HomeMy WebLinkAboutChange Order No.1 Coopers Lane South Sewers CHANGE ORDER - EXTRA WORK AGREEMENT NO. 1 JOB NO. 0809
Project Name: Coopers lane South Sewers
Owner. Jeffersonville Sewer Board
Contractor: Dan Cristiani Excavating, Inc.
General Contract Additions
1 Deduct in quantity of 8' Sanitary Sewer, SDR 35 !Installation) by 53 LF @ $53.32/IF (Pay Item 2) - $2,825.96
2 Deduct In quantity of 8' Sanitary Sewer, SDR 35 (Material) by 53 LF @ $2.63/LF (Pay Item 2.1) -5139.39
3 Increase In quantity of Property Service Connections (Installation) by 7 @ $1,037/ea. (Pay Item 4) 57,259.00
4 Increase In quantity of Property Service Connections (Material) by 7 @ $439/ea. (Pay Item 4.1) 53,073.00
5 Increase in quantity of 4' Force Main (Installation) by 23 LF @ $30.91/LF (Pay Item 10) $710.93
6 Increase in quantity of 4' Force Main (Material) by 23 LF @ $1.54/LF (Pay Item 10.1) 535.42
7 Decrease In quantity of Silt Fence by 2001F @ $L80 /lF (Pay Item 11) 4360.00
8 Decrease in quantity of Concrete Encasement by 75 LF @ $23.011/1.F (Pay Item 12) 41,725.00
9 Decrease in quantity of Surface Asphalt by 94.45 Ton (9 561.50/Ton (Pay Item 14) 45,808.68
10 W mp Sum Modifications @ 5005 Hamburg Pike due to Water line Confkt (Sue Attached) 53,857.59
11 Fence & Asphalt Modifications @ Pump Station Site (See Attached) 51,314.00
Subtotal 55,390.91
Total Change Order:
increase in the amount of Five Thousand Three- Hundred and Ninety Dollars and NtnetyOne Cents. 55,390.91
Consulting Engineer: Jacobi, Ioombs & Lanz, Inc.
9
Enginee S 1 ,:l
Date
Owner's Approval: Jeffersonville Sewer B VI)a,7)/(
lure Owner(s) of owr(sl
Contractor's Approval: Dan Cristaan) Excavating, Inc. /' ('
QA t r 11 it\ O, /-
Authorized Representative Signature (] Date
•
DAN CRISTIANI EXCAVATING CO., INC.
1221 Old Hwy. 3113
P.O. Box 2427
CIarksville, SN 47131 -2427
PHONE (812)282 -9866 Pax (8I2)282 -9908
PROPOSAL
To: City of Jeffersonville
Attn: Josh Hillman
DATE: June 30, 2011
JOBBITE: Cooper Lane
Proposal for extra work performed on Line D approximately station 22 +00 due to
16" water line interference. The proposed 8" route was already sawcut and some
excavation before being stopped and redirected.
Proposed 8" area
Sawcut on 8" main 234' a $1.35 $315.90
Asphalt restoration 60'X 4.5' 5 ton. a $80 $400.00
Stone backfill 20 ton 0 7.00 $140.00
Proposed lateral alternate route 6"
6" pipe 120 foot a 22.00 $2640.00
6" sawcut Coopers 80' a $1.35 $ 108.00
6" Bends 45 2 018.00 $ 36.00
Stone backfill 80' 80 tone ® 7.00 $ 560.00
Asphalt patch 200' 3 tons ® 80.00 $ 240.00
Normal Lateral Deduction
6" pipe 28' a $22.00 - $ 616.00
Sawcut 20' a $1.35 foot - $ 27.00
Stone Backfil] 30 Ton a $7.00 - $ 210.00
Asphalt Patch 20' 1 ton a 80 - $ 80.00
Sub total $3506.90
Mark up %10 350.69
Total Change $3857.59
Acceptance to constitute a contract between us. This bid to hold for a period
of 30 days from date. Terms: Net I5 days following date of invoice.
DAN CRIBTIANI EXCAVATING CO., INC. ACCEPTED
444 Au/
BY BY
DATE
Or \PROPOSALS 2 C11\A ULRRX PROPOSAL PORR.doc
DAN C.RJSTI NI EXCAVATING CO., INC.
1221 Old Hwy. 31E
P.O. Box 2427
CIarksville, IN 47131 -2427
PRONE (8I2)282 -9866 Fax (812)282 -9908
PROPOSAL
To: City of Jeffersonville
Attn: Josh Hillman
DATE: July 26, 201I
JOBSITE: Coopers Lane Lift station
Proposal for additional fence and asphalt at the Coopers Lane Lift Station to
allow for additional room for the portable generator. Approximately 10' x 38'
Remove previous set post $150.00
Hartlage Pence $385.00
Stone base 20 ton $185.00
Libs Paving 4" 9 ton $594.00
Total add $ 1314.00
Acceptance to constitute a contract between us. This bid to hold for a period
of 30 days from date. Terms: Net 15 days following date of invoice.
DAN CRISTIANI EXCAVATING CO., INC. ACCEPTED
BY BY
DATE