HomeMy WebLinkAboutChange Order 4
CHANGE ORDER - EXTRA WORK AGREEMENT NO.
I
4
JOB NO.
0720
Project Name: Blanchel Terrace Combined Sewer Separation
i I
Owner:
Jeffersonville Sewer Board
Contractor:
Team Contracting, LLC
I. Asphalt Wedging & Additional y," of Surface Asphalt, I 06.75 tons @ $60.00/ton (Per unit price submitted w/bid)
2. Concrete Driveway Apron to create positive drainage, 9.6 sys @ $75.00/sys
$ 6,405.00
$ 720.00
3. Deduction in unit quantities of surface milling by 204.4 sys ~ $1.60/sys (per unit price submitted w/bid) $ -327.04
4. Deduction in unit quantities of 6-inch stand-up ccncrete curb by 28.3 If@ $I4.00/lf (Per unit price submitted w/bid) $ -396.20
5. Delete pay item No.7, Dewatering for C.I.P.P. Installation $ -1.00
Total $ 6,400.76
r,
The method of payment for this change order shall be an addition in the amount of
Six Thousand Four Hundred Dollars and Seventy Six Cents.
$ 6,400.76
I
Date
t1T
acting,LLC
~~zrA/(W,46-t.:H-
Title
71 ~8
Date
r,
S\EP2002\PROJEC TS\0720\0720i -C 04