HomeMy WebLinkAbout02) Change Order #2
CHANGE ORDER - EXTRA WORK AGREEMENT NO.
2
JOB NO. 0546i
f' Project Name: S.R. 62 & Utica-Sellersburg Road Sanitary Sewer & Water Line Extension
Owner:
Jeffersonville Sewer Board
Contractor:
Team Contracting, LLC
1. Retesting 15" gravity sewer between Manholes No. .5 & 6 due to Fire Station connecting lateral before $ 653.00
sewer had been tested and approved.
2. Tree removal near existing building and 8" sewer line construction on Cunningham property
$ 750.00
TOTAL THIS CHANGE ORDER
$ 1,403.00
jr'\
"
The method of payment for this change order shall be an addition in the amount of
One-thousand four-hundred and three dollars and z~ro cents.
$ 1,403.00
Signature ofOwner(s)
Jeffersonville Board of Public Works
co~~mval' Toam Cootractffig,LLC
~~
Authorized Rfpresentative
&o.)ezT ~N,d~
Title
/Z-/J- 07
Date
t\
S\EP2002\PROJECTS\0546o\0546-C02