HomeMy WebLinkAboutCHANGE ORDER CRUMS LANE CHANGE ORDER-EXTRA WORK AGREEMENT NO. 1 JOB NO. 17012
Project Name Crams Lane#2 Pump Station Replacement
Contractor Dave O'Mara Contractors
You are hereby authorized to proceed with the following described change or extra work:
Final Installed Quantity Adjustment-.
1 Add Quantity to Pay Item No. 13 Concrete Sidewalk 4 SY @$275.00/SY = $ 1,100.00
2 Delete Quantity from Pay Item No.14 Concrete Roll Curb:4 LF @$52.00/LF = $ (208.00)
3 Delete Quantity from Pay Item No. 15 Concrete Driveway Apron: 13 SY @$140.00/SY = $ (1,820.00)
4 Delete Quantity from Pay Item No.20 Seeding. 123 SY @$6.00/SY = $ (738.00)
5 Delete Quantity from Pay Item No.21 Unidentified Rock Removal: 10 CY @$175.00/CY = $ (1,750.00)
6 Delete Quantity from Pay Item No.22 Undercut/Stabilization of Unsuitable Subgrade:10 CY @$50.00/CY = $ (500.00)
7 Delete Quantity from Pay Item No.23 Unidentified Conflict Contingency:0.91036 LS @$25,000/LS = $ (22,759.00)
TOTAL = $ (26,675.00)
The method of payment for this change or extra work shall be: '
A contract reduction in the amount of Twenty Six thousand six hundred seventy five dollars and no cents =$26,675.00
Consulting Engineer. acob��• `.sand
1 • .eer's Sign:
Date
Owner's Appro City offe: 'nville
-- /221)/18
Signature of Owner .) Date
Contractor's Approval: Dave O'M Contractors
sre=C-FT. 1 Lam,- ! � ,,. G • ,.•s.•s /2-14'-/'g .
Authorized Representative V, J Tide `
Date
Page 1 of 1