HomeMy WebLinkAboutChange Form #1 10th St PS Expansion WORK DIRECTIVE CHANGE FORM
TO: PACE CONTRACTING WORK DIRECTIVE CHANGE NO. 1
DATE: 8/3/11
PROJECT NAME 10Th ST. PS EXPANSION
PROJECT NO: 423098
Specification Reference: 007215 GC 114 00 73 14 Supplem r Conditions paragraph SC 13
Drawing Reference: NA
DESCRIPTION OF WORK COVERED BY THIS DIRECTIVE CHANGE:
Substantial Completion deadline shall be extended 22 calendar days from May 16, 2012 to June 7, 2012.
Final completion date shall not be extended (remains at July 30, 2012. Pump station shall have minimum
35 mgd capacity by May 24, 2012.
City shall not direct means and methods for how to achieve the scheduled deadlines. No overtime or fast
track costs shall be paid.
REASON FOR THIS ORDER:
Vectren gas line relocation was anticipated to be complete in April 2011 as per Specification Section 0073
14 Supplementary Conditions, paragraph SC -13. However, actual gas line relocation was not completed
until June 2, 2011, causing excavation activities to be delayed. Contractor schedule indicated a start date
for driving H -beam piling of May 9, 2011. However, Contractor did not start driving piling until May 31,
2011 due to the concern over the active gas line onsite. This represents a delay of 22 calendar days.
See attached letter from Pace dated 8/2/11.
AUTHORIZATION:
THIS WORK DIRECTIVE CHANCE AUTHORIZES THE WORK TO BE COMPLETED AS OUTLINED. A
Contract Change Order in the amount of $ 0.00 will be issued to you in the near future to
cover this WORK DIRECTIVE CHANGE.
PROJECT COMPLETION DATE: 0i /DEDUCT/UNCHANGED 22 r'AI.ENDAR DAYS TO
SUBST • 0, COMLETIOND' ILINEONLY n
By: e BY: ' t,.,,. f(a¢a
Proj � c •n Engineer) entP •ject Representative
BY E B �� V /
Prolger (Contr- or) • dministrator (• 7 Ref tative)
Jeffersonville, Indiana Additional Forms Supplemental to Agreement Form
Tenth Street Pump Station Expansion 00 52 25