HomeMy WebLinkAboutMAC Construction Change Order No.1 for Jeff CCMG 2024-1 Street Paving Project (BBPW approved 10/23/24) CHANGE ORDER- EXTRA WORK AGREEMENT NO. 1 JOB NO. 24017
Project Name Jeffersonville CCMG 2024-1 Street Paving Project
Contractor MAC Construction&Excavating, Inc.
You are hereby authorized to proceed with the following described extra work associated with milling and paving of
Falcon Rd. &Meadowland Dr.:
As per attached documentation:
1. Mobilization/Demobilization = $ 8,637.00
2. Maintenance of Traffic = $ 5,000.00
3. Asphalt Milling/Cleaning _ = $ 2,016.00
4. HMA Surface,Type B (Assume 165 LB/SY)(1.5 Inch) = $ 11,725.00
TOTAL = $ 27,378.00
The method of payment for this change or extra work shall be:
An additional amount of Twenty seven thousand three hundred seventy eight dollars and no cents= $27,378.00
Consulting Engineer: Jacobi, Toombs and Lanz, Inc.
f� 10-21-2024
•
ngineer's signature Date
Owner's Approval: Jeffersonv'le .. • of Odic Works and Safety
10 •a�-a
Signature of Owner( Date
Contractor's Approval: MAC Construction&Excavating, Inc.
'vc Project Manager 10/17/24
Authorized Representative Title Date
Y:\SharedUTL\Projects\Active\24017-Jeffersonville CCMG 2024-1 Paving Project\Documents\24017 Change Order 1-Paving Falcon Rd and Meadowland Dr.xls
BID PROPOSAL
=MAC
CONSTRUCTION MAC CONSTRUCTION & EXCAVATING, INC.
1908 UNRUH COURT
NEW ALBANY,IN 47150
Contact: Ted Newton
Phone: 239-877-8809
Email: tedn@macconstruction.com
Quote To: Kevin Morlan Job Name: Jeffersonville CCMG 2024-1 Paving
Street Commissioner C.O.#1 -Falcon Rd/Meadowland Dr.
Job# 124229
Phone: 812-285-6455
Email: kmorlan@cityofjeff.net Engineer: Jacobi Toombs and Lanz
ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE AMOUNT
10 MOBILIZATION/DEMOBILIZATION 1.00 LS 8,637.00 8,637.00
20 MAINTENANCE OF TRAFFIC 1.00 LS 5,000.00 5,000.00
30 ASPHALT MILLING/CLEANING 2,100.00 SYD 0.96 2,016.00
40 HMA SURFACE,TYPE B(ASSUME 165 LB/SY) 175.00 TON 67.00 11,725.00
(1.5 INCH)
GRAND TOTAL $27,378.00
NOTES:
1. All fuel and asphalt prices are subject to a price adjustment using the formulas of calculation per the Kentucky 2008
Standard Specifications for Road and Bridge Construction.
2. MAC excludes permits,bonds,testing,rock excavation,handling or disposal of contaminated materials,relocation of
existing utilities,and any applicable fees.
3. Bid is based on normal work hours.
4. MAC excludes undercut and refill.
Page 1 of 1