HomeMy WebLinkAbout2013-No. 2 Lentzier Creek Div 1 CHANGE ORDER - EXTRA WORK AGREEMENT NO. 2 JOB NO. 12189
Project Name: Lentzier Creek Division 1- P.S., Gravity Interceptor & FM
Owner: Jeffersonville Sewer Board
Contractor: Mac Construction & Excavating
General Contract Additions
1 Creek Crossing #2 Pump Around Due to Creek Washout and Exposed FM Pipe $12,889.52
2 Lower 30" Sanitary Sewer Line Station 48 +48 to 66 +28 Due to Creek Washout $9,000.00
3 16" Bore & Jack Casing in Unidentified Rock 2OLF @ $190 /LF $3,800.00
4 Unidentified Rock Removal - 3,200 CY @ $150 /CY $480,000.00
5 Open Cut vs. Bore & Jack (See Attached Breakdown Comparison) Due to Unidentified Rock $63,883.20
Subtotal
$569,572.72
General Contract Deductions
1 Unidentified Rock Removal Credit for Increased Quantity 3,300 CY @ $30 /CY $99,000.00
$99,000.00
Increase in the amount of Four Hundred and Seventy Thousand Five Hundred and Seventy Two Dollars
and Seventy Two Cents $470,57232
Consulting Engineer: Jacob: Toombs & Lanz, la .
?--- A 6 (1S1 ti3
Engineer's Signa re Date
Owner's Approval: Jeffers° isle ' •w t oard a rd
6131" 8 - ls -
Signature of Ow er(s) D
Contractor's Approval: Mac • ruction : Excavat"' :
/ ,?,:::,- ) /3/..
Authorized Reprees tiEa ' e Signature / Date