HomeMy WebLinkAbout4-01-09 Change OrderCHANGE ORDER -EXTRA WORK AGREEMENT NO. 1 JOB NO. 0779
Project Name: _Allison Lane Sidewalk Installation
Owner Jeffersonville Board of Public Works & Safety
Contractor: Clark Nickles, Inc.
1. Increase in Quantity of 4" Concrete Sidewalk by 165 SYS @ unit price of $37.00/SY (Contract Pay Item No. 1) $ 6,105.00
2. Increase in Quantity of Compacted Aggregate Base, 53 by 37 Tons @ unit price of $18.00/Ton (Contract Pay Item No. 3) $ 666.00
3. Increase in Quantity of Curb Ramp, Red by 17.6 SYS @ unit price of $57.00/SY (Contract Pay Item No. 4) $ 1,003.20
4. Increase in Quantity of 12" Storm Sewer, Circular by 36 LFT @ unit price of $21.00/LFT (Contract Pay Item No. 6) $ 756.00
5. Increase in Quantity of Sod by 183 SYS @ unit price of $3.60/SY (Contract Pay Item No. 9) $ 658.80
6. Increase in Quantity of Seed by 183 SYS @ unit price of $0.35/SY (Contract Pay Item No. 10) $ 64.05
7. Additional Clearing of Right-of--Way (Lump Sum)
$
3,000.00
8. Additional Linear Grading (Lump Sum)
$
500.00
9. Remove and Reset Sign (Lump Sum) $ 200.00
10. Additional Maintenance of Traffic
$
300.00
The Method of payment for this Change Order shall be an addition in the amount of:
Thirteen Thousand Two Hundred and Fifty-Three Dollars and Five Cents $ 13,253.05
Consulting Engineer: Jacobi, Toombs and Lanz, Inc.
Engineer's Signature
Owner's Approval: Jeffersonville Board of Public Works & Safety Date
Signature of Owner(s)
Contractor's Approval: Clark Nickles, Inc. Date
Authorized Representative Title Date