HomeMy WebLinkAbout02-01-2011 Change Order Seventh and Indiana Partial Sewer Separation CHANGE ORDEIL- EXTRA WORK AGREEMENT NO. 2 - JOB NO. 0699C _
Project Name Seventh and Indiana Partial Sewer Separation _
Contractor TS1 Paving
l
Yon are hereby authorized to pmeeed with the following desccbed change or extra work:
As per attached documentation:
1. Add 90 TT of 12" Perforated Pipe a $24.00/LI _ $ 9„160.00
2. Core Existing Catch Basin (No. 13) a $362.50/LS = $ 362.50
3. Core Drywall {a} $290.00/LS - $ 290.00
4. Raise Drywell Rim with 18" Ring = $ 1,000.00
ADD = $ 3,812.50
The method of payment for this change or extra work shall be
An additional amount of three- thousand eight hundred and twelve dollars and fifty cents = $3,812.50
Consulting Engineer: ac Tnornlrs and Lanz, Inc.
F. g ' Dat
Owners Approval: 9Jeferson,/ r ,//
` �% 2163
Si is rc •f awucr s D tc
Contractor's Approval: '' P ving ` r ���
Authorized Repre ' • a ' di Titte t o