HomeMy WebLinkAboutUTICA PIKET DRAINAGE IMPROVMENTS AT PERRIN POINT 2 TRC, LLC PO Box 273, Floyds Knobs, IN 47119
structural concrete, precast erection, carbon fiber strengthening, concrete rehabilitation, piling
March 14, 2018
Matt Bell
City of Jeffersonville
2003 Renfroe Way,Suite 300
Jeffersonville, IN 47130
Re:Utica Pike Drainage Improvements
Dear Mr. Bell,
We are pleased to provide to you a quote including all necessary labor,equipment,form materials and supervision
for the following scope per the drawings dated February 8,2018:
• Furnish& install+/-402 If of 12-in SDR 35 PVC.
• Furnish&Install(2)Catch Basins.
• Tie-in existing catch basin.
• Patch driveway with DGA and concrete patch.
a Maintenance of Traffic.
• Cleanup and mulched seeding. )
• LUMP SUM PRICE $28,920.00
Notes:
• No sales tax.
• No relocation of existing utilities.
• No testing,permits or fees.
• No haul off or disposal of hazardous materials.
• We include haul off and disposal of as necessary.
• No layout or engineering.
• No erosion or sediment control.
• No retainage to be held.
• Work to be completed as non-union contractor.
• No overtime included.Work to be completed on normal 40 hour work weeks.
• No bond included. If necessary add 2.0%to total contract.
• TRC needs 30 days-notice to schedule start of work.
Thank you for the opportunity to quote this scope of work to you. Should you have any questions or comments
please feel free to contact me
Thank you, Accepted By For City of Jeffersonville:
Signed: � �✓� /� 1„,
1 n Cavan
Project Manager Printed: -DALE ORFM
Dated: V.
Equal Opportunity Employer