Loading...
HomeMy WebLinkAbout11-20-2002MINUTES OF MEETING JEFFERSONVILLE REDEVELOPMENT COMMISSION Wednesday, November 20, 2002 The Jeffersonville Redevelopment Commission met on Wednesday November 20, 2002 in the Mayor's Conference Room, Fourth Floor, 501 E. Court Avenue, Jeffersonville, Indiana. The following were present: Robert Campbell, President Barry Cahill, Vice President Nathan Samuel, Secretary Ed Zastawny, Commission Member Kyle Williams, Commission Member STAFF: Dustin White, Interim Director Mary Sue Ellenbrand, Assistant to Director Kathy Haller, Consultant David Duggins, Consultant Anne Marie Galligan, City Attorney Thomas R. Galligan, Mayor GUEST: Jorge Lanz, of Jacob, Toombs, & Lanz CALL TO ORDER: President Robert Campbell called the meeting to order at 5:35 PM APPROVAL OF MINUTES: Mr. Campbell asked for any additions or corrections to the minutes of the October 30, 2002 meeting. Hearing none Mr. Cahill made a motion to approve the minutes of the October 30, 2002 meeting. Mr. Williams seconded. Motion carried unanimously. CLAIMS: Mr. White presented claims for the month of November totaling $7,313.94. Mr. Zastawny made a motion to approve the claims for November 2002. Mr. Williams seconded. Motion carried unanimously UPDATE ON TENTH AND SPRING STREET: City Attorney, Anne Marie Galligan, gave an update on the progress of the Tenth and Spring Street project. Ms. Galligan reported that the two buildings owned by Mr. Glenn Lewis were taken down premature. A check for $350,000.00 was sent to Mr. Lewis but was never cashed. Due to an error by the The Evening News the notice of condemnation was not published properly. This delayed the process. All legal work was done properly and the condemnation will be complete in the next few weeks. Mr. Lewis had ample opportunity to contest the condemnation but did not show up at the necessary hearings. A miscommunication with the construction crew resulted in the buildings being taken down. The check was returned this week. Mrs. Galligan stated that the RFP process and the widening of 10`h Street would proceed as scheduled. UPDATE ON QUADRANGLE: Mayor Galligan reported that he and Mr. Neal Harding, of the Heritage Group, met on Monday, November 18 and Mr. Harding informed him that they would not be able to continue with the Quadrangle project. Mr. Harding said that due to the Department of Natural Resources not approving their plans they would miss the deadline on the tax credits and would not be able to proceed with the project. Mayor Galligan then reported that-plans to move the city offices to the Quadrangle would proceed. VETERANS PARKWAY CHANGE ORDER REQUEST: Mr. Jorge Lanz, of Jacobi, Toombs and Lanz presented a Veterans Parkway Change Order request. This is change order No. 1. This Change Order consists of a Three-Sided Arch Culvert added to the contract as stated in Item 0111. Mr. Samuel made a motion to approve Change Order No. 1 and Mr. Zastawny seconded. Motion passed. CASI PARKING LOT IMPROVEMENT INVOICE: Mr. White presented a claim for $18,166.00 for paving the CASI parking lot. This money will come out of the CASI account. The Commissioners requested that the next time there is any expenditure from the CASI account the Commissioners be advised in advance. Mr. Duggins reported that the paving and a new furnace were agreed upon at the time of the purchase of the building. Mr. Cahill made a motion to approve the claim for $18,166.00. Mr. Williams seconded. Motion carried. PROJECT UPDATE REPORT: (See attached sheet) Ms. Haller presented the Project Update Report. ADJOURNMENT: Mr. Campbell asked if there was any additional business. Hearing none Mr. Zastawny made a motion to adjourn the meeting. APPROVED: Robert Campbell, President Nathan Samuel, Secretary ~] I~ PROJECT DEVELOPMENT UPDATE INTERCITY ROAD BRIDGE PROJECT: February: Engineering plans are 99% complete. Ready to submit to INDOT. July letting anticipated for the road and bridge project. Property acquisition: proceeding with condemnation with trustees of church. March: Plans submitted and a copy made available to Redevelopment. Awaiting review. April: Received review. Submitting final tracings. Haven't received final comments on bridge. Late Sumner letting period. May: Jeffersonville will be the lead agency on the Veterans Parkway . Jeffersonville is on the state's August letting schedule. June: Jeffersonville still on the state's August letting schedule. July: Nothing new to report at this time. August: Refer to report from Jorge Lanz, Jacobi, Toombs & Lanz, Inc. September: Groundbreaking scheduled for Thursday, Sept. 26°' at BestvvayTrucking. Some construction has begun. October: Construction is on schedule. November: Construction going slow due to wet weather. Ready to begin construction on Veterans Parktivay Bridge over US 31 and L&I RR tracks. NORTIISHORE DEVELOPMENT: February: Ceridian did not work out. Oncology group is interested in second floor. MRI group in interested in remaining square footage on first floor. Looking at Verizon group for rooftop towers and renting some space in basement. Vision Plus has moved in. Union Planters has not yet moved in. A local educational institution is .still renting. Will still have 4,300 sq ft remaining on the second floor. March: A local educational institution is still renting and has expressed interest in permanent space. Union Planters signed their lease. A travel agency has undertaken negotiations for 1 '/z floors of space. April: Union Planters will start improvements on Monday. IUS has approval from Bloomington to establish a fixed site and hope to complete negotiations in May for availability in Fall. A travel agency is still in discussions for 1 '/z floors of space, as well as a dot com company and a medical group. If all these sign, building should be at 90% capacity. May: Union planters improvements are almost complete. IUS is continuing to move along, however, some discussion has occurred concerning possible undergraduates attending. Third floor -three groups still interested and now talking specifics with prospects. The dot com company and the medical group are still in negotiations. June: Third floor-one medical group has indicated serious interest and taken measurements. Union planters will move the weekend of July 20`i' and open on July 22"d. IUS anticipate signing lease this week for 3800 sq ft on third and 1500 on first floor, and have permits to begin construction this week. Anticipate opening this Fall. Several other prospects have indicated interest in third floor -nothing specific. July: IUS signed the lease for 3800 sq ft on third floor and 1500 on first floor. Ribbon cutting was held July 15"'. Expect classes to begin Fall of 2002. August: Nothing new to report at this time. September: NS holding classes. Two tenantslooking at second floor space -1800 sq. ft. for electrical distributor. Two companies still looking at third floor, but nothing definite. October: Three parties interested in 3rd floor and one party is looking at the remaining half of the second floor. Should know something within 30 days. The interested parties are looking to begin operations by Spring of 2003. November: Received proposed plans for finishing out half of 2nd floor and all of 4`h floor for a travel agency. Have not signed the agreement, as yet. If this proposal were accepted, only 1/3 of first floor would • , remain for lease. H:UCathy\DORreports\02 Nov project update.doc -1- PROJECT DEVELOPMENT UPDATE URBAN ENTERPRISE ZONE: February: Refer to David's report. March: Refer to David's report. April: Awaiting receipt of fully executed grant agreement for $22,095. May: Received fully executed grant agreement for $22,095. Have instructed the selected engineering firm of Lineback Funld~ouser to proceed with Phase I and Phase II environmental assessment. June: Preliminary report on the lab results to be completed mid-week. Engineering firm is preparing a final invoice for the Phase I and II for. the two sites at 10~' & Spring Streets. July : Engineering report recommended additional testing at the R&W site. Currently negotiating with IDOC to allow the balance of funds not used on the grant (due to the unavailability of the third site - fireworks warehouse) and re-allocate those unspent funds for the additional testing. August: submitted a claim voucher for $12,770 for final payment for Phase I and Phase II for R&W Tire Store and Andy Hampton's Used Car Sales. Also submitted a revised scope of work for additional work at R&W Tire Store for $7,565. September: Awaiting receipt of payment request for the Phase I and Phase II environmental assessment on Tenth & Spring Streets. October: received authorization from IDOC to conduct additional testing on the R&W Tire Store site. This will result in an additional expenditure of $7,565 from the original grant, leaving a balance of $1,760 that will revert back to IDOC. November: Authorized Lineback Funkhouser to proceed with additional testing at the RB.W Tire Store site. Additional testing should be completed by early next week. COURT AVENUE EXTENSION: February: Have secured approval of plans by INDOT. Awaiting signature process at the state level. Anticipate being able to bid the project around the first part of June 2002. March: Awaiting the finalization ofhold-harmless agreement between INDOT and the City regarding liability for possible safety issues. April: Nothing new to report at this time. May: Bob Miller sent papers in to INDOT for an inspection engineer on June 4°i. Should have a letting before the end of June. June: Final confirmation of the drop-dead date for bidding on Court Avenue extension is Sept. 1, 2002. It may go to bid in August. July: City Engineer still pushing ahead on this project. August: Nothing new to report at this time. September: City Engineer reports bid letting has been pushed back to November 1, 2002. October: INDOT requested additional infornlation, which has been reviewed and approved. Contract letting pushed back to Februray 18, 2003. November: The date for contract letting has been changed to January 20, 2003. Will take place in Indianapolis offices of INDOT. BETH NOVA TUBE L.L.C.: February: No report at this time. March: No report at this time. April: The report for the first quarter of 2002 showed 7 new jobs, compared to a goal of 74. Capital investment was $12,915,283.64 compared to a goal of $19,565,000. • May: No report at this time. • June: No report at this time. July: No report at this time. H:\Kathy\DOR reports\02 Nov project update.doc -2- PROJECT DEVELOPMENT UPDATE August: The report the second quarter of 2002 showed 9 new jobs to-date, compared to a goal of 74. Capital investment was $16,478,757.00 to-date. September: No report at this time. October: No report at this time. However, a conversation with plant manager revealed that a total of 4 new hires had been made. November: The report for the third quarter of 2002 showed 2 new jobs, bringing the total to 11 new jobs to-date out of a goal of 74. Capital investment to-date is $16,916,596.10. INAAP: February: Nothing new to report at this time. March: Nothing new to report at this time. April: Nothing new to report at this time. May: Nothing new to report at this time. June: Nothing new to report at this time. July: Nothing new to report at this time. August: Nothing new to report at this time. September: Nothing new to report at this time. October: Sent master lease off to Washington for the entire Park property, fora 25-year lease -will allow them to sub-lease. Completed the engineering study for development of the first 900 acres -fronting along Hwy 62. Ready to ask Army to deed the 900 acres outright. Completed archaeological study for the 900 acres, which was OK. Going to bring property manager in-house, rather than sub-contract. November: Nothing new to report at this time. RIVERFRONT OFFICE CONDOS (NORTH SHORE OFFICE PARK): February: Have secured a ]ease for 8,000 sq. ft. out of the first 16,000 sq.ft. Exterior is completed. Build- out will be accomplished as new contracts are executed. March: Project is 95% complete. Small items need to be completed, as well as a gas line issue that is close to resolution. Parking lot will go down in 2 weeks. Landscaping should be installed shortly. Sidewalks are poured and curbs. Close on a couple deals for prospective clients. April: Reported a closing on one of the units and being close on two other units out of the 16 units completed to date. May: Closed on the first condo and the owners have moved in. Three other prospects are in the negotiation stages. Ready to finish the landscaping. Any interest in touring the new condos will be gladly accommodated. June: Nothing new to report at this time. July: Landscaping for this phase is complete. August: One unit leased and tenants moved in, as of 9/1/02. Long distance service business. Have since begun constntction of three leased units, as of 1 week ago with planned completion on Oct. 1 -coordinating auto delivery for Ford. Working on construction of another model unit. September: Construction on interior of four units. Should complete this activity in 30 days. October: An Open House is scheduled for Friday, November 22"d at 11 AM. November: Nothing new to report at this time. QUARTER~9ASTER DEPOT: February: Working on the details of contract with Heritage Foundation. 11~Iarch: Refer to meeting comments. April: Environmental Review Process, including Section 106 Historic Review has commenced. May: Will publish the Finding of No Significant Impact within the next rivo weeks. Continuing to work with the project architect to develop a packet for historic review. H:![Cathy\DOR reports\02 Nov project update.doc -3- ...-~...~~.,.-._r_. _.___._ r _,____r _______- -6-