2 Subject to the conditions noted below,the following alternates may be accepted by the Owner following execution of this Agreement.Upon acceptance,the Owner shall issue a Modification to this Agreement. (Insert below each alternate and the conditions that must be met for the Owner to accept the alternate.) Item Price Conditions for Acceptance §4.3 Allowances,if any,included in the Contract Sum: (Idents each allowance.) Item Price Contingency Allowance $100,000 Playground Equipment $ 50,000 Entrance Sign $ 60,000 §4.4 Unit prices,if any: (Idents the item and state the unit price and quantity limitations, if any, to which the unit price will be applicable.) Item Units and Limitations Price per Unit($0.00) Excavation;earth,trench,machine,including Cubic Yard $ 20.20 removal from site Cubic Yard $ 99.65 Excavation;earth,trench,machine,including Cubic Yard $209.00 removal from site Cubic Yard $ 98.75 Trench Rock Removal Linear Foot $ 7.20 Mass Rock Removal Linear Foot $ 2.80 Dirt Trail Construction Grass Trail Construction §4.5 Liquidated damages,if any: (Insert terms and conditions for liquidated damages, if any.) Init. AIA Document A101"'—2017.Copyright®1915,1918,1925,1937,1951,1958,1961,1963,1967,1974,1977,1987,1991,1997,2007 and 2017 by The American Institute of Architects.All rights reserved.WARNING:This AIA5 Document is protected by U.S.Copyright Law and International Treaties. 3 Unauthorized reproduction or distribution of this AIA,' Document,or any portion of it,may result in severe civil and criminal penalties,and will be prosecuted to the maximum extent possible under the law.This document was produced by AIA software at 09:35:45 ET on 12/12/2018 under Order No. 5571159570 which expires on 06/26/2019,and is not for resale. User Notes: (3B9ADA4D) §4.6 Other: (Insert provisions for bonus or other incentives, if any, that might result in a change to the Contract Sum.) ARTICLE 5 PAYMENTS §5.1 Progress Payments §5.1.1 Based upon Applications for Payment submitted to the Architect by the Contractor and Certificates for Payment issued by the Architect,the Owner shall make progress payments on account of the Contract Sum to the Contractor as provided below and elsewhere in the Contract Documents. §5.1.2 The period covered by each Application for Payment shall be one calendar month ending on the last day of the month,or as follows: §5.1.3 Provided that an Application for Payment is received by the Architect not later than the Twenty-Fifth day of a month,the Owner shall make payment of the amount certified to the Contractor not later than the last day of the following month.If an Application for Payment is received by the Architect after the application date fixed above, payment of the amount certified shall be made by the Owner not later than thirty (30 )days after the Architect receives the Application for Payment. (Federal, state or local laws may require payment within a certain period of time.) §5.1.4 Each Application for Payment shall be based on the most recent schedule of values submitted by the Contractor in accordance with the Contract Documents.The schedule of values shall allocate the entire Contract Sum among the various portions of the Work.The schedule of values shall be prepared in such form,and supported by such data to substantiate its accuracy,as the Architect may require.This schedule of values shall be used as a basis for reviewing the Contractor's Applications for Payment. §5.1.5 Applications for Payment shall show the percentage of completion of each portion of the Work as of the end of the period covered by the Application for Payment. §5.1.6 In accordance with AIA Document A201TM_2017,General Conditions of the Contract for Construction,and subject to other provisions of the Contract Documents,the amount of each progress payment shall be computed as follows: §5.1.6.1 The amount of each progress payment shall first include: .1 That portion of the Contract Sum properly allocable to completed Work; .2 That portion of the Contract Sum properly allocable to materials and equipment delivered and suitably stored at the site for subsequent incorporation in the completed construction,or,if approved in advance by the Owner,suitably stored off the site at a location agreed upon in writing;and .3 That portion of Construction Change Directives that the Architect determines,in the Architect's professional judgment,to be reasonably justified. §5.1.6.2 The amount of each progress payment shall then be reduced by: .1 The aggregate of any amounts previously paid by the Owner; .2 The amount,if any,for Work that remains uncorrected and for which the Architect has previously withheld a Certificate for Payment as provided in Article 9 of AIA Document A201-2017; .3 Any amount for which the Contractor does not intend to pay a Subcontractor or material supplier, unless the Work has been performed by others the Contractor intends to pay; .4 For Work performed or defects discovered since the last payment application,any amount for which the Architect may withhold payment,or nullify a Certificate of Payment in whole or in part,as provided in Article 9 of AIA Document A201-2017;and .5 Retainage withheld pursuant to Section 5.1.7. Inst. AIA Document A101 TM'm2017.Copyright O 1915,1918,1925,1937,1951,1958,1961,1963,1967,1974,1977,1987,1991,1997,2007 and 2017 by The American Institute of Architects.All rights reserved.WARNING:This AIA Document is protected by U.S.Copyright Law and International Treaties. 4 Unauthorized reproduction or distribution of this AIA9 Document,or any portion of it,may result in severe civil and criminal penalties,and will be prosecuted to the maximum extent possible under the law.This document was produced by AIA software at 09:35:45 ET on 12/12/2018 under Order No. 5571159570 which expires on 06/26/2019,and is not for resale. User Notes: (3B9ADA4D) • §5.1.7 Retainage §5.1.7.1 For each progress payment made prior to Substantial Completion of the Work,the Owner may withhold the following amount,as retainage,from the payment otherwise due: (Insert a percentage or amount to be withheld as retainage from each Application for Payment. The amount of retainage may be limited by governing law) §5.1.7.1.1 The following items are not subject to retainage: (Insert any items not subject to the withholding of retainage,such as general conditions, insurance, etc.) §5.1.7.2 Reduction or limitation of retainage,if any,shall be as follows: (If the retainage established in Section 5.1.7.1 is to be modified prior to Substantial Completion of the entire Work, including modifications for Substantial Completion of portions of the Work as provided in Section 3.3.2, insert provisions for such modifications.) §5.1.7.3 Except as set forth in this Section 5.1.7.3,upon Substantial Completion of the Work,the Contractor may submit an Application for Payment that includes the retainage withheld from prior Applications for Payment pursuant to this Section 5.1.7.The Application for Payment submitted at Substantial Completion shall not include retainage as follows: (Insert any other conditions for release of retainage upon Substantial Completion.) §5.1.8 If final completion of the Work is materially delayed through no fault of the Contractor,the Owner shall pay the Contractor any additional amounts in accordance with Article 9 of AIA Document A201-2017. §5.1.9 Except with the Owner's prior approval,the Contractor shall not make advance payments to suppliers for materials or equipment which have not been delivered and stored at the site. §5.2 Final Payment §5.2.1 Final payment,constituting the entire unpaid balance of the Contract Sum,shall be made by the Owner to the Contractor when .1 the Contractor has fully performed the Contract except for the Contractor's responsibility to correct Work as provided in Article 12 of AIA Document A201-2017,and to satisfy other requirements,if any,which extend beyond final payment;and .2 a final Certificate for Payment has been issued by the Architect. §5.2.2 The Owner's final payment to the Contractor shall be made no later than 30 days after the issuance of the Architect's final Certificate for Payment,or as follows: §5.3 Interest Payments due and unpaid under the Contract shall bear interest from the date payment is due at the rate stated below,or in the absence thereof,at the legal rate prevailing from time to time at the place where the Project is located. (Insert rate of interest agreed upon, if any.) Legal prevailing rate Init. AIA Document A101 T"-2017.Copyright©1915,1918,1925,1937,1951,1958,1961,1963,1967,1974,1977,1987,1991,1997,2007 and 2017 by The American Institute of Architects.All rights reserved.WARNING:This AI/5 Document is protected by U.S.Copyright Law and International Treaties. 5 Unauthorized reproduction or distribution of this AI/0 Document,or any portion of it,may result in severe civil and criminal penalties,and will be prosecuted to the maximum extent possible under the law.This document was produced by AIA software at 09:35:45 ET on 12/12/2018 under Order No. 5571159570 which expires on 06/26/2019,and is not for resale. User Notes: (3B9ADA4D) ARTICLE 6 DISPUTE RESOLUTION §6.1 Initial Decision Maker The Architect will serve as the Initial Decision Maker pursuant to Article 15 of AIA Document A201-2017,unless the parties appoint below another individual,not a party to this Agreement,to serve as the Initial Decision Maker. (If the parties mutually agree, insert the name, address and other contact information of the Initial Decision Maker, if other than the Architect.) §6.2 Binding Dispute Resolution For any Claim subject to,but not resolved by,mediation pursuant to Article 15 of AIA Document A201-2017,the method of binding dispute resolution shall be as follows: (Check the appropriate box.) [ ] Arbitration pursuant to Section 15.4 of AIA Document A201-2017 [X] Litigation in a court of competent jurisdiction [ ] Other(Specify) If the Owner and Contractor do not select a method of binding dispute resolution,or do not subsequently agree in writing to a binding dispute resolution method other than litigation,Claims will be resolved by litigation in a court of competent jurisdiction. ARTICLE 7 TERMINATION OR SUSPENSION §7.1 The Contract may be terminated by the Owner or the Contractor as provided in Article 14 of AIA Document A201-2017. §7.1.1 If the Contract is terminated for the Owner's convenience in accordance with Article 14 of AIA Document A201-2017,then the Owner shall pay the Contractor a termination fee as follows: (Insert the amount of or methodfor determining, the fee, if any,payable to the Contractor following a termination for the Owner's convenience.) §7.2 The Work may be suspended by the Owner as provided in Article 14 of AIA Document A201-2017. ARTICLE 8 MISCELLANEOUS PROVISIONS §8.1 Where reference is made in this Agreement to a provision of AIA Document A201-2017 or another Contract Document,the reference refers to that provision as amended or supplemented by other provisions of the Contract Documents. • §8.2 The Owner's representative: (Name, address, email address, and other information) Paul Northam City of Jeffersonville 500 Quartermaster Court,Suite 205 Telephone Number:(812)285-6440 Email Address:pnortham@cityofjeff.net §8.3 The Contractor's representative: Init. AIA Document A101 T"'."2017.Copyright©1915,1918,1925,1937,1951,1958,1961,1963,1967,1974,1977,1987,1991,1997,2007 and 2017 by The American Institute of Architects.All rights reserved.WARNING:This AIA5 Document is protected by U.S.Copyright Law and International Treaties. 6 Unauthorized reproduction or distribution of this AIA'' Document,or any portion of it,may result in severe civil and criminal penalties,and will be prosecuted to the maximum extent possible under the law.This document was produced by AIA software at 09:35:45 ET on 12/12/2018 under Order No. 5571159570 which expires on 06/26/2019,and is not for resale. User Notes: (3B9ADA4D) (Name, address, email address, and other information) Chris Jackson Dan Cristiana Excavating Co.,Inc. 1221 Old Highway 31 E. Clarksville,IN 47129 Telephone Number: 812.282.9866 Email Address:chrisj@dcexc.com §8.4 Neither the Owner's nor the Contractor's representative shall be changed without ten days' prior notice to the other party. §8.5 Insurance and Bonds §8.5.1 The Owner and the Contractor shall purchase and maintain insurance as set forth in AIA Document A101T"_ 2017,Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum, Exhibit A,Insurance and Bonds,and elsewhere in the Contract Documents. §8.5.2 The Contractor shall provide bonds as set forth in AIA Document A101T"_2017 Exhibit A,and elsewhere in the Contract Documents. §8.6 Notice in electronic format,pursuant to Article 1 of AIA Document A201-2017,may be given in accordance with AIA Document E203Tm-2013,Building Information Modeling and Digital Data Exhibit,if completed,or as otherwise set forth below: (If other than in accordance with AIA Document E203-2013, insert requirements for delivering notice in electronic format such as name, title, and email address of the recipient and whether and how the system will be required to generate a read receipt for the transmission.) §8.7 Other provisions: ARTICLE 9 ENUMERATION OF CONTRACT DOCUMENTS §9.1 This Agreement is comprised of the following documents: .1 AIA Document A101T"_2017,Standard Form of Agreement Between Owner and Contractor .2 AIA Document A101T"_2017,Exhibit A,Insurance and Bonds .3 MA Document A201T"_2017,General Conditions of the Contract for Construction .4 MA Document E203T"_2013,Building Information Modeling and Digital Data Exhibit,dated as indicated below: (Insert the date of the E203-2013 incorporated into this Agreement.) .5 Drawings Number Title Date See attached"Exhibit A"-Drawing Index .6 Specifications Section Title Date Pages See attached"Exhibit B"- Specification Index .7 Addenda,if any: Inst. AIA Document A101 T' -2017.Copyright O 1915,1918,1925,1937,1951,1958,1961,1963,1967,1974,1977,1987,1991,1997,2007 and 2017 by The American Institute of Architects.All rights reserved.WARNING:This AIA' Document is protected by U.S.Copyright Law and International Treaties. 7 Unauthorized reproduction or distribution of this AIA'°Document,or any portion of it,may result in severe civil and criminal penalties,and will be prosecuted to the maximum extent possible under the law.This document was produced by AIA software at 09:35:45 ET on 12/12/2018 under Order No. 5571159570 which expires on 06/26/2019,and is not for resale. User Notes: (3B9ADA4D) Number Date Pages One(1) November 1,2018 Thirteen(13) Two(2) November 12,2018 Eighteen(18) Three(3) November 20,2018 Six(6) Four(4) November 26,2018 One(1) Portions of Addenda relating to bidding or proposal requirements are not part of the Contract Documents unless the bidding or proposal requirements are also enumerated in this Article 9. .8 Other Exhibits: (Check all boxes that apply and include appropriate information identin)ing the exhibit where required.) [ j AIA Document E204TM_2017,Sustainable Projects Exhibit,dated as indicated below: (Insert the date of the E204-2017 incorporated into this Agreement.) [ ] The Sustainability Plan: Title Date Pages [ ] Supplementary and other Conditions of the Contract: Document Title Date Pages .9 Other documents,if any,listed below: (List here any additional documents that are intended to form part of the Contract Documents.AIA Document A201 Tm-2017 provides that the advertisement or invitation to bid, Instructions to Bidders, sample forms, the Contractor's bid or proposal,portions of Addenda relating to bidding or proposal requirements, and other information furnished by the Owner in anticipation of receiving bids or proposals, are not part of the Contract Documents unless enumerated in this Agreement.Any such documents should be listed here only if intended to be part of the Contract Documents.) This Agreement entered into as of the day and year first written above. OWNER(Signature) CONTRACTOR(Signature) Nathan Pruitt,Director of Planning and Zoning (Printed name and title) (Printed name and title) Inst. AIA`Document A101 TM—2017.Copyright©1915,1918,1925,1937,1951,1958,1961,1963,1967,1974,1977,1987,1991,1997,2007 and 2017 by The American Institute of Architects.All rights reserved.WARNING:This AIA'Document is protected by U.S.Copyright Law and International Treaties. 8 Unauthorized reproduction or distribution of this AIA"Document,or any portion of it,may result in severe civil and criminal penalties,and will be prosecuted to the maximum extent possible under the law.This document was produced by AIA software at 09:35:45 ET on 12/12/2018 under Order No. 5571159570 which expires on 06/26/2019,and is not for resale. User Notes: (3B9ADA4D) "EXHIBIT A" ARCHITECTURAL DRAWING SHEET INDEX 2018 Chapel Lake Park Jeffersonville, IN Number Title GENERAL DRAWINGS COW OVERALL SITE LOCA00I RAN 6001 RETER0CE WATER TREATMENT PINK SMEVE1101 DRIERS) CA02 OVERALL PARR SURAEV(((0600 G03-1 0651116 C00113015 PINI:SITE WEST CD03-2 0651114 CCOCIDDIS RAH:SITE EAST CDM OVERALL SNE=anal RMI SECTION 1:CHAPEL LAKE DRAWINGS G100.1 CHAPEL LAKE MSE MD 6100-2 CHAPEL LIME ALTERNATE RD [100-0 CRUEL LVE OEA'GIRRI RAI C10I-I CHAPEL LAE OVERALL ME 112011 C101-2 CNARL LAKE ENTRNKE SITE PLAN 0101.3 CHAPEL LANE DETER SITE PVH C1014 HI1LSILE OVERLOOK SITE&0111061085 R.U1 CREEK CGSSIIG SITE a 011151(11 PLAN CHAPEL LAME SIELTSR DLIRGFMOIT 01001101 PERT 0101-5 CHAPEL LAE OMENSIOI RAN C1016 CHAR LAKE TRAIL E SURFACE TREATMDN RAH 0102-1 CHAPEL LAKE OVERALL GRAMS RAN 0102-2 CHAPEL LAKE TRRMCE GRADING 1 DRAINAGE PLAN C102-3 CHAPEL LAZE SHELTER GRADIS 9 DRAINAGE RAI C102-4 CHAPEL LIKE NIORTH PATHS GRADIN G PLAN CHAPEL LIRE MUSE OVERLOOK GRADING PLAN CHAPEL LAO:CRD(CR0411G GRARIG PLAN CHAPEL LAKE SOLIDI PATH CR1111G PLVl CI02-5 CHMEL WE DETAILED LVO:TRADING AND OWIAGE RAH 0103-1 CHAPEL LAKE SEDIMENT CONTROL RAI 0103-2 SEDIMENT CONTROL NARRATIVE 0103-3 SERMON CONTROL LETARS 18101-I CIWR LME LIRRECAPE RAH 1101.2 CHAPEL LAME SHELTER BLOW-UP RMI LID2-1 CNARL LAKE SEED 9 MULCH RAI L103 1 CHAPEL LAKE SITE RI911TSRE RAI DI0T-1 CHAPS LAKE WATER 9 ELECTRICAL RAI 0101-2 OUSEL LME SURTARY RAIZ 0101.1 CHAPEL LME WELTER AR H1TECTRIL RAI 6101-2 CHARS.LAKE 51ELTER FOMENTS.RAN 1101-3 CHAIR VALE WELTER ROOF FRM01G PLAN 81014 CHAPEL LAKE SIELTERROGE RMI 910,-5 01A1 1 LAME SHELTER ELEVAT106 9101-6 CHAPEL IME SHELTER SECT1O6 91013 CHAR)NNE SHELTER Pl1WR1G AND AECNVTCIL PLANS 81011 CHAPELLIE SHELTER ELECTRICAL RA6 SECTION 2:NATURES VIEW DRAWINGS 621-1 IIATIRES VIEW MSE BD G2062 NATURES VIEW ALTERNATE IOD 02000 NATURES NEW OPMRITIRI PLAN 0201-1 IIAITRES NEW OVERALL SITE RMI CAI-2 IATLRES NEW TRAILRE1O SITE PLAN TRMLIEAO DETAIL OPIEI6 01 PVN NATURES NEW PIERL0011 SITE PLAN SEATWALL DETAIL 09M1610N RMI 0201-3 IATUIES NEW TRAIL 9 SURFACE IEATMDIT RAN 0202-1 NATURES VIEW OVERALL GRADING RMI 11111/815 VIEW TPNLHEID DETMED GRADING PUN) 002.2 NEW CRYSTAL SPRIGS RTNALL 003-1 IATIRES VIEW SUWONT CONTROL RAO L201-H MOIRES VIEW LANDSCAPE PLAN 1202-I NATURES NEW SEED 9 MICA PLANT 1203-I NATURES VIEW SITE FURNITURE RAI SECTION 3:LENTZIER CREEK DRAWINGS 0300-1 LENDER CARR MSE MD 6300-2 LODGER CREEK ALTERNATE AD 000-0 LENDER GREEK 000111011 PLAN CAI-1 (ODDER CREEK OVDOO.SITE RAN 001.2 WILDER CREEK SHELTER 9 OVERLOOK SITE PLANS C301-3 GENTLER[RED(SHELTER 9 0IEROR(01MEIAIRI PLANS 001-1 WOOER RIEEK TRAIL 9 SUMFMJ_TREATAE3(I PLAN 002-1 LDNTTIER CRED(OVERALL GRADING RAN C302-2 LENT/1ER CRED(SHELTER MIMED GRADRG RAN 0300.3 LENDER[RED(OVERLOOK CUSSED GRADIS RMI 0031 LODGER CREEK SEDIMENT C 11501 RAN L]011 LENDER CREW SHELTER WUSCME RAI SHELTER 9LOW-IR RMI L302-I IEIITDER CREEK SEED 9 MULCH PLAN L303-1 WDITDER CREEK SITE P RIETURE PIAN 113X1-1 MM.CRETKWATER 9 ELECTRICAL RAI U301-2 101110ER CREEK SANITARY PIAN 9301-I PONDER CREEK SHELTER ARCHITECTURAL RMI 0301.2 1011218 CREEK SHELTER 101R012101 RN1 9301-3 LENT-DER CREEK SHELTER ROOF FRAMING PVH 0301--I IENITTFA OED(S1ELTERIGOF RMI 61815 101DLER CREEK SHELTER ELEVATIONS ism16 EETTDER CREEK SHELTER SECTIONS 03011-2 LDNDER CREEK PLUMB/NG 9 MECHANCAL PLAIN 9181 I WIRIER CREDI ELECTRICAL RNA CONSTRUCTION DETAILS 001 ARM CRGIRICTTOIRTMS 0102 PAM CEISTINCROH RETAILS 6133 PAM CRSRRK:MR OETARS CION PAM CE6T111KIIOI DETAILS CROS PAIN CONSTRUCTION DETAILS LENTZIER CREEK STREAM RESTORATION 0501 STREAM RSTORATGM SOIL PIN1 AND GENERAL MOTES 0501 PEREIM1AL SREIM I-UPPER RFAd1 PROPORED RNEORM MID PROFILE(BEET 11 0103 PERENNL STREAM I-UPPER REACH PROPOSED PLOWER/ANS PROFILE CHEST 21 0501 PERENUL STREAM I-LOWER REAL)PROPOSED PTAEORA NO PROFILE(SLEET I I CW5 RFEHULSIREW I-LOITER(CA01 PROPOSED RAEOPM MO PROFILE(SLEET 21 006 SIORWWATER AWMI RAIEORM MR PROFILE(CRYSTAL SRMICS 01DFML) 0502 RICPOSED ORES SECTIONS(OEET 1) 0508 RKR10ED M305E0106611E021 [509 R1EP3SED MOSS SECTIONS(SHEET 31 0510 PROPOSED CROSS SECTIONS(SHEET I) 011 STREAM RESTOLATG,I OETMS(SHEET I 0512 STREAM 18320016010ETAILS(SHEET 2) CSI T PLANERS RAN "EXHIBIT B" CHAPEL LAKE PARK 201834.01 CITY OF JEFFERSONVILLE, IN 10/17/2018 INDEX TO SPECIFICATIONS BIDDING REQUIREMENTS Section 00 11 13 Notice to Bidders AIA A701 Instructions to Bidders— 1997 Section 00 22 13 Supplementary Instructions to Bidders Section 00 41 00 Contractor's Bid Form: Public Works Section 00 42 01 Proposal Form: Part I (Form 96, Revised 2013) Section 00 42 02 Proposal Form: Part II (Form 96, Revised 2013) Section 00 43 93 Contractor's Bid Submittal Checklist Section 00 45 46.02 Indiana Certificate of Qualification for Public Works Projects CONTRACT FORMS Section 00 43 13 Bid Security Form AIA A310 Bid Bond -2010 Section 00 43 36 Subcontractor List Section 00 52 00 Agreement Form AIA A101 Standard Form of Agreement Between Owner and Contractor-2017 Section 00 52 99 Escrow Agreement Section 00 61 13 Contractor's Bond for Construction AIA A312 Performance Bond and Payment Bond—2010 CONDITIONS OF CONTRACT Section 00 72 00 General Conditions AIA A201 General Conditions of the Contract for Construction—2017 Section 00 73 01 Supplementary General Conditions DIVISION 01 GENERAL REQUIREMENTS Section 01 11 00 Summary of Work- Single Contract Section 01 14 00 General Construction Requirements Section 01 21 13 Cash Allowances Section 01 21 16 Contingency Allowance Section 01 23 00 Alternates Section 01 29 73 Schedule of Values Section 01 31 00 Project Management and Coordination Section 01 31 19 Project Meetings Section 01 32 00 Construction Progress Documentation Section 01 33 00 Submittal Procedures Section 01 35 53 Project Security Section 01 42 00 References Section 01 45 00 Quality Control Section 01 51 00 Temporary Utilities Section 01 53 00 Temporary Construction Section 01 62 00 Product Options and Substitutions Section 01 65 00 Product Delivery and Handling Section 01 74 23 Cleaning Section 01 77 00 Closeout Procedures Section 01 78 00 Closeout Submittals Section 01 78 46 Closeout Maintenance Materials INDEX TO SPECIFICATIONS INDEX-1 "EXHIBIT B" CHAPEL LAKE PARK 201834.01 CITY OF JEFFERSONVILLE, IN 10/17/2018 DIVISION 02 EXISTING CONDITIONS Section 02 30 00 Subsurface Exploration/Investigation Section 02 70 00 Stream Restoration DIVISION 03 CONCRETE Section 03 30 00 Cast-In-Place Concrete DIVISION 04 MASONRY Section 04 01 00 Masonry Protection and Cleaning Section 04 05 13 Mortar Section 04 05 19 Masonry Reinforcement Section 04 05 23 Masonry Accessories Section 04 22 00 Concrete Unit Masonry Section 04 43 01 Limestone Section 04 73 00 Manufactured Stone DIVISION 05 METALS Section 05 50 00 Miscellaneous Metals DIVISION 06 WOODS, PLASTICS AND COMPOSITES Section 06 10 00 Rough Carpentry Section 06 18 00 Glue-Laminated Construction DIVISION 07 THERMAL AND MOISTURE PROTECTION Section 07 11 00 Dampproofing Section 07 19 00 Water Repellents Section 07 21 00 Insulation Section 07 25 00 Weather Barriers Section 07 42 13 Metal Wall and Ceiling Panel Section 07 44 56 Fiber Cement Panels Section 07 60 00 Flashing, Sheet Metal and Roof Accessories Section 07 61 13.02 Metal Roofing Section 07 65 00 Flexible Flashing Section 07 92 00 Joint Sealers DIVISION 08 OPENINGS Section 08 11 13 Steel Doors and Frames Section 08 31 13.01 Access Doors Section 08 31 13.02 Concrete Work and Access Panels Section 08 71 00 Finish Hardware DIVISION 09 FINISHES Section 09 65 13.13 Rubber Base Section 09 90 00 Painting DIVISION 10 SPECIALTIES Section 10 13 00 Building Signs Section 10 14 16 Plaques Section 10 28 13 Toilet Accessories Section 10 28 40 Electric Dryers Section 10 44 00 Fire Extinguishers and Cabinets INDEX TO SPECIFICATIONS INDEX-2 "EXHIBIT B" CHAPEL LAKE PARK 201834.01 CITY OF JEFFERSONVILLE, IN 10/17/2018 DIVISION 11 EQUIPMENT Section 11 68 13 Playground Equipment DIVISION 22 PLUMBING Section 22 05 00 Basic Mechanical Requirements Section 22 05 53 Mechanical Identification Section 22 07 00 Piping Insulation Section 22 10 00 Plumbing Piping Inside Building Section 22 14 00 Plumbing Specialties Section 22 40 00 Plumbing Fixtures DIVISION 23 HEATING, VENTILATING AND AIR CONDITIONING (HVAC) Section 23 05 00 Basic Mechanical Requirements Section 23 05 53 Mechanical Identification Section 23 82 39 Electrical Heaters DIVISION 26 ELECTRICAL Section 26 01 00.01 Summary of Electrical Work Section 26 01 00.02 Electrical Coordination Section 26 01 00.03 Codes, Fees and Standards Section 26 01 00.04 Basic Materials and Methods (Electrical) Section 26 05 19 Wire and Cable Section 26 05 26 Grounding Section 26 05 33.13 Conduit Systems Section 26 05 83 Wiring for Equipment Section 26 09 23 Lighting Sensors Section 26 24 13.02 Feeder and Branch Circuits Section 26 24 16.01 Branch Circuit Panelboards Circuit Breaker Type Section 26 24 16.02 Distribution Panelboards Circuit Breaker Type Section 26 24 19.02 Motor Starter Section 26 27 26 Wiring Devices and Plates Section 26 28 16 Disconnect Switches Section 26 51 00.01 Lighting Section 26 56 00 Exterior Lighting DIVISION 31 EARTHWORK Section 31 00 00 Earthwork Section 31 10 00 Site Clearing Section 31 25 00 Erosion Control Section 31 31 16 Termite Control INDEX TO SPECIFICATIONS INDEX-3 "EXHIBIT B" CHAPEL LAKE PARK 201834.01 CITY OF JEFFERSONVILLE, IN 10/17/2018 DIVISION 32 EXTERIOR IMPROVEMENTS Section 32 12 16 Asphalt Concrete Paving (IN) Section 32 14 16 Brick Pavers Section 32 16 00 Concrete Paving and Curbs Section 32 17 13 Parking Stops Section 32 17 26 Cast In Place Detectable/Tactile Warning Surfaces Section 32 18 16.14 Playground Rubber Surface System Section 32 32 16 Precast Concrete Retaining Wall Section 32 32 23 Segmented Retaining Wall Section 32 33 00 Site Furnishings Section 32 34 13 Pedestrian Bridges Section 32 39 13 Metal Bollards Section 32 92 00 Lawns and Grasses Section 32 92 19 Prairie Grasses Section 32 93 00 Trees, Plants and Ground Covers DIVISION 33 UTILITIES Section 33 10 00 Plumbing Piping Outside Building Section 33 11 00 Water Distribution Section 33 30 00 Sanitary Sewage Section 33 32 00 Sewer Grinder Pump Section 33 40 00 Site Drainage INDEX TO SPECIFICATIONS INDEX-4