CHANGE ORDER - EXTRA WORK AGREEM~NT NO.
2
JOB NO.
0596
Project Name Annex Area 4 Sanitary Sewer Improvements
Contractor
Team Contracting, LLC
You are hereby authorized to proceed with the following described change or extra work:
As per attached documentation:
1. Additional cost to provide the complete Telemetry 'system due to misinterpreting the specs, add
2. Additional stone for the base of the Wetwell, add
3. Change pumps to explosion proof due to pump supplier request, add
$
$
$
3,948.00
1,920.00
7,715.35
ADD = $
13,583.35
The method of payment for this change or extra work shall be:
An additional amount of thirteen thousand five hund~ed and eighty-three dollars and thirty-five cents = $13,583.35
Owner's Approval:
C-f rV tvt, ttJ4. M
7-/0" 0 to
Date
{'
\,_~' i
C:JGS\project files\03171\0596 cbange order 2.xls
Page 1 of1
06/05/2006 14:12
,
8122943901
TEAM CONTRACTING
PAGE 02
A
TEAM CONTRACTING, LLC
Te'jeph~rie'IH2~2'94=12i;8
......... . ...-.- ".-.--. ,- --.-. -
Post Offiee Box 237
Memphis, Indiana 47148
r\
14912 Railroad $tr$et
Memphis, Indiana 47143
__,._. ~_'___'_'__M"_"_" _~"'~_""'M';'_"__".'''''' --.. .....--..- ...-.-,. ......-.., ...-....
. .-. . Fax'812~294;ag01
In Business Since 1995
June 5, 2006
Mr. Jorge Lanz
Jacobi, Toombs and Lanz, Inc.
120 Bell Avenue
ClarksviJIe, Indiana 47129
Re: Annex Area 4 Project
Telemetry
Mr. Lanz:
At the time of our bid on this project, we interpreted from the specifications that the telemetry
equipment was to be relocated from an existing facility. We now are being told that it is to be a
new installation and we are expected to provide and install the telemetry equipment. This is an
unexpected added expense to us and we would appreciate your consideration to compensate us for
the added cost.
(\
We are requesting a change order for this w'ork as follows:
Teknon Controls, Inc. - Equipment & Programming: $4,450.00
As Bid to relocate equipment: ~ 690.00
Additional Cost:
Supervision, overhead & profit - 5%:
$3,760.00
188.00
Total Additional Requested:
$3,948.00
Respectfully,
~~TRA~TI~G.LLC
Tom veroiz:z.~
Construction Manager
D~m';;i'itl~"; ~-coriorete - Site Devaiopment - Utliltles'
Equal opportunity f:mployer - MIFIHN
f\
f\
r
(''Ii
'05/05/2005 14:12
.
TEAM CONTRACTING
<1- -1![_I!.:Pl f-f T;ey
PAGE 03
Page 1 of 1
8122943901
!lJ/NE;{' /!.t?eA
Joe Jenkins
,
-~~--;.--..~-~~-~,~
- ...............-..-.--...---'-".-..--.-...,
From: Tom Mac Donald [tom@teknoncontrols.com]
Sent: Wednesday, May 24,20068:37 AM
To: Joe Jenkins
Subject: Lift Station Telemetry
Attachments: QTE Team Annex 4.pdf
Joe,
Attached is my quotation for the Lift Statfon Telemetry. The price is $4450. Normally, the price is $3540. The
increase reflects $250 in materials normally supplied by the Pump Panel manufacturer that is not supplied with
this panel for some reason. Also, some panel wiring that is normally supplied by the panel builder has not been
supplied on this job. These omissions are a result of vague Lift Station Specifications. Technically, the Pump
Panel meets the specs, but it is not sufficrent to do the job. Besides that, I added $250 for the 20x20x8 enclosure,
and some time to mount it and install condUIt to the. Pump Panel.
Thank you,
Tom MacDonald
5/2412006
~ ~6/05/2006 14:12
.j ,
8122'343'301
T~AM CONTRACTING
PAGE 04
('
Teknoll;t~tmis Inc.
,~. " ~" ,. ~'." '.. "': '1'::;: : I, . f: .
7705 Bluegrass Court, Crestwood, KY 40014
Quotation
May 24, 2006
RE: Annex 4 Lift Station Telemetry
General Scope
Teknon Controls, Inc. proposes to provide PLC and HMI programming for the
Annex 4 Lift Station and the Jt';ffersonvitte Waste Water Treatment Facility, and Radio
Telemetry equipment for the Lift Station. Thetele11letry equipment and programming
will provide the same features as those currer'ltly in place for similar lift stations.
Services Provided
(',
Enaineerina and Software
./ Program the Lift Station Pump Panel PLC.
./ Program the JWWTP Master PLC and HMI computer to provide the typical Lift
Station monitoring. '
Radio Sv:stem
./ Perform radio path study.
./ Prepare FCC license application forms.
./ Verify prQper radio communication to ,fWWTP.
Installation
./ lnstall Antenna & Radio transr:nission line, connections.
./ Install Radio Modem & Powet; Supply.
./ Install Radio enclosure, conduit and wire to Pump Panel.
./ Wire Pump-Fail signals to PLC inputs.
./ install RS-232 Opto-Coupler in Pump Panel
Phone/Fax (502) 241-2567, Cell 'Phone (502)-639-2561, 1Q!ll@teknoncontrols.com,
Page 1 of3
09/05/2006 14:12
"''::'
8122'343'301
TEAM CONTRACTING
;.. .
Tekno4 .C_l:tt~t)ls, Inc.
." ~,..,. "". " ..,". . ~ ,. '. .. .
I
7705 Bluegrass Court, Cre$twood, KY 40014
Materials Provided
,Radio Eauioment
../ Radio Modem
../ Radio Modem Power Supply
.,( Antenna
../ Lightning Arrestor
.,( Transmission Line Kit
0/ RS~232 Opto-Coupler and cable to PLC
.; Radio Enclosure
Not Provided
o The antenna mast is NOT provided
r
t
Terms and Conditions
Warranty
Teknon Controls, Inc. will warrant its workmanship and materials for one (1) year froro
the date of startup.
Terms
. Net 30 days
Price
Price for the above: $4,450.00
This quotation is valid for 90 days.
Thomas Mac Donald
Estjmator
I
Phone/Fax (502) 241-2567, Cell Phone (502)-639-2561, tom@teknancontrols.c:om.
Page 2 of3