HomeMy WebLinkAboutTSI CHANGE ORSER #1 NEW CHAPEL SIDEWALKS PHASE 2 CONSTRUCTIONnfc.
July 24,2018
Mr.Josh Darby,P.E.
JTL Engineers
1829 E. Spring Street,#201
New Albany,IN 47150
Re: New Chapel Sidewalks,Phase 2
Request for Change Order#1
Dear Mr. Darby;
Per our earlier requests and conversations,TSI hereby requests a Change Order for the following
revisions and changes in scope of work on the above referenced project. Please note the following items:
A.
• Revisions in pedestrian bridge supports. TSI proposes to eliminate the poured in place piers,
including the excavation,backfill, erosion control, shoring, etc,and replace it with a driven pile
alternate. This includes the following:
• Stamped engineering drawings. (Indiana Stamp).
• HP 12x53 piles with points driven with vibratory hammer on excavator. (4) piles each bent, (2)
battered and (2)vertical.
• Reinforced concrete bents+/-2 ft wide x 3 ft tall x 16 ft long.
• Set bridge with bearings as shown on original drawings.
• Pour deck as shown on original drawings
If approved,the Indiana P.E. will provide the engineered drawings to JTL for final approval.
Total Credit for this item---$21,000
B.
Change the Keystone type walls with geogrid reinforcing to a stand alone Redi-Rock design(approved
by JTL prior to Bid). Locations,elevations, etc,remain the same. A complete submittal on this type of
wall has been attached to this letter.
Total Credit for this item----$ 67,600
Total Request for Change Order#1-----Credit$88,600
Respectfully submitted;
Dennis Coffman,Operations Manager
TSI CONSTRUCTION, INC. Post Office Box 1540, New Albany, Indiana 47151-1540
2325 Green Valley Road, Suite#103, New Albany, Indiana 47150 Phone 812.948.6691 Fax 812.948.0266
www.tsiconstructioninc.com
CHANGE ORDER-EXTRA WORK AGREEMENT NO. 1 JOB NO. 17108
Project Name New Chapel Sidewalk Phase II
Contractor TSI Construction,Inc.
You are hereby authorized to proceed with the following described change or extra work:
As per attached documentation:
1 Revise Modular Concrete Retaining Wall Supplier to Redi-Rock(Reduces Required Exavation and Geogrid) = $ (55,600.00)
2 Delete Quantity from Item No.26 HMA Over Concrete Pavement Patch:150 SY @$80.00/SY = $ (12,000.00)
3 Revise Prefabricated Pedestrian Bridge Foundation System = $ (21,000.00)
TOTAL = $ (88,600.00)
The method of payment for this change or extra work shall be:
An contract reduction in the amount of Eighty eight thousand six hundred dollars and no cents =$88,600.00
Consulting Engineer: Jacobi, 7..mbs and Lanz,Inc.
• 7-ato—t
,ngineei s Signature Date
Owner's Approval: City ofJe etson•.e
Signature of Owner(s) Date
Contractor's Approval: T,F.r Const .c.
`'L -./f 1-tae,Gv 7-2(n -18
l
Authorized Representative Title Date