HomeMy WebLinkAbout01) Change Order #1
4" '
CHANGE ORDER - EXTRA WORK AGREEMENT NO.
1
JOB NO. 0546i
Project Name: S.R. 62 & Utica-Sellersburg Road Sanitary Sewer & Water Line Extension
Jeffersonville Sewer Board
r- Owner:
~
Contractor:
Team Contracting, LLC
1. Relocation of existing 14" Sanitary Force Main Located directly over 15" Sanitary Sewer where
manhole is to be constructed for connection to proposed sewer. See attached Letter from Team
Contracting for additional details.
$ 12,388.00
TOTAL THIS CHANGE ORDER
$ 12,388.00
r :
, The method of payment for this change order shall be an addition in the amount of
Twelve-thousand Three-hundred and Eighty-Eight Dollars and No Cents
$ 12,388.00
Signature ofOwner(s)
e onville Board of Public Works
Contractor's Approval: Team Contracting,LLC
/6'~;?()7
Date
~
-t-
S\EP2002\PROJECTS\0783i\0783i-CO 1
~ 09/~8/2007 12:41
8122943901
TEAM CONTRACTING
PAGE 62/02
r\
,. ..)
~
14912 Railroad Street
Memphis, Indiana 47143
=
Telephone 812-:294-1258
TEAM CONTRACTING, LLC
In Business Since 1995
Post OffIce Box 237
MemphIs, Indiana 47143
... -= =---=::: ......
Fal< ~12-29~3901
September 17, 2007
Mr. Josh Hillman
Jacobi, Toombs & Lanz, Inc.
120 Bell Avenue
ClarksVille, Indiana 47130
Re: S.R. 62 & Utica-Sellersburg Road Sanitary Sewer Extension
Dear Mr. Hillman:
This letter Is to serve as Team Contracting, LLC's formal request for a change order for
the relocation of the existing 14 inch diameter force main that is In conflict with the new
manhole at station 10+00,
We will provide labor, equipment and supervision to relocate approximately 20 LF of 14"
SDR 18 PVC force main 5' north of its existing location where it conflicts with the new
manhole (per the drawing faxed to our office). We indude f10wable fill backfill and
asphalt pavement restoration.
(\
,
The cost for this additional work Is $12,388,00.
. Please provide your verbal approval of this additional work, so that we may proceed
with ordering the pipe and fittings for this work.
Additionally, we request that 5 working days be added to our contract time for this
work,
If you have any questions, or need additional information, please contact our office.
Sincerely,
Team Contracting, lLC
~~.
Mar~e
Project Manager
MC:jm
PC: Project File
Oemolltlon -: CQnc;:rete - Site Development - Utilities
Equal Opportunity Employer - M/F/HN
""'-