CHANGE ORDER - EXTRA WORK AGREEMENT NO. 1 JOB NO. 10108
Pmjcct Name 8th Street Combined Sewer Separation
Contractor TSI Paving
You are hereby authorized to proceed with the following described change or extra work
As per attached documentation:
Material Costs
1. 543 Tons of Bedding & Backfill Stone lR'e $8.05/ = $ 4,371.00
2. Dumping Pees - 30 (ry $11.00 EA = $ 330.00
3. Depth of Precast Structure Increase per S&M (d, $1114.00/LS = $ 1,114.00
4. Bond Rate Q 1.3% = $ 260.00
TOTAL = $ 6,075.00
Labor Costs
1. Pay Foreman (ifs $40.00 /hr for 13 hour = $ 520.00
2. Pay 2 Operators (ri, $41 :0/hr for 13 hours = $ 1,089.00
3. Pay 1 Pipe Layer a(' $34.02/hr for 13 hours = $ 442.00
4. Pay 1 Laborer (4 $33.72/hz for 13 hours = $ 438.00
5 Taxes & Insurance (rP 32.0% = $ 795.00
TOTAL = $ 3,284.00
Equipment Ccets
1. Caterpillar 320 Excavator ® $260 /day for 1.6 days = $ 416.00
2. Caterpillar IT-24 Wheel Loader ® $210 /clay for 1.6 days = $ 336.00
3. Mlisoellaneous 'Tools (or? $25 /day for 1.6 days = $ 40.00
4. Fuel ® $3.711 /gallon for 95 gallons = $ 353.00
TO'T'AL = $ 1,145.00
Subcontractor Fees
1. Messier (4 $72.00 /hr for 30 hours for Hauloff Trucking = $ 2,160.00
2. Manion e $0.50 /12 for 765.00 IF for Staking = $ 383.00
TOTAL = $ 2,543.00
Tond Fees
ADD = $ 13,047.00
' 15115% Contingency for Materials, Labor & Equipment $ 1,575.60
5% for Submntnemr Fees $ 127.15
TOTAL = $ 14,749.75
The method of payment for this change or extra work shall be:
An addiconal amount of fourteen thousand seven hundred forty -nine dollar and seventy -five tens = $14.749.75
An additional 2 days will also be added to the Contacted Project Compktion Date.
Consulting Engineer. Jacobi, Toombs and Lanz, Inc.
8/4111
Engineer's Signature Date
Owner's Approval: city of j vine
�t
Signat ' Owner(s) Date
Contracuors • vul:: TSl Paving
of TO gett /� - l.ea4 l My S/O /P /l
Authorized Representative Title J Date
Page 1 of 1