HomeMy WebLinkAboutPRIMROSE DRAINAGE TRC, LLC PO Box 273, Floyds Knobs, IN 47119
structural concrete, precast erection, carbon fiber strengthening, concrete rehabilitation, piling
April 30, 2019
Doug Hayden
City of Jeffersonville
2003 Renfroe Way,Suite 300
Jeffersonville, IN 47130
Re: Primrose Drainage Improvements
Dear Mr. Hayden,
We are pleased to provide to you a quote including all necessary labor,equipment,form materials and supervision
for the following scope per the plan sheet 1 of 1,dated 4/4/19:
• Furnish& Install+/-234 If of 36-in HDPE Pipe.
• Furnish& Install +/-78 If of 24-in HDPE Pipe.
• Furnish& Install (2)Catch Basins.
• Form& Pour Concrete Headwalls.
• Import fill material for over pipes and regrade ditch.
• Patch road with 8-in concrete and 1-1/2-in asphalt.
• Patch Curb and Sidewalks.
• Seed and place straw blanket on disturbed areas.
• Maintenance of Traffic—Assume Road Closure for Pipe Installation.
• LUMP SUM PRICE $61,885.00
Notes:
• No sales tax.
• No relocation of existing utilities.
• No testing,permits or fees.
• No haul off or disposal of hazardous materials.
• We include haul off and disposal of as necessary.
• No engineering.
• No retainage to be held.
• Work to be completed as non-union contractor.
• No overtime included.
• No bond included. If necessary add 2.0%to total contract.
• TRC needs 30 days-notice to schedule start of work.
Thank you for the opportunity to quote this scope of work to you. Should you have . 1 questio . or comments
please feel free to contact me.
Thank you, Accepted By F 'ity of Jeffer•.nville:
Signed:
Bryan Cavan
Project Manager Printed:
Dated:
Equal Opportunity Employer