HomeMy WebLinkAboutChange Order 1CHANGE. ORDER -EXTRA WORK AGREEMENT NO. 1 JOB NO. 0545 .Project Name: Jeffersonville-Charlestown Pike Sidewalk, Phase 1 Owner: Jeffersonville Board of Public Works and A~JG ~ ~ ~l1Ub Contractor: Pace Contracting, LLC You are-hereby authorized to proceed with the following change to your contract . dated 21 June 2006. 1. Pay Item No. 23: Reconstruct stone block entrance, move entire entrance and side fence back 5', instead of just ~~ two(2) front pillars, add ~ + $ 10,200.00 , 2. Pay Item No. 26: Remove and replace 10" or 12" culverts under driveways to houses in Suburban Acres if required using HDPE pipe. 3. New Pay Item No. 27: Cut new swales in yards to drain, only if directed b _ 100 LFT @ $12/LF, add + $ 1,200.00 4. Pay Item No. 15: 6" PVC Storm Sewer, 124 LFT @ $20.00/LF, add + $ 2,480.00 5. New Pay Item No. 28: Encase 6" pipe in concrete 36 LF @ $10.00/LFT, add + $ 360.00 6. New Pay Item No. 29: Remove 4" Tree 1 EA. @ $250.00/ea, add + $ 250.00 7. New Pay Item No. 30: Slope earth bank back & re ade @ T.. school 1 LS @ $1,000.00, add j_____± _~_ 1,000.00 8. New Pay Item No. 31: Replace 48" CMP culvert under Charlestown Road' n ,~ with new 48" RCP Class IV, complete ~-. ash 1 LS @ $16,608.00, add ~ ~1~~' ~\~, + $ 16,608.00 9. Pay Item No. 16: Extend existing 48" CMP culvert, delete. 1 LS @ $2,000.00, subtract - $ 2,000.00 ~otal This Change Order No. 1, add = $32,898.00 5 EA. @ $20.00 LFT x $28.00/LF, add + $ 2,800.00 S:~ydney~ ~,do~s~o9~o549~ohangeo~de~ ~.xls CHANGE ORDER -EXTRA WORK AGREEMENT NO. 1 JOB NO. 0545 .Project Name: Jeffersonville-Charlestown Pike Sidewalk, Phase 1 Owner: Jeffersonville Board of Public Works and Safe The method of paymentfor this change or extra work shall be: Consulting Engineer: Owner's Approval: O/ Date G Signature of O net(s) Date Contractor' entative Title ~ Date 5:\jyd~ey~ Pdocs\o9\o545\changeorder i.xls contracting, LLC 200 willinger lane Jeffersonville, irdiana 47130 812-283-5784 phone 812-283-5795 fax pacecontractingllc@sbcglobal.net July 7, 2006 Jorge Lanz., PE Jacobi, Toombs, anc~ Lanz, Inc. 120 Bell Avenue Calrksville, IN 47129 Subject: ..City. of Jeffersonville, IN -__ Charlestown.:Pike Sidewalks Pace Job 5190 Move Stone Entrance Back - flAy ~ -~~ z 3 Our bid item to reconstruct the stone block entrance. by moving the front columns back 5 feet was $8000.00 per the enclosed breakdown: • Remove stone. columns and 5 feet of wall 2 each $1000.00 Pour new column footings. 2 each $1000.00 Rebuild stone columns 2 each $4800.00 Pace Markup 1 Is 1200.00 Total $8000.00 Our price to move the entire entrance back 5 feet and move the fence back is as follows: Remove all stone columns and walls 2 each $2000:00 Pour new.column, and wall footings 2 each $3000:00 Rebuild stone columns and walls 2 each $10,000.00 _ Move fence back 1 Is $500,00 Pace Markup 1 Is 2700;00 TotaF $18,200.00 Seeding or sodding of disturbed yard area will be paid for by bid unit prices c ely