CHANGE ORDER - EXTRA WORK AGREEMENT NO.
3
JOB NO.
0412i
Project Name Meadows Drainage Improvement
Contractor Temple & Temple Excavating & Paving, Inc.
You are hereby authorized to proceed with the following described change or extra work:
As per attached documentation:
1. Delete 1514 CY of Berm Earthwork at $13.00 per CY = $ . (19,682.00)
2. Add 4.03 TN of HMA Surface, Type "B" at $52.00 per TN = $ 209.56
3. Delete 27.05 TN of HMA Intermediate, Type "B" at $50.00 per TN = $ (1,352.50)
4. Add 443.40 TN of Type "0" Compacted Aggregate at $21.00 per TN = $ 9,311.40
5. Delete 1780 TN of Indiana No.2 Stone at $11.00 per TN = $ (19,580.00)
6. Add 28 LF ofPVC Pipe Extensions at $25.00 per LF = $ 700.00
7. Add 2457 SY of Seeding at $0.32 per SY = $ 786.24
8. . Delete 1210 SY of Sodding at $2.85 per SY = $ (3,448.50)
9. Delete 700 LF of Erosion Control Silt Fence at $3.00 per LF = $ (2,100.00)
10. Add 207.63 TN of Repave Crum's Lane at $52.00 per TN = $ 10,796.76
11. Add 200 SY of Mill 4' Strip at $3.50 per SY = $ 700.00
12. Delete 5714.26 CY of Berm Key Way and Undercut at $14.00 per CY = $ (79,999.64)
13. Delete 99 LF of Grade Beam Wall at $45.08 per LF = $ (4,462.92)
14. Delete 56 SY of Grouted Rip-Rap at $44.00 per SY = $ (2,464.00)
15. Add 30.75 LF of Retaining Wall at $505.00 per LF = $ 15,528.75
16. Add 15.31 TN of Rip-Rap at $28.45 per TN = $ 435.57
17. Add adjust to line #44 $2 perLS = $ 2.00
r DELETE $ (94,619.28)
=
The method of payment for this change or extra work shall be:
A deletion in the amount of ninety-four thousand and six hundred and ninteen dollars and twenty-eight cents =
$94,619.28