HomeMy WebLinkAboutJacobi, Toombs, and Lanz (Wastewater)City of Jeffersonville
Government Contract Coversheet
Please note: All information MUST be completely filled out and submitted to Clerk's Office
within 48 hrs of execution.
Date Submitted to Clerk: 1/24/2025
WastewaterDepartment:
Vendor Name:
Jacobi, Toombs & Lanz, LLC
Sign Date: 1/23/2025
Ending Date: August 31,2025
Amount of Original Contract: 150,000
Is this an amendment or change order
to original contract?
Amended Contract Amount:
Purpose:
Construction Administration & Inspection
Services for three (3) Construction Projects.
For Clerk's Office to fill out
Date uploaded to Gateway: //p?016
ATTACHMENT B: WORK ORDER FORM
WORK ORDER NO. 2025-1
CHERRY CREEK PUMP STATION REPLACEMENT,
GCCS NEW MIDDLE SCHOOL SEWER SERVICE EXTENSION AND
SR 62 LOW PRESSURE SEWER EXTENSION
CONSTRUCTION ADMINISTRATION AND INSPECTION
Date: t/o7
In accordance with the General Services Agreement between the City of Jeffersonville, Indiana, acting
thru its duly appointed Sewer Board (OWNER), and Jacobi, Toombs and Lanz, LLC (CONSULTANT),
dated 04/01/2010, this WORK ORDER is the written authorization to the CONSULTANT to provide the
work described herein, in accordance with the attached schedule, and fees
Work: The Work shall be as described in Section A of this Work Order. CONSULTANT shall furnish all
labor, materials, supplies, equipment, supervision and services necessary for and incident to the
performance of the Work. CONSULTANT represents that it has thoroughly reviewed the Work and the
General Services Agreement and that it accepts the Work and the conditions under which the Work is to
be performed.
Schedule: The Schedule shall be set forth in Section B of this Work Order. CONSULTANT represents
that the Schedule is reasonable and achievable.
Payment Terms: Payments to the CONSULTANT shall be as described in Section C of this Work Order.
Terms and Conditions. The terms and conditions of the General Services Agreement referenced above
shall apply to this Work Order. This Work Order also incorporates, in Section D, all the terms and
conditions required to be included in it by the General Services Agreement.
OWNER: CONSULTANT:
Jeffersonville Sewer Board Jacobi,Toombs, and Lanz, LLC
Jeffersonville, Indiana 1829 E. Spring Street
500 Quartermaster Cou New Albany, IN 47150
Jeffersonville, Indiana 130 812) 945-9585
812) 285-6400
G
By By HarrsTl
Mayor Mike oore, President Michael C. Harris, P.E.
President
pfk DarbyByWbtnessJoshDary(Jan 16, 2s 08:47 EST)
ale L. Orem, Member Josh Darby, P.E.
Construction Services Team Leader
By
William A. Saegesser, P..E. P.L.S., Member
WORK ORDER NO. 2025-1
SECTION A— DESCRIPTION OF THE WORK
Jacobi, Toombs and Lanz, LLC (JTL)shall provide Professional Engineering services for the project
described as follows:
Full Time Construction Administration and Inspection services for the Cherry Creek Pump Station
Replacement project, the GCCS New Middle School Sewer Service Extension project and the SR 62 Low
Pressure Sewer Extension project. Since all three projects follow a similar timeline, we propose to supply
one full-time Inspector that will cover all three projects concurrently. These services will include.
Provide a full time Owner's Resident Project Representative (Inspector)who will remain on-site to
observe the Contractor's Construction Activities to ensure that all items are being performed and
constructed in accordance with the contract documents. Inspector will prepare and submit Daily
Inspection Reports and Weekly Inspection Summaries to document the work. Inspector will also
measure installed quantities of all pay items for tracking and progress payment.
Review and approve or take other appropriate action in respect to Shop Drawings, Samples and
other data that Contractor is required to submit to Owner with respect to Work designed or
specified by the Engineer, but only for conformance with the information given in the contract
documents and compatibility with the design concept of the completed project as a functioning
whole as indicated by the contract documents. Such reviews and approvals or other action shall
not extend to means, methods, techniques, sequences, or procedures of construction or to safety
precautions and programs incident thereto. Engineer shall meet any Contractor's submittal
schedule that the Owner has accepted.
Make recommendations to Owner concerning special inspections or tests of the work as deemed
reasonably necessary, and receive and review all certificates of inspections, tests, and approvals
required by the contract documents. Engineer's review of such certificates will be for the purpose
of determining that the results certified indicate compliance with the contract documents and will
not constitute an independent evaluation that the content or procedures of such inspections,
tests, or approvals comply with the requirements of the contract documents. Engineer and
Owner shall be entitled to rely on such inspections, tests and approvals.
Assist Owner in review of Pay Applications and the accompanying supporting documentation.
Assist Owner in determining the amounts that Owner will recommend that Owner pay to
Contractor.
Assist Owner in conducting a final visit to the site to determine if the completed work is
acceptable so that Engineer may recommend to Owner, in writing,that final payment by made to
Contractor with respect to such work.
Engineer shall not be responsible for the acts or omissions of any Contractor, Subcontractor,
Supplier or of any other individuals or entities performing or furnishing any of the work, for safety
or security at the Site, or for safety precautions or programs incident to the work, during the
construction phase or otherwise. Engineer shall not be responsible for failure of any Contractor
to perform or furnish the Work in accordance with the contract documents.
Engineer shall not be responsible or held liable for failure of any Contractor, Subcontractor, Utility
Company or any other entity performing work related to this project, to perform or furnish the
Work in accordance with the Contract Documents or any schedules set forth within or outside
those documents.
SECTION B—SCHEDULE
The construction period for the Cherry Creek Pump Station Replacement project has been defined as 150
calendar days. The construction period for the GCCS New Middle School Sewer Service Extension
project has been defined as 90 calendar days. The construction period for the SR 62 Low Pressure
Sewer Extension project has been defined as 30 calendar days 6 months are being budgeted for the
inspection under this work order in case the schedules do not exactly align.
SECTION C— PAYMENT TERMS
Payment to the CONSULTANT for Construction Administration and Inspection Services shall be on a time
and materials basis, based on the JTL hourly billing rates current at the time that work is completed, for a
fixed, not to exceed sum of $150,000.00. The JTL 2024 hourly billing rates are being attached for
reference. The JTL 2025 hourly billing rates will be provided once available.
The CONSULTANT may submit monthly invoices for payment for work completed to date.
Exceeding Estimated Fees: The estimated total fees shown herein are based on the description of work
described in this agreement. The CONSULTANT reserves the right to request an adjustment to the
estimated total fees, if necessary, as a result of scope changes or schedule adjustments that are outside
the CONSULTANT'S control.
JACOBI, TOOMBS AND LANZ, LLC.
2024
HOURLY BILLING RATES
STANDARD
HOURLY BILLING
CODE CLASSIFICATION RATE*
PR2 PRINCIPAL- PRESIDENT 225
PRI PRINCIPAL -VICE PRESIDENT 210
PM3 PROJECT MANAGER III 170
PM2 PROJECT MANAGER II 155
PM1 PROJECT MANAGER I 145
DL DISCIPLINE LEADER 230
E6 ENGINEER VI 190
E5 ENGINEER V (PE) 175
E4 ENGINEER IV (PE) 160
E3 ENGINEER III (PE) 145
E2 ENGINEER II (PE) 130
El ENGINEER I (PE) 115
ET4 ENGINEERING TECH IV (EIT) 100
ET3 ENGINEERING TECH III (EIT) 90
ET2 ENGINEERING TECH II 80
ETI ENGINEERING TECH I 70
CT3 CAD TECH III 110
CT2 CAD TECH II 95
CT1 CAD TECH I 80
LS2 LAND SURVEYOR II (LS) 130
LS1 LAND SURVEYOR I (LS) 120
SC SURVEY CHIEF 95
ST2 SURVEY TECHNICIAN II 85
STI SURVEY TECHNICIAN I 75
RCM RESIDENT CONSTRUCTION MANAGER 130
RP RESIDENT CONSTRUCTION REPRESENTATIVE 115
RI RESIDENT INSPECTOR 100
CL CLERICAL 75
PL3 PLAN REVIEWER III 120
PL2 PLAN REVIEWER II 105
PLl PLAN REVIEW I 90
GPS GPS 50
RTS ROBOTIC TOTAL STATION EQUIPMENT 50
ATV/UAS ATV/DRONE: DAILY RATE 125
EXP MILEAGE: PER MILE Current federal mileage rate
Overtime will be charged at 1.25 times the standard billing rate.
Serving as an expert witness in legal proceedings will be charged at 2 times the standard billing rate.
These rates may be adjusted on an annual basis as required by economic factors at the discretion of Jacobi, Toombs and Lanz, Inc.
JACOBI, TOOMBS AND
LANZ, LLC CONSTRUCTION ADMIN I INSPECTION FEE JUSTIFICATION
PROJECT NO.: 24057
DESCRIPTION: Cherry Creek PS Replacement, GCCS New Middle School Jeffersonville Sewer Board
Sewer Extension, SR 62 Low Pressure Sewer Extension
PERSONHOURS BY CLASSIFICATION TOTAL TOTAL
DESCRIPTION PM Ill RCM Regular HOURS DOLLARS
Darby) Layton)TASK /TASK
O $
Full-Time Inspection (6 Months, 40 Hours Per
Week) 960 960 $ 124,800.00
0 $
Project Management/Coordination, Shop Drawing
Reviews,Pay Applications,Progress Meetings,RFIs,
Site Observation,etc.(6 Months,6 Hours PerWeek)
144 144 $ 24,480.00
O $
0 $
O $
0 $
0 $
O $
TOTAL HOURS 0 144 0 960 0 0 0 0 1,104 $ 149,280.00
STANDARD HOURLY RATE 170.00 130 00
TOTAL COSTS S - S 24.480 00 S 5 124.800 00 $ - S - $ - S - 149,280.00
TOTAL FEE:149,280.00
Y.\Shared\JTL\Protects\Active\24057-Cherry Creek Pump Station Replacement\Proposal\24057-Inspedtiorkf8pmtrrlrour Justification