HomeMy WebLinkAboutCHANGE ORDER CEDARVIEW PUMP STATION CHANGE ORDER-EXTRA WORK AGREEMENT NO. 1 JOB NO. 16016
Project Name Cedarview Pump Station Replacement
Contractor Clark Nickles,Inc.
You are hereby authorized to proceed with the following described change or extra work:
As per attached documentation:
1 Install Additional Manhole per City of Jeffersonville Request = $ 2,350.00
2 Tree Removal per City of Jeffersonville Request = $ 1,500.00
3 Additional Dewatering as Required Due to Pound Site Conditions = $ 2,500.00
TOTAL = $ 6,350.00
The method of payment for this change or extra work shall be:
An additional amount of Six thousand three hundred fifty dollars and no cents =$6,350.00
Consulting Engineer: Jac . Toombs and Lana;Inc.
t _ � §V-1
Engine r s Signa Date
Owner's Approval: f ffe ontd!!e /oh-7-
a e Owner(s) Date
Contractor' 1j�p v QatkNickles,Inc. l/,7
Authorized Representative Title Date
Page 1 of 1
1501 Tunnel Mill Road
Charlestown,IN 47111
(812)256-3477 phone
(812)256-6074 fax
CLARK N ICKLS, INC.
COMMERCIAL EXCAVATION DEMOLITION CRANE He HEAVY EQUIPMENT RENTAL
BONDED&FULLY INSURED LICENSED DEMOLITION CONTRACTORS IN INDIANA&KENTUCKY
A Family Owned Business Since 1945
August 4,2017
Jacobi,Toombs and Lanz
1829 E. Spring
New Albany,IN 47150
Re: Cedar View#16016
Please accept this request for change order#1 on the Cedar View Project.
Install additional manhole per request of Marion Shepherd $2,350.00
Removal of trees $1,500.00
Dewatering $2,500.00
Total $6,350.00
Z
kk Nickles,Inc.
Cc: Marion Shepherd
CITY OF JEFFERSONVILLE
CEDARVIEW PUMP STATION REPLACEMENT JOB NO. 16016
ITEM UNIT DESCRIP'T'ION INSTALLED
NO. UNIT PRICE
1
IF 2"Force Main $ 36. 00
2 LF 8" PVC Gravity Sewer $ 52 . 00
3 EA Type C Manhole $ 2350. 00
4 TON HMA Surface,Type B $ 125 . O
5 TON HMA Intermediate, Type B $ 125. 0(
6 TON Compacted DGA,No. 53 $ 25. 00
7 SY Surface Milling, 1.5" Depth $ 7 . 50
8 LF Cedar Privacy Fence $ 110 . 0
9 LF 6" PVC Property Service Lateral _ $ 4 2 . 0
10 CY PCCP for Approaches $ 550. 00
.11 LF Safeload Ex. Sanitary Sewer $ 40 - 00
12 LS Dewatering $ 2500. 0 0
13 CY Undercut/Stabilization of Unsuitable Sub=grade35. 00
�f
C'T ARTK NTCKT FS, TNC_
Contractor
Unit Prices
For additions and deletions to the Contract, the above unit prices shall be applicable for the
specific items listed. Unit Prices shall be complete, in place including required labor, materials,
permits, equipment, implements, testing,parts and supplies necessary for, and incidental to
proper installation, as indicated on the Drawings, and in the Specifications.
1.The Contractor agrees that for requested and/or required changes in the scope of work,the
Contract Sum shall be adjusted in accordance with the following unit prices, where the Owner
elects to use this method of determining costs.
2. The Contractor is advised that the unit prices will enter into the determination of the
successful bidder. Unreasonable prices may result in rejection of the entire bid proposal.
A-207