HomeMy WebLinkAboutCHANGE ORDER 3 GOTTBRATH PARKWAY CHANGE ORDER-EXTRA WORK AGREEMENT NO. 3 JOB NO. 16031I2
Project Name Gottbrath Parkway Phase II
Contractor Excel Excavating,Inc.
You are hereby authorized to proceed with the following described change or extra work:
As per attached documentation:
1 Add 115 Days to the Contract Completion Period,Resulting in a Revised Contract Substantial Completion Date of November 25,2019
The method of payment for this change or extra work shall be:
No additional payment shall be made. This Change Order only revises the Contract Completion Date
Consulting Engineer: Jac . Toombs d Lanz,Inc.
Engineer's Signat Date
Owner's Approval: City ofJe rsonville 7 3l//I
Signature of Owner(s) ate
Con . or's A ,val: Excel Excavating,Inc.
Authorized ep esentative Tit e I ate
Page 1 of 1
Gottbrath Parkway Phase II
City of Jeffersonville, Indiana
JTL Job No. 16031I2
7/31/2019
Summary of Construction Delay Days
Delay Days Due to Unsuitable Subgrade Issues = 55 days
From Date Contractor Began Placing Fill Over Shot Rock (5/10/19)to
Date Change Order was Approved and Direction for Remediation was
Given (7/3/19)
Delay Days Due to City Shut Down of Project Due to Sanitary Sewer Permit = 1 day
Issues
Delay Days Due to Additional Erosion Control Measures Directed by the = 13 days
City/IDEM
• 12/19/18 - 4 hrs
• 2/8/19 - 2 hrs
• 2/21/19 - 4 hrs
• 2/28/19 - 8 hrs
• 3/5/19 - 2 hrs
• 3/19/19 - 5 hrs
• 3/20/19 - 8 hrs
• 4/17/19 - 1 hr
• 5/2/19 - 0.5 hr
• 6/17/19 - 3 hrs
• 6/24/19 - 1 hr
• 6/25/19 - 2 hrs
• Pump Around Flow Diversion - 60 hrs
109.5 hrs = 13 days
Delay Days Due to Delayed Response by Patriot Regarding Shot Rock Limits. = 28 days
Contractor Requested Guidance On 1/11/19, Did not Receive Direction
Until 2/8/19
Delay Days Due to Excessive Inclement Weather = 18 days
INDOT Specifications Estimate 65 Inclement Weather Days from
January Through July. 83 Inclement Weather Were Recorded from
Start of Work to Original Contract Completion Date.
Total Construction Delay Days to Date = 115 days