HomeMy WebLinkAboutJacobi, Toombs & Lanz Supplemental Contract #1
SUPPLEMENTAL CONTRACT NO.1
This Supplemental Contract No.1 made and entered into this q~ day of .Jut y ,
2008, by and between The City of Jeffersonville, Indiana, acting by and through its proper
officials, hereinafter referred to as the LOCAL PUBLIC AGENCY or LPA, and Jacobi,
Toombs and Lanz, Inc., Consulting Engineers and Land Surveyors, 120 Bell Avenue,
Clarksville, Indiana 47129, hereinafter referred to as the CONSULTANT.
WITNESSETH
WHEREAS, the LPA and the CONSULTANT did, on December 9, 1991, enter into a
Contract providing for Preliminary Engineering Services required in the development of contract
plans and for the professional services required in the preparation of the appropriate
environmental studies for the reconstruction of Hamburg Pike from Dutch Lane to New
Albany-Charlestown Pike, a distance of approximately 1.46 miles, in the City of
Jeffersonville, IN, Clarks County, herein known as Project No. STP-C700004, Des. No.
9185035 and 9185036, and
WHEREAS, the Original Contract dated December 9, 1991 is now inadequate and
outdated, and the fees must be updated to allow for the completion of the plans, and,
WHEREAS, now that Location-Design Approval has been granted by INDOT, it is
appropriate and necessary to initiate and complete the Right-of- Way Engineering Phase of this
project.
NOW THEREFORE, it is agreed by and between the parties hereto to the following
additions or changes in the Contract:
APPENDIX "A"
Services by CONSULTANT
A.I The CONSULTANT shall update the field survey required to fmalize the design plans.
1. RIGHT -OF- WAY ENGINEERING
The CONSULTANT shall provide right-of-way engineering in accordance with the
procedures and standards as indicated in the Indiana Department of Transportation
(INDOT) Division of Land Acquisition Right-of-Way Engineering Procedures Manual
including but not limited to the following:
1. Prepare and provide one mylar and four (4) copies of the fmal right-of-way plans.
2. Provide a documented twenty (20) year title search prepared by a professional
abstractor for each parcel with a fair market value of $5,000.00 or more. At the
S:\Sydney\WPDOCS\9\920SFSupplemental\supplemental contract 1-070808.docx Page 1 of 7
time each such parcel is acquired, the title search shall be updated and one of the
following documents issued:
a. An examination of the abstract and opinion of title by an attorney, or
b. A Guaranty of Title or Title Insurance in the amount of $5,000.00. For
parcels with a fair market value of less than $5,000.00 and for temporary
right-of-way, verify the last deed of record or provide a minimal title
search prepared by a title company.
3. Provide metes and bounds legal descriptions and transfer documents for each
parceL The descriptions shall be prepared and certified by an Indiana registered
land surveyor.
4. Provide individual plats for each parceL Each plat shall be certified by an Indiana
registered land surveyor and include the following:
a. Total area before taking;
b. Area of existing right-of-way; and
c. Areas of all residue.
5. Provide separate folders for each parcel containing information obtained from A.I
through A.4 of this Appendix.
6. Complete the Parcel Listing Summary Sheet in final right-of-way plans.
7. Provide in the field a stake-out locating the new right-of-way line (including
temporary and permanent right-of-way) for the partial takings included in all
parcels. The stake-out shall be made using wooden hubs located at
changes in bearing and -other points necessary to show the location of the
proposed right-of-way takings.
J. APPRAISAL PROBLEMS ANALYSIS
The CONSULTANT shall provide an Appraisal Problem Analysis prepared by an
appraiser as approved by INDOT as follows:
1. Examine the right-of-way plans and determine the extent of the taking;
2. Perform an on-site inspection of each parcel requiring right-of-way acquisition;
3. Determine the type of appraisal needed for each parcel according to FHW A
Regulations (49 CFR Part 24, dated March, 1989).
4. Complete an Appraisal Problem Analysis form for each parcel to be acquired;
S:\Sydney\ WPDOCS\9\920SFISupplemental\supplemental contraCll-070808.docx Page 2 0 f 7
'~.
5. Prepare a summary sheet setting out:
Parcel Number
Name of Owner
Size of Property
Amount of right-of-way to be acquired
Types of right-of-way to be acquired
Recommended Appraisal form
6. Transmit two copies of the completed report to the appropriate LP A official for
submission to INDOT for review.
APPENDIX "B"
INFORMATION AND SERVICES TO BE FURNISHED BY LOCAL PUBLIC AGENCY
The LOCAL PUBLIC AGENCY (LPA) shall furnish the CONSULTANT with the
following:
14. Sufficient quantities of all pertinent forms.
15. Mylar reproductions of the approved design plans
16. Access to (or make all provisions for the CONSULTANT to enter upon) public
and private lands as required for the CONSULT ANT to perform the work under
this agreement.
17. Review and approval of all completed transfer documents by an attorney (their
own or fee attorney).
18. Copies of the design or location-design study reports.
19. Copies of the environmental studies and/or approvals.
APPENDIX "c"
SCHEDULE
A.3 Update field survey within 30 calendar days of approval ofthis Supplemental Contract
No. 1.
A.8 Final field check plans within 90 calendar days after Notice To Proceed with the
Supplemental Contract has been reviewed.
A.9 Right-of-Way Tracings within 30 calendar days after approval of Right-of- W ay check
S: ISydneyl WPDOCSl919205F\Supplementallsupplememal contract 1-070808dncx
Page 3 of7
points and Final Field check Plans have been reviewed.
A.I0 Final contract plans for preliminary review within 60 calendar days after approval of
Final Field Check Plans.
SCHEDULE OF RIGHT -OF- WAY ENGINEERING
All work by the CONSULTANT under this agreement except Section 12-D below shall
be completed and delivered to the LOCAL PUBLIC AGENCY no later than one hundred eighty
(180) calendar days after notification of notice to proceed from the LOCAL PUBLIC AGENCY,
exclusive of LOCAL PUBLIC AGENCY'S review time.
D. ROADWAY DESIGN. RIGHT -OF- WAY PLANS AND BRIDGE PLANS
12. For the purpose of contract control the work will be submitted by the
CONSULTANT to the LOCAL PUBLIC AGENCY for review within the
following approximate time periods.
A. Final Right-of-Way plans, title search, legal descriptions, transfer
documents and land plats for each parcel within one-hundred five (105)
calendar days after receipt from the LOCAL PUBLIC AGENCY of notice
to proceed.
B. Right-of-Way stake-out within thirty (30) calendar days after redeipt from
the LOCAL PUBLIC AGENCY of approval of the final right-of-way
plans and notification to proceed with the stake-out.
C. Appraisal Problem Analysis report within forty-five (45) calendar days
after right-of-way engineering is complete.
D. Title search updating and issuance of title work to be at the time of each
parcel acquisition.
S:\Sydney\ WPDOCS\9\9205F\Supplemental\supplemental contract 1-070808.docx
Page 40f7
APPENDIX "D"
COJ\1PENSA TION
A. AMOUNT OF PAYMENT
1. The Consultant shall receIve as payment the additional amount of this
Supplemental Contract $386,070.00, increasing the maximum total not to exceed
$568,008.36 unless a modification of the Contract is approved in writing by the
LP A, INDOT and FHW A.
2. The Consultant will be paid for the work performed under this Contract,
excluding the geotechnical services and pavement investigation services, on a
Lump Sum basis in accordance with the following schedule:
a.l
Update Topographic Survey
$7,000.00
e.
Road Design & Plans
Bridge Design and Plans
(for Bridge RehabilitationlNew Supertructure)
$194,605.00
f.
$ 42.380.00
5. The CONSULTANT shall receive as payment for the work performed under this
Agreement based on the specific cost per unit multiplied by the actual units of
work performed.
QUANTITY UNIT PRICE TOTAL
1 Lsum @ $XXXX.XX $20,400.00
Lsum @ $XXXX.XX $19,300.00
76 Each @ $250.00 $19000.00
17 Each @ $175.00 $2,975.00
10 Each @ $50.00 $500.00
10 Each @ $250.00 $2,500.00
95 Each @ $500.00 $47,500.00
100 Each @ $150.00 $15,000.00
78 Each @ $80.00 $6,240.00
89 Each @ $50.00 $4,450.00
Page 5 of7
a. Location Control Route Survey Plat
b. Final Right-of-Way Plan
c. Title Work
With Guarantee
Minllnal Search
Updates
Special Requests
d. Legal Descriptions
First Description
Additional Description
e. Transfer Documents
Fee Simple Acquisition
Temporary Acquisition
S:\Sydney\ WPDOCS1919205F\Supplementallsupplemental contract 1-070808.docx
f. Land Plats 95 Parcels $500.00 $17,500.00
@
Appraisal Problem Analysis 93 Parcels $200.00 $18,600.00
g. @
h. Right-of-Way Stake-Out 1 Lsum @ $XXXX.XX $27,400.00
TOTAL $231,365.00
The amount of$231,365.00 determined above is an estimate of the cost which the
CONSULTANT will incur in fulfilling the requirements of Appendix "A". The final
amount will be adjusted according to the actual units of work performed; however, the
final amount shall not exceed $266,070.00 without approval of the LOCAL PUBLIC
AGENCY and the Indiana Department of Transportation.
B. Method of Payment
1. The CONSULTANT shall submit invoices to the LOCAL PUBLIC AGENCY,
not more often than once per month during the progress ofthe work, for partial
payment of account for the work completed to date.
2. For work performed under Section A.l of Appendix "A" the LOCAL PUBLIC
AGENCY agrees to pay the CONSULTANT for the percentage of the work
completed.
3. For work performed under Section A.2 through A.7 and Section B of Appendix
"A" and upon completion ofthe respective work and its acceptance by the
LOCAL PUBLIC AGENCY, the LOCAL PUBLIC AGENCY agrees to pay the
CONSULTANT the fees established above. No partial payments shall be made on
a per parcel fee.
4. In the event of a substantial change in the scope, character or complexity of the
work on the project, the maximum fee payable and the specified fee shall be
adjusted is accordance with item 12 (changes in work) of General Provisions set
out in the Agreement.
S: \Sydney\ WPDOCS\9\920SF\SupplementaJ\suppJemental contract 1-070808.MCX
Page 60f7
. .....
EXCEPT as herein modified, changed and supplemented, all items of the original
Contract dated December 9, 1991, shall continue in full force and effect.
IN WITNESS WHEREOF, the parties hereto have made and executed this supplemental
Contract the day and year first mentioned above.
CONSULTANT
I, TOOMBS AND L
Barbara Wilson, Member
ATTEST:
Q~
.
U]jtJk)
City Attorney
S: ISydneyl WPDOCSl919205F\Supplementallsupplemental contract 1-070808.docx