HomeMy WebLinkAbout12-15-2011 8th Street Combined Sewer Separation Change Order 4 Job No. 10108 CHANGE ORDER - EXTRA WORK AGREEMENT NO. 4 JOB NO. 10 08 Project Name 8th Street Combined Scrum Separation Contractor TS. I Paving You are hereby authorized to proceed with the following described change or extra work: As per attached documentation: 1. Work at Ml I No. 16A at 8th and Walnut - Conflict Adjustments - 1 3,750.00 2. Work at \III No. 17A - Core new opening for pipe, rework invert - $ 801.55 3. Work at MH No. 18A - Cote two new openings for pipe, pour new inven - 5 ' ,960.75 4. Raise Pipe, Concrete Cap Sm. 32 +15 to 32 +56 = $ ,24200 5. Diffrmtoe in atone baackfi8 between old and new elevations from 32 +15 CO Sta. 36+36.42 (Deduct) = $ (1,30295) 6. Sanitary MH No. 7 - Core and connect active 6" tine into new MH No. 7 = $ 375.00 7. Install 89 LP of 12" RCP a $50 /1,1 instead of Slotted Vane Drain Pipe = 3 5.450.00 8. Deduct Installation of 103IP of Slotted Vane Drain Pipe = 3 (10.780.09) TOTAL = $ 496.26 The method of payment for this change or extra work shall he: An additional amount of Pour hundred ninety six dollars and twenty six cents = $496.26 An additional three days will also be added to the Contracted Project Completion Dam Consulting Iinginccr. Jacobi, Toombs and Lanz, Inc. Engineer's .: • / Dare Owner's Approval: Ci we e r� 12k 1 if Signature • Owner(s) 1)ace Contractofa Approval: TM Paring Authorized Representative 'fide Dam 4// // a • Page 1 of 1