CONTRACT CHANGE ORDER FORM
TO: Pace Contracting CONTRACT CHANGE ORDER NO.: 2
DATE: 11/28/2011
PROJECT NAME: Tenth Street Pump Station Expansion Pro ect
ORIGINAL. CITY P.O. NO.:
I. You are directed to make the following changes to this Contract:
I TEM AMOUNT'S) SCHFDI /LED ADRIS7MENT f +) or ( -1 DAYS
1. Grit Removal (FO 44) 61,502.00 No schedule adjustment
2. Pump ARVs (FO 17) 11,966.00 No schedule adjustment
3. Remove Crane (F0 19) 7,860.00 No schedule adjustment
4. Smart Building (F0 110) 23,327.00 No schedule adjustment
5. Unforeseen Cond. (FO 112) 7,758.00 No schedule adjustment
6. ARV Vault in Road (FO 416) 2,799.00 No schedule adjustment
7. FM Drains/Valves (FO 421) 79,156.00 No schedule adjustment
8. Flow Meters (FO 123) - 29,942.90 No schedule adjustment
9. Dismantling Joints (FO 027) 32,895.00 No schedule adjustment
1I. The following referenced documents further describe the changes outlined in Paragraph 1, and Ire
to be considered part of this Change Order:
F.O.: 14.07,09.410.412 116.021.123,027
111. The changes result in the following adjustment of Contract Price and Contract Time:
Contract Sum Prior to this Change Order $ 10.377.530.90
Contract Sum will be increase /decrease by this Change Order $ 197.320.10
New Contract Sum including this Change Order 5 10,574.35100
Contract Time Prior to this Change Order lune 7, 2012 Substantial Completion Date
Tuly 30.2012 Final Completion Date
Net increase /decrease resulting from this Change Order g Days
Current Contract Time including this Change Order lune 7.2017 - Substantial Completion Da e
h4y 30.2012 Final Completion Date
This Change Order is for full and final Settlement of all direct, indirect, impact costs and time extensio 1
incurred at any time resulting from the performance of the changed work.
•
Jeffersonville, Indiana Additional Forms Supplemental to Agreement Foam
Tenth Street Pump Station Lxpansinn 00 52 25
.
The Above Changes Are The Above Changes are Approved:
Recommended: Accepted:
C1-12M MI J. Pace Contracting 0 . terse. ' .
Engineer Contractor Owner
401 W. Main St, Ste 500 200 Willinger 1 ane 500 • , - master rt
Address Address Address
Louisville. KY 40202 - u .nville . , 0 efferso ndian, '130
City/State /Zip f'itylStale/ / • City /State/Zip
AA ( •
By: ,,.•. S1eaa By: �LL4� By:
Phone: Sfl.- 224 159t. Phone: 9f 2.-Z23- Sig & Phone:
Date: 11 (9.4 1 2A I Date: ff/L4lf/ Date: _
Jeffersonville, Indiana Additional Forms Supplemental to Agreement F. -m
Tenth Street Pump Station Expansion 00 5.25