HomeMy WebLinkAboutCHANGED ORDER UTICA PIKE CHANGE ORDER-EXTRA WORK AGREEMENT NO. 4 JOB NO. 17C8
Project Name Utica Pike Sewer Replacement
Contractor Temple and Temple Excavating and Paving
You are hereby authorized to proceed with the following described change or extra work:
As per attached documentation:
1 Connect Laterals from Existing Grinder Pumps = $ 10,068.65
TOTAL = $ 10,068.65
The method of payment for this change or extra work shall be:
An additional amount of Ten thousand sixty eight dollars and sixty five cents =$10,068.65
Consulting Engineer: Jaco.1, Toombs and Lanz,Inc.
5;1'7/
Engineer's Signa - Date
Owner's Approva: I o ors nville
5l17//2
ignature of Owner(s) )atc
Contractor's Approval: Temple and Temple Exca va ting and Paving
yL Secretary/Treasurer 5/14/2018
A y+lorized Representative Title Date
Page 1 of I
4i•Vmple
1mpie
EXCAVATING & PAVING. INC
1367 South Stat%, goad 60 • Salem. IN 47167 - Ph 812-8883 6644 • Fax 812-883.6664
DATE: May 11,2018
TO: Josh Darby
Jacobi,Toombs and Lanz,Inc
RE: Utica Pike
Change Order—Lateral Connection
It was brought to our attention that after completion of the job,a lateral was not shown on the plans. Please
see our price below for potholing existing utilities,installing a 2" line to connect to a nearby location,and
restoring disturbed areas with sod. Please let me know if you have any questions.
Cost per Markup
Description Qty Unit Unit Total Cost % Markup$ Total Price
Laborer 80 HR $ 35.00 $ 2,800.00 15% $ 420.00 $ 3,220.00
Operator 40 HR $ 45.00 $ 1,800.00 15% $ 270.00 $ 2,070.00
Potholing Machine 10 HR $ 85.00 $ 850.00 15% $ 127.50 $ 977.50
Rented Excavator 1 LS $ 619.53 $ 619.53 15% $ 92.93 $ 712.46
2"PVC Pipe 200 LF $ 0.81 $ 162.00 15% $ 24.30 $ 186.30
Fittings 1 LS $ 313.82 $ 313.82 15% $ 47.07 $ 360.89
Skid Steer 10 HR $ 45.00 $ 450.00 15% $ 67.50 $ 517.50
Sodding 220 SY $ 8.00 $ 1,760.00 15% $ 264.00 $ 2,024.00
$ 8,755.35 $ 1,313.30 $ 10,068.65
Sincerely,
Jason Miller
Estimator/Project Manager
Page I of 1