AMENDMENT No. 1
THIS AMENDMENT NO. 1 IS MADE AND ENTERED INTO THIS , BY AND
BETWEEN THE CITY OF JEFFERSONVILLE, INDIANA, HEREINAFTER REFERRED TO AS THE "OWNER" AND
LOCHMUELLER GROUP, INC., HEREIN AFTER REFERRED TO AS THE"CONSULTANT".
WITNESSETH
WHEREAS, the OWNER and CONSULTANT did on November 16, 2017 enter into an Agreement to
provide services for the Downtown Wastewater Treatment Plant Blower Improvements project, and
WHEREAS,the location of the blower system has changed to the existing digesters, and
WHEREAS, due to the change in location of the blower system, architectural design and additional
mechanical design services will be required, and
WHEREAS, OWNER desires CONSULTANT to provide the additional services, and
WHEREAS, CONSULTANT has expressed an interest to provide the additional services,and
WHEREAS, in order for CONSULTANT to provide the additional services, it is necessary to amend the
original agreement, and
NOW, THEREFORE, it is agreed by and between both parties that the original agreement be amended as
follows:
I. Item 2.3.5 is added to Item 2.3 of Appendix"A"as follows:
2.3.5 Architectural
II. The date of completion for the 100% Final Design Submittal to OWNER in Appendix "C" is
modified to read July 31,2018.
III. Item 1.1 of Appendix"D" is modified to as follows:
1.1 The CONSULTANT shall receive as compensation for providing the services set forth in
Appendix "A" of this Agreement a total lump sum fee of One Hundred Thirty One
Thousand Nine Hundred Fifty Dollars ($131,950.00), unless a modification of the
Agreement is approved in writing by both parties.
IV. Item 1.2.1 of Appendix"D"is modified to as follows:
1.2.1 Design Phase $111,350.00
CITY OF JEFFERSONVILLE Page 1 of 2 AMENDMENT NO. 1
W:\ACCNTING\CON TRACT\IEFFER50NVILLE\2170519 DOWNTOWN WWI'?BLOWER IMPROVEUFFFERSONVILLE\AMENDMENT NO I WITH CITY 072518 DOC 217-519-0W W
Except as herein modified, changed and supplemented, all terms of the original Agreement dated
November 16, 2017 shall continue in full force and effect.
The previous lump sum fee total was $98,600.00. This Amendment No. 1 increases the original value by
$33,350.00 to a new lump sum fee of$131,950.00.
IN TESTIMONY WEHREOF,the parties hereto have executed this Agreement.
LOCHMUELLER GROUP,INC. CITY OF JEFIIER ON ILLE
Patricia Yount Mike Moore
Branch Manager—Se for A sociate Mayor
CITY OF JEFFERSONVILLE Page 2 of 2 AMENDMENT NO. 1
WMCCMING\CONTNACT\IEFFERSONVHLEU170519 DOWNTOWN WWTP BLOWER IMPROVE UFFFERSONVILLE\AMENDMENT NO 1 WITH CITY 07251B.D0C 217-519-OW W