Loading...
HomeMy WebLinkAboutTSI CHANGE ORSER #1 NEW CHAPEL SIDEWALKS PHASE 2 CONSTRUCTIONnfc. July 24,2018 Mr.Josh Darby,P.E. JTL Engineers 1829 E. Spring Street,#201 New Albany,IN 47150 Re: New Chapel Sidewalks,Phase 2 Request for Change Order#1 Dear Mr. Darby; Per our earlier requests and conversations,TSI hereby requests a Change Order for the following revisions and changes in scope of work on the above referenced project. Please note the following items: A. • Revisions in pedestrian bridge supports. TSI proposes to eliminate the poured in place piers, including the excavation,backfill, erosion control, shoring, etc,and replace it with a driven pile alternate. This includes the following: • Stamped engineering drawings. (Indiana Stamp). • HP 12x53 piles with points driven with vibratory hammer on excavator. (4) piles each bent, (2) battered and (2)vertical. • Reinforced concrete bents+/-2 ft wide x 3 ft tall x 16 ft long. • Set bridge with bearings as shown on original drawings. • Pour deck as shown on original drawings If approved,the Indiana P.E. will provide the engineered drawings to JTL for final approval. Total Credit for this item---$21,000 B. Change the Keystone type walls with geogrid reinforcing to a stand alone Redi-Rock design(approved by JTL prior to Bid). Locations,elevations, etc,remain the same. A complete submittal on this type of wall has been attached to this letter. Total Credit for this item----$ 67,600 Total Request for Change Order#1-----Credit$88,600 Respectfully submitted; Dennis Coffman,Operations Manager TSI CONSTRUCTION, INC. Post Office Box 1540, New Albany, Indiana 47151-1540 2325 Green Valley Road, Suite#103, New Albany, Indiana 47150 Phone 812.948.6691 Fax 812.948.0266 www.tsiconstructioninc.com CHANGE ORDER-EXTRA WORK AGREEMENT NO. 1 JOB NO. 17108 Project Name New Chapel Sidewalk Phase II Contractor TSI Construction,Inc. You are hereby authorized to proceed with the following described change or extra work: As per attached documentation: 1 Revise Modular Concrete Retaining Wall Supplier to Redi-Rock(Reduces Required Exavation and Geogrid) = $ (55,600.00) 2 Delete Quantity from Item No.26 HMA Over Concrete Pavement Patch:150 SY @$80.00/SY = $ (12,000.00) 3 Revise Prefabricated Pedestrian Bridge Foundation System = $ (21,000.00) TOTAL = $ (88,600.00) The method of payment for this change or extra work shall be: An contract reduction in the amount of Eighty eight thousand six hundred dollars and no cents =$88,600.00 Consulting Engineer: Jacobi, 7..mbs and Lanz,Inc. • 7-ato—t ,ngineei s Signature Date Owner's Approval: City ofJe etson•.e Signature of Owner(s) Date Contractor's Approval: T,F.r Const .c. `'L -./f 1-tae,Gv 7-2(n -18 l Authorized Representative Title Date Pagel ofl