HomeMy WebLinkAbout01) Change Order #1
1
JOB NO.
CHANGE ORDER - EXTRA WORK AGREEMENT NO.
0642i
Longview Beach Pump Sation, Upper River Road Pump Station, Sanitary Sewer and Force Main
Project Name
Installation
Contractor
:MAC Construction & Ex-cavating, Inc.
The increase in unit price for items 1-19 is due to an increase in shipping cost due to the delay in awarding the
contract.
1. Add $0.80 to unit price ofItem No.8, from $64.00 per LF to $64.80 per LF
2. Add $1.50 to unit price ofItem No.9, from $105.00 per LF to $106.50 per LF
3. Add $0.60 to unit price ofItem No. 10, from $38.00 per LF to $38.60 per LF
4. Add $0.60 to unit price ofItem No. 11, from $42.00 per LF to $42.60 per LF
5. Add $0.50 to unit price ofItem No. 12, from $31.00 per LF to $31.50 per LF
6. Add $0.50 to unit price ofItem No. 13, from $31.00 per LF to $31.50 per LF
7. Add $1.50 to unit price ofItem No. 14, from $88.00 per LF to $89.50 per LF
8. Add $1.50 to unit price ofItem No. 15, from $90.00 per LF to $91.50 per LF
9. Add $0.50 to unit price ofItem No. 16, from $40.00 per LF to $40.50 per LF
10. Add $150.00 to unit price ofItem No. 17, from $3100.00 per EA to $3250.00 per LF
11. Add $150.00 to unit price ofItem No. 18, from $2900.00 per EA to $3050.00 per LF
12. Add $400.00 to unit price ofItem No. 19, from $6500.00 per EA to $6900.00 per LF
13. Add $157.00 to unit price ofItem No. 20, from $4800.00 per EA to $4957.00 per LF
14. Add $21.19 to unit price ofItem No. 21, from $1800.00 per EA to $1821.19 per LF
15. Add $3100.00 to unit price ofItem No. 24, from $188,000.00 per LS to $191,100.00 per LS
16. Add $1,300.00 to unit price ofItem No. 25, from $45,500.00 per LS to $46,800.00 per LS
17. Add $1.20 to unit price ofItem No. 26, from $60.00 per TON to $61.20 per TON
18. Add $1.20 to unit price of Item No. 27, from $54.00 per TON to $55.20 per TON
19. Add $0.50 to unit price ofItem No. 27, from $30.00 per TON to $30.50 per TON
Subtotal of Items 1-19
Additional Cost due to the relocation of the Upper River Road Lift Station
20. Additional site work near the hill side, 1 LS @$4,697.00
21. Large tree removal, 10 trees (12"-24"), 1 LS @ $3,003.00
22. Rock excavation and additional trucking due to truck constraint, 40 CYS @ $200 per CYS
23. Additional depth to wetwell, 1 LS @ $1,968.00
24. 12" RCP, 56 LF @ $32.71 per LF
You are hereby authorized to proceed with the following described change or extra work:
As per attached documentation:
Subtotal of Items 20-24
$
$
= $
$
$
$
= $
= $
$
$
= $
= $
= $
= $
$
$
= $
$
= $
= $
$
$
= $
= $
= $
= $
816.00
1,543.75
960.00
1,818.60
1,375.50
1,353.00
301.50
415.50
2,850.00
1,350.00
1,200.00
314.00
1,589.25
3,100.00
1,300.00
1,266.00
307.20
387.50
22,247.80
4,697.00
3,003.00
8,000.00
1,968.00
1,832.00
19,500.00
ADD = $ 41,747.80
The method of payment for this change or extra work shall be:
A addition in the amount of for one thousand and seven hundred and four -seven dollars and ei h cents =
$41,747.80
Inc.
C:Aaron\0411i\0641i change order-I REVISED
Page 1 of 2
.. ..
CHANGE ORDER - EXTRA WORK AGREEMENT NO.
1
JOB NO.
0642i
Longview Beach Pump Sation, Upper River Road Pump Station, Sanitary Sewer and Force Main
Project Name Installation
MAC Construction & Excavating, Inc.
val: ..MAC Construction & Exca
p
C:Aaron\04I 2i\0642i change order-I REVISED
Page 2 of 2