HomeMy WebLinkAboutLochmueller Group Amendment No. 2 City of Jeffersonville
Government Contract Coversheet
Please note: All information MUST be completely filled out and submitted to Clerk's Office
within 48 hrs of execution.
Date Submitted to Clerk: 6/20/2024
Department: Wastewater
Vendor Name: Lochmueller Group
Sign Date: 6/20/2024
Ending Date: 12/31/2024
Amount of Original Contract: $75,000
Is this an amendment or change order
to original contract?
Amended Contract Amount: $225,000
Purpose:
This is Amendment 2 to Task Order 1 for
General Engineering Services
For Clerk's Office to fill out
Date uploaded to Gateway: tililo?ribyl
LOCHMUELLER
GROUP
331 Quartermaster Court,Jeffersonville,Indiana 47130-3623
AMENDMENT No. 2 TO TASK ORDER No. 1
This Amendment No. 2 to Task Order No. 1 is an amendment to and made part of the Master
Agreement dated April 19, 2023, by and between the City of Jeffersonville, hereinafter referred to as
"CLIENT" and Lochmueller Group, Inc., hereinafter referred to as "CONSULTANT". This Amendment No.
2 to Task Order No. 1 presents the scope of services, costs, and schedule.
W ITNESS ETH
WHEREAS, the CLIENT and CONSULTANT did on May 4, 2023, enter into Task Order No. 1 to provide "as-
needed" general services for the CLIENT, and
WHEREAS,the CLIENT desires to continue to provide services, and
WHEREAS, in order to compensate CONSULTANT to continue to provide additional services, it is
necessary to amend and supplement the original Task Order, and
NOW THEREFORE, it is agreed by and between both parties that Task Order No. 1 be amended as
follows:
I. Item C. PAYMENT of Task Order No. 1 is modified as follows:
CONSULTANT shall receive compensation for providing the services set forth on page 1 of the General
Services Agreement on an hourly rate basis in accordance with the hourly rate schedule attached hereto
as Exhibit "1" and incorporated herein by reference. The total fee shall not exceed Two Hundred
Twenty-Five Thousand Dollars ($225,000.00) unless an Amendment to this Task Order is approved in
writing by both parties.
Except as herein modified, changed and amended, all terms and conditions of the original General
Agreement dated April 19, 2023, Task Order No. 1 dated May 4, 2023, and Amendment No. 1 to Task
Order No. 1 dated September 21, 2023, shall continue in full force and effect.
This Amendme o. 2 to Task Order No. 1 increases the initial not-to-exceed total of $150,000.00
by$75,000 0 '• - new not-to- ceed total of$225,000.00.
CITY OF JEF E '• ILLE LOCHMUELLER G OUP, INC.
Mike Mo re v . of
Mayor Regional Leader-Southern Indiana
Date: JCJi1-( 2-0/ `1-t) 2.--If Date: June 18, 2024
CITY OF JEFFERSONVILLE 1 of 1 AMENDMENT 2 TO TASK ORDER 1
2024-06-1eaM 2 ro TO 1 wrr1 Cm.00c 123-2010-01 W
EXHIBIT "1"
LOCHMUELLER.
GROUP
2024 INDIANA HOURLY RATE SCHEDULE
ENGINEERING, ENVIRONMENTAL,SURVEYING AND PLANNING SERVICES
CLASSIFICATION HOURLY RATE CLASSIFICATION HOURLY RATE
Senior Project Manager II-IV $305 Environmental Specialist IV $193
Senior Project Manager I $257 Environmental Specialist III $176
Senior Engineer II $249 Environmental Specialist II $138
Senior Engineer I $247 Environmental Specialist I $104
Project Engineer IV $206 Environmental Technician II $106
Project Engineer III $197 Environmental Technician I $102
Project Engineer II $160 Environmental Geologist $171
Project Engineer I $152 Historian/Section 106 Specialist IV $178
Engineering Intern III $134 Historian/Section 106 Specialist III $162
Engineering Intern II $122 Historian/Section 106 Specialist II $131
Engineering Intern I $116 Historian/Section 106 Specialist I $91
Engineering Designer IV $202 Certified Construction Engineer III $197
Engineering Designer III $157 Certified Construction Engineer II $168
Engineering Designer II $148 Certified Construction Engineer I $127
Engineering Designer I $122 Certified Construction Project Supervisor II $190
Engineering Technician III $148 Certified Construction Project Supervisor I $147
Engineering Technician II $109 Certified Construction Inspector II $142
Engineering Technician I $90 Certified Construction Inspector I $110
IT System Specialist $233 Transportation Planner IV $184
Project Liaison $184 Transportation Planner III $140
Senior Trans Planner II $241 Transportation Planner II $120
Graphic Designer $152 Transportation Planner I $94
Senior Landscape Architect I $242 Senior Appraiser $220
Landscape Architect $140 Right of Way Services Specialist $178
Professional Surveyor IV $212 Realty Specialist $131
Survey Party Chief III $146 Real Estate Buyer $89
Survey Party Chief II $121 Manager Administrative Services $144
Survey Party Chief I $107 Administrative Assistant $107
Survey Technician $87 Student Intern $76
TRAVEL TIME for survey crews will be charged both directions from door-to-door.
OVERTIME work will be performed only at the direction of the client. All work on survey crews, drafting or clerical over eight hours per day or work
performed on weekends or holidays is considered overtime and will be billed at 1.25 times above quoted rates.
CONSTRUCTION LAYOUT: Contractors shall verify construction layout stakes and notify the surveyor of any discrepancies prior to construction.
DIRECT EXPENSES will be charged to the client in addition to the above quoted rates. Mileage will be charged at the allowable federal mileage
reimbursement rate at the time the mileage was incurred. Direct expenses include but are not limited to: mileage, filing fees, testing, express mail
costs,etc. provided that they are reasonable and necessary for the accomplishment of the work.
These rates may be changed on an annual basis at the discretion of Lochmueller Group,Inc.
HTTPS.//LOCHGROUP-MY.SHAREPOINT.COM/PERSONAL/TAYLOR_OECORREVONT_LOOWROUP_COM/DOCUMENTS/DESKTOP/2024 HOURLY RATES WORKING/COMPANY WIDE/2024 INDIANA HOURLY RATES.DOC EW