HomeMy WebLinkAbout09-01-2011 Change Order no.2 8th Street Combined Sewer Separation Project CHANGE ORDER - EXTRA WORK AGREEMENT NO. 2 JOB N0.10108
Project Name: 8th Street Combined Sewer Separation Project
Owner: Jeffersonville Sewer Board
Contractor: TS! Paving
General Contract Additions
1 Fence and Driveway Modifications at Pfau Entrance along 8th Street (See Attached) $7,400.00
Subtotal $7,400.00
Total Change Order:
Increase in the amount of Seven- Thousand Four - Hundred Dollars and Zero Cents. $7,400.00
Consulting Engineer: Jacobi, Toombs & Lanz, Inc. Q / I l t1
Engineer's .ignatu e n Date
Owner's Approval: Jeffersonville Sewer B.. d �i
Signature ff Owner(s) . / Date
Contractor's Approval: 751 Paving 4,, /� //
Authorized Representative Signature / 0 e
ILljPaving Estimate
OUR LIST OF SERVICES GOES ON FM AILES
P.O. BOX 1540 Date Esumatei
NEW ALBANY, 1/4 47151
a 2&2OI I 226 -201
Name/ Address
City ofieffersonville
City of Jeffersonville
500 Quatermasta Court
Jeffersonville Indiana 47130
PHONE 812 - 948-6691
FAX 812 -948 -0266 Project
web tsipaving.nct
Rem Description Qty Rate Total
Fence Instill - Re... Fence and Gate Installation and or rework including any 1 4,025.00 4.025.00
type of controller installation or relocation - Relocate
conwlla 8' and add additional 8' to existing gate width.
Move all support where necessary
Concrete Flat Work Concrete Flat Work and Finishing - Add additional 8' x 36 93.75 3,375.00
32' x 16' area of heavy duty 9" concrete radius for truck
traffic @ Gate N 1 Pfau — 36 sq yards
Projea Indiana & 8th Combined Projott - Change Order
Reg: 2
TSI is not ruyv.uible for the location or Locates of
Private Property Utilities or any other type underground
services.
Thank you for the opportunity to be of son ice
Total $7,400.00