HomeMy WebLinkAboutAGREEMENT WITH JRC SECTION B-2 AGREEMENT BETWEEN OWNER AND CONTRACTOR AGREEMENT THIS AGREEMENT, made this y day of Oc Tcxp2- 2018, by and between the Jeffersonville Redevelopment Commission, hereinafter called "OWNER" and Excel Excavating, Inc., doing business as a corporation hereinafter called"CONTRACTOR", WITNESSETH: That for and in consideration of the payments and agreements hereinafter mentioned: 1. The CONTRACTOR will commence and complete the Gottbrath Parkway Phase 2 Project. 2. The CONTRACTOR will furnish all of the material, supplies, tools, equipment, labor and other services necessary for the construction and completion of the PROJECT described herein. 3. The CONTRACTOR will commence the work required by the CONTRACT DOCUMENTS within 10 calendar days after the date of the NOTICE TO PROCEED and will reach substantial completion by August 2, 2019 unless the period for completion is extended otherwise by the CONTRACT DOCUMENTS. 4. The CONTRACTOR agrees to perform all of the WORK described in the CONTRACT DOCUMENTS and comply with the terms therein for the sum of $1,999,482.00 based on the unit prices in the BID schedule. B-202 5. The term "CONTRACT DOCUMENTS" means and includes the following: (A)NOTICE TO BIDDERS (B)INFORMATION FOR BIDDERS (C)BID (D)BID BOND (E)AGREEMENT (F) GENERAL CONDITIONS (G)PAYMENT BOND (H)PERFORMANCE BOND (D NOTICE OF AWARD (J) NOTICE TO PROCEED (K)CHANGE ORDER (L)DRAWINGS prepared by Jacobi, Toombs&Lanz, Inc., dated August 2018 (M) SPECIFICATIONS prepared by Jacobi, Toombs & Lanz, Inc. dated August 2018 (N) ALL ADDENDA 6. The OWNER will pay to the CONTRACTOR in the manner and at such times as set forth in the "General Conditions" such amounts as required by the CONTRACT DOCUMENTS, provided that work is satisfactorily completed, and same is certified in writing,to the OWNER, by CONTRACTOR and ENGINEER. 7. The CONTRACTOR must pay its subcontractor for satisfactory performance no more than 30 days from the prime contractor's receipt of payment from the OWNER. B-203 8. This Agreement shall be binding upon all parties hereto and their respective heirs, executors, administrators, successors, and assigns. 9. This Agreement may be terminated by either the OWNER or the CONTRACTOR, with or without cause, upon a thirty (30) day written notice to the other party. If the Agreement is so terminated, the Contractor shall be entitled to its contractual compensation for all work performed up to the termination date. In WITNESS WHEREOF, the parties hereto have executed, or caused to be executed by their duly authorized officials, this Agreement in (triplicate) each of which shall be deemed original on the date first above written. OWNER: Jeffersony.}lle Redevelopment Commission sr~� BY: / I / Gyt.-` Name: /it I ( 4 Title: II�NS✓G�� gra : Date: /6/`/`/, (SEAL) AT. .T/ • BY:ill i., 1 ,1 / Iry� A r'7EINa ! �t,t, Title: _ t, if l 4 j B-204 CONTRACTOR Excel Excavating, nc. ,``001111lbw BY: 4011A,01,`e cel Exe ,,„ _46 �i�•• ••.♦Lp idr.1 Name:ul�waw 4, CORP() �'"' Title:J.?Za;•. v Address:ni,e *nal 664.61641694 ,_ 1te Iff ••.,�y • . �� Date: to icdizol$ Ateff. ...... (g�11111111���rated o�N °, ATTEST: S—NamBY: `»CS— Name: e: Nte. r'44►4.P.s••1 Title: Id tee, (yo•Z Za) Waal B-205