HomeMy WebLinkAboutChange Order #3 for CCMG 2023-2 Street Paving Project CHANGE ORDER- EXTRA WORK AGREEMENT NO. 3 JOB NO. 24012
Project Name Jeffersonville CCMG 2023-2 Street Paving Project
Contractor Libs Paving Co., Inc.
You are hereby authorized to proceed with the following described change or extra work associated with the
addition of repaving of Walpole Avenue from Martha Avenue to Ewing Lane:
1. Mobilization/ Demobilization: 1 LS @$550.00/LS = $ 550.00
2. Maintenance of Traffic: 1 LS @ $500.00/LS = $ 500.00
3. Asphalt Milling: 1,806 SYD @$0.85/SYD = $ 1,534.72
4. PIMA Surface,Type B (Assume 165 LB/SY)(1.5 Inch): 164 TON @$70.00/TON = $ 11,480.00
5. Stop Bars,Thermo:24 LF @$10.00/LF = $ 240.00
TOTAL = $ 14,304.72
The method of payment for this change or extra work shall be:
An additional amount of Fourteen thousand three hundred four dollars and seventy two cents= $14,304.72
Consulting Engineer: Jacobi, Toombs and Lanz,Inc.
6-5-2024
E gineer'sgnatu Date
Owner's Appro aI: Jefferson•' Board ofPublic Works and Safety
Signature of Owner(s) Date
Con actor's Approval: Lib aging Co., Inc.
(RwN 76/2._el
Authorized Representative Title Date
Y:LShared11TL\ProjcctsWctive\240I2-Jeffersonville CCMO 2023-2 Paving Project\Documents\24012 Change Order 3-Walpole from Martha to Ewing