HomeMy WebLinkAbout2007-R-32
RESOLUTION # ?-DO+ r ~r 3-::l
ACCEPTANCE OF PRELIMINARY ENGINEERING REPORT
WHEREAS, the City of Jeffersonville, Indiana, acting through it's duly appointed Sewer Board has
caused a Preliminary Engineering Report dated October 2007 to be prepared by the consulting firm of Jacobi,
Toombs and Lanz, Inc. for the Long View Beach Sanitary Sewer Installation and Septic Tank Elimination.
WHEREAS, said report has been presented to the public at a public hearing held February 7,2007 for
their comments; and
WHEREAS, the City of Jeffersonville fmds that there was not sufficient evidence presented in
objection to the recommended project in the Preliminary Engineering Report.
NOW, THEREFORE BE IT RESOLVED THAT:
1. The Preliminary Engineering Report dated October 2007 be approved and adopted by the City
Council of the City of Jeffersonville; and
2. That said report be submitted to the Indiana Department of Environmental Management for
review and approval.
Passed and adopted this ~ day of November, 200~ by the Common Council of the City
of Jeffersonville, Clark County, Indiana.
ATTEST:
~b)J)pJ
Peg lder
Clerk/Treasurer
~
Presented by me as Clerk and Treasurer to the Mayor of said City of Jeffersonville this
Ldayof November, 200~.
Approved and signed by me this ~ day of November
S :ISydneyIWPDOCSISIS70SIS70SSlresolution.DOC
..
PRELIMINARY ENGINEERING REPORT
LONGVIEW BEACH SANITARY SEWER INSTALLATION
AND SEPTIC TANK ELIMINATION
City of Jeffersonville
Clark County, Indiana
October 2007
Revised October 26,2007
City of Jeffersonville
Sanitary Sewer Board
PREPARED BY:
JACOBI, TOOMBS AND LANZ, INC.
CONSULTING ENGINEERS
120 BELL AVENUE
CLARKSVILLE, INDIANA 47129
(812) 288-6646
(812) 288-6656 FAX
.
,
..
PRELIMINARY ENGINEERING REPORT
LONGVIEW BEACH SANITARY SEWER INSTALLATION
AND SEPTIC TANK ELIMINATION
TABLE OF CONTENTS
I. PROJECT AREA
II. CURRENT SITUATION
A. Description of Existing System
B. Problems with Existing System
III. FUTURE SITUATION
A. Current Population
B. Population Projections
C. Proposed Design Wastewater Flows and Loading
IV. EVALUATION OF ALTERNATIVES
A. No Action
R Force Main (Pressure Sewers)
C. Installation of Gravity Sanitary Sewers
D. Recommended Alternative and Rationale for Selection
V. ENVIRONMENTAL IMPACT DOCUMENTATION
A. Biota
R Wetlands
C. Soils/Geology
D. Hydrology
E. Groundwater
F. Natural National Landmarks
G. Coastal Zone Program
H. Historic, Architectural, and Archaeological
1. Induced hnpacts
1. Air Quality
K. Open Space and Recreational Opportunities
VI. SELECTED PLANS
A. Project Description
R Project Phasing
C. Preliminary Design Summary
D. Project Costs
E. Project Schedule
F. Land Acquisition
TABLES
Table 1: Estimated Project Costs
SRF Project Financing Information
Page No.
1
1
1
2
3
6
Rev. October 26, 2007
PRELIMINARY ENGINEERING REPORT
LONGVIEW BEACH SANITARY SEWER INSTALLATION
AND SEPTIC TANK ELIMINATION
I. PROJECT AREA
The proposed project is located in the south portion of Clark County just North of the
Town of Utica approximately 3.5 miles north of port road along Utica Pike. The project
area is located in Survey Nos. 17 and 27 of the Illinois Grant (also know as the Clark
Military Grant), as shown on the Jeffersonville, Ind.-Ky. Quadrangle map. The project
area is shown on Figures 1 and 2.
II. CURRENT SITUATION
A. Description of Existing System
The homes along Longview Beach Drive, Conservation Drive, and Upper River Road
currently dispose of wastewater through various on-site systems. A majority of the
homes are connected to septic tanks.
B. Problems with Existing System
The homes in the project area were developed several decades ago. Since that time,
the regulations governing residential development have been changed. The lots in the
project area are approximately one quarter (0.25) of an acre. Due to the small lots,
septic systems are difficult to install and maintain.
The Clark County Health Department (CCHD) supports the installation of sanitary
sewers in this area because of the health concerns associated with the septic systems
and the proximity of the homes to the Ohio River. See Appendix A for the supporting
documentation from the CCHD.
III. FUTURE SITUATION
A. Current Population
The current population of the Project Area is estimated to be 180.
(75 homes x 2.39 persons per home = 180)
This population is based on the actual number of homes connecting on to the new
sewer system. The populations shown on the sanitary sewer permits were based on
preliminary estimates that were done prior to the final design.
1
Rev. October 26, 2007
B. Population Projections
For the purposes of this report, the future residential population in the project area is
projected to remain the same. The lots fronting the proposed improvements are fully
developed. However, there are proposed developments on the Indiana Department
of Resources (IDNR) property that will impact this project. IDNR has planned a 50-
seat restaurant and a 50-room lodge. The IDNR development has been included in
the loading design.
C. Proposed Design and Wastewater Flows and Loadings
1. Wastewater Flows
Domestic Flows
Peaking Factor
Peak Hourly Flow
63,900 GPD
3.9
173 gpm
2. Design Loadings (1)
CBODs (1)
TSS (1)
NH3N (1)
40lbs/day
45lbs/day
4.7Ibs/day
(1) Ten State Standards
3. Impact on Existing System
The existing receiving lines and lift stations have sufficient capacity to accept
and convey the estimated loads. The new sewers will discharge into an existing
12" diameter sanitary sewer located at Quarry Bluff Subdivision. The capacity
of this sewer line has been verified; therefore this project will have a minimal
impact on the overall system.
IV. EVALUATION OF ALTERNATIVES
The alternatives considered include no action, installation of a pressure system with
grinder pumps, and the installation of gravity sanitary sewers.
A. No action
The no action option consists of maintaining the existing septic systems. The CCHD
supports the installation of sanitary sewers in the project area. Continued use of the
existing septic systems will create more health hazards in the project area. This option
is not considered an acceptable option due to the site constraints and the potential
impact to public health and safety.
2
Rev. October 26, 2007
B. Force Main (pressure Sewers)
A pressure sewer system with individual grinder pumps was considered as an option
as an alternative to the lift station and gravity sewer system along Upper River Road.
The residents in the project area were against the use of grinder pumps, therefore this
option was not chosen.
C. Installation of a Gravity Sanitary Sewers
The third option is the. installation of a gravity sanitary sewer system. The City of
Jeffersonville and the CCHD have a policy to recommend the use of a gravity
sanitary sewer system whenever possible. Gravity sanitary sewers are possible in the
project areas, therefore this will be the only option considered. Under this option,
gravity sewer lines will be installed on Longview Beach Drive, Conservation Drive,
and Upper River Road.
D. Recommended Alternative and Rationale for Selection
Alternatives were evaluated based on cost effectiveness, practicality, technical
feasibility, reliability, resident support, ease of implementation and environmental
effects. The only option that satisfies all of the criteria is the installation of a gravity
sanitary sewer system. The proposed plan is shown on Figures 1 and 2.
v. ENVIRONMENTAL IMPACT DOCUMENTATION
Environmental impacts are either direct or indirect. Direct impacts result from the
construction, operation, and maintenance processes of the project. Indirect impacts are
those that are made possible by the project, whereby creating a change which will
ultimately effect the environment.
Most of the improvements will occur within road rights-of-way and easements along
previously disturbed areas. As such, limited undisturbed areas, trees, or brush will be
disturbed. The following sections will discuss specific environmental impacts.
A. Biota
The construction and operation of the project will not negatively impact state or
federal-listed endangered species or their habitat. The project will be implemented to
minimize impact to non-endangered species and their habitat.
B. Wetlands
Wetlands will not be impacted by the construction or the operation of the project.
There is a stream crossing of Battle Creek in this project. A creek crossing of Battle
Creek with a six-inch (6") force main will be required to complete the project. The
creek crossing will be approximately 40 feet. The force main will be installed by open
3
Rev. October 26,2007
cut, and will be encased in concrete. The force main is being installed perpendicular
to creek to limit the amount of disturbed area. Alternate routes were studied to
eliminate the crossing, however none were possible. A National Wetlands Inventory
map is included as Figure 3. A photograph of the creek crossing location is included
in Figure 6.
C. Soils/Geology
1. Soil Characteristics
Soils in the project area consist of Caneyville-Rock, Elkinsville-Millstone silt
loams, and Huntington silt loam. Due to the small lot size and the proximity of the
lots to the Ohio River, the project area is not suitable for septic tanks regardless of
the soil. Soil map is included as Appendix B.
2. Prime Farmland
A Farmland Conversion Impact Rating request has been submitted to the Natural
Resources Conservation Service (NRCS). Once the rating has been completed, we
will submit the rating and forms to be included in this report. The letter and forms
requesting the rating is included in Appendix A.
3. Land Characteristics
The land adjacent to the proposed sewers is developed as residential lots. The
gravity portion will be constructed within sewer easements between twelve (12')
to twenty feet (20') wide. There will also be a temporary construction easement
approximately twenty feet (20') wide. The temporary construction easement will
be used to store material, equipment, and dirt spoils during construction. A small
portion of the force main route, approximately 400 feet, will be in an undisturbed
area. This area consists of small trees and some brush. The construction corridor
for the force main will be approximately fifteen feet (15') wide. The route was
chosen to minimize the amount of impact to the undisturbed areas. The disturbed
area will be limited to what is necessary to construct the sanitary sewers.
A creek crossing of Battle Creek with a six-inch (6") force main will be required
to complete the project. The creek crossing will be approximately 40 feet. The
force main will be installed by open cut, and will be encased in concrete. The
force main is being installed perpendicular to creek to limit the amount of
disturbed area. Alternate routes were studied to eliminate the crossing, however
none were possible.
Also, the two lift stations are located in undisturbed areas. Both of the lift station
sites have small trees and brush that will be removed. The disturbed area will be
limited to what is necessary to construct the lift stations. Photographs of the two
lift station sites are included in Figure 6.
4
Rev. October 26, 2007
. .
4. Karst, Bedrock, Hydric Soils
Soil types do not include karst, bedrock, or hydric soils and thus the proj ect will
not be adversely affected by such.
5. Siltation and Erosion
Any measures necessary to reduce both siltation and erosion will be implemented.
Erosion control measures have been shown on the plans, and will be implemented
during construction. Erosion control and siltation measures include the following:
a. The contractor will be required to install silt fence along all
ditches, creeks, or top of banks. All disturbed areas must be
covered with seed and straw as soon as practical, but no longer
than 14 days.
b. Natural vegetation will be retained wherever possible.
c. Excavations will be limited to rights-of-way and easements.
d. Appropriate best management practices, such as silt fence,
seeding, and mulching, will be implemented wherever possible
to control runoff throughout the project.
e. All surface drainage, including ditches and creeks, will be
returned to their pre-construction state as soon as feasible.
f. Roadways and driveways will remain stabilized during
construction as much as possible.
g. When possible, construction activities will be scheduled to avoid
excessively wet conditions.
h. No more than 100 feet of open trench will be allowed. Where
possible, excavated material will be kept on the upland side of
the trench. Excess materials will be used elsewhere on the
project, or removed from the site.
1. The existing topsoil will be reused during the restoration where
possible.
J. If necessary, discharge from dewatering may be directed to silt
fence or a straw check dam prior to discharging into the
surrounding surface waters.
D. Hydrology
1. Creek Crossings
A creek crossing of Battle Creek with a six-inch (6") force main will
be required to complete the project. The creek crossing will be
approximately 40 feet. The force main will be installed by open cut,
and will be encased in concrete. Anti-seep collars will be installed on
both sides of the creek crossing to prevent groundwater from
5
Rev. October 26, 2007
draining into the sewer trench. The force main is being installed
perpendicular to creek to limit the amount of disturbed area.
Alternate routes were studied to eliminate the crossing, however
none were possible. A photograph of the creek crossing location is
included un Figure 6.
2. Floodplain
The project is situated near a known floodway. All above ground
components have been placed at elevations to minimize flood
hazards. Also, all manholes require bolt down, watertight lids. The
flood map for the project area is provided as Appendix C.
3. Water Supply
A portion of this project is near water wells on the IDNR property.
The sanitary sewer lines have been designed to maintain the
minimum distance of 50 feet from all wells. Also, IDNR is currently
under design to relocate the existing wells further away from the
sewer project.
E. Groundwater
Soil borings were taken throughout the project, and groundwater was not
encountered.
F. Natural National Landmarks
Construction and operation ofthe proposed project will not impact Natural National
Landmarks.
G. Coastal Zone Program
The proposed activity complies with Indiana's approved coastal management
program and will be conducted in a manner consistent with such program.
H. Historic, Architectural and Archeological Sites
There are no known historic, architectural or archaeological sites that will be
impacted by this project. No architectural features of any sites will be affected. All
work activities will be limited to rights-of-way and easements. A map of historic
features is included as Figure 4. An archaeology study is being completed for the
project area. An archaeological report will be submitted once it has been finalized.
6
Rev. October 26,2007
I. Induced Impacts
The City through the authority of the sewer board, or planning commission will
ensure the future development, as well as future collection system or treatment
works projects connecting to SRF funded facilities, will not adversely impact
wetlands, archaeological/historic/structural resources, or other sensitive
environmental resources. The City will require new development and treatment
works projects to be constructed within the guidelines of the U.S. Fish and Wildlife
Service, IDNR, Indiana Department of Environmental Management (IDEM) and
other environmental review authorities.
J. Air Quality
Construction activities may generate some noise, fumes and dust normally resulting
from such activity. The adverse impacts caused by dust may be alleviated by
periodically wetting the exposed soil and unpaved roadways. To reduce noise
impacts, construction will be limited to daytime hours. The dust, fumes, and noise
are all short-term impacts, and will last only throughout construction. Construction
activities should not impact ozone, airborne pollutants or other current or future air
quality concerns.
K. Open Space and Recreational Opportunities
The proposed project's construction will neither create nor destroy open space or
recreational opportunities.
VI. SELECTED PLAN
A. Proj ect Description
Installation of a gravity sewer system with two lift stations is the recommended
alternative. Figures 1 and 2 show the proposed layout. Sanitary sewers will be
installed along Longview Beach Drive, Conservation Drive, and Upper River Road.
Installation of the sewers will be in the road rights-of-way and sewer easements. The
sewers will discharge into an existing gravity sewer. Based on capacity studies, there
is sufficient capacity in the existing sewer lines and system.
B. Proj ect Phasing
Completion and operation of this project will neither benefit nor hinder the
completion of any other projects proposed in the City of Jeffersonville's PER. The
City has bid this project as an individual project.
7
C. Preliminary Design Summary
Rev. October 26,2007
The proposed improvements are shown on Figures 1 and 2. The design of this project
is based on the 10 State Standards, IDEM policies, and accepted engineering
standards and practice. A final design summary for this project is as follows:
12" SDR 35 Sanitary Sewer
12" SDR 26 Sanitary Sewer
8" SDR 35 Sanitary Sewer
8" SDR 26 Sanitary Sewer
6" Force Main
2" Force Main
Manholes
Lift Stations
Property Connections
1,600 LF
3,031 LF
2,123 LF
1,235 LF
4,685 LF
1,032 LF
31 Each
2 Each
75 Each
Please note, the quantities shown on the two permits for these projects were based on a
preliminary design. The quantities above, including the property connections, are based
on the final design.
D. Project Cost
The estimated cost and itemized breakdown is shown on Table 1.
E. Project Schedule
Advertise for Construction Bids
Bid Opening
Submit PER to IDEM
Submit Plans & Specs to IDEM
IDEM Approval of PER
SRF Loan Closing
Contract Award Approval
Begin Construction
Substantial Completion
Initiation of Operation
F. Land Acquisition
June 2007
June 2007
October 2007
October 2007
November 2007
December 2007
December 2007
December 2007
June 2008
July 2008
Most of the sewer is located within the road rights-of-way. Easements will be
required along the IDNR property, and Conservation Drive. All easement acquisition
is being accomplished by donations, and will be completed prior to construction.
8
Table 1
Estimated Project Costs
Longview Beach Sanitary Sewers Installation and
Septic Tank Elimination
Rev. October 26, 2007
Item Approx. Unit Unit Price Total
Crushed Limestone 0 TON $ 16.00 $
Bank Run Sand 0 TON $ 16.00 $
Formed Conc. Non-Reinforced 0 CY $ 400.00 $
Non-Formed Cone. Non-Reinforced 0 CY $ 300.00 $
Reinforcing Steel 0 LBS $ 1.25 $
Sod 0 SY $ 4.50 $
Seed, Fertilizer and Mulching 0 SY $ 0.75 $
8" SDR 35 San. Sewer 2123 LF $ 52.28 $ 110,990.44
8" SDR 26 San. Sewer 1235 LF $ 105.00 $ 129,675.00
12" SDR 35 San. Sewer 1600 LF $ 38.00 $ 60,800.00
12" SDR 26 San. Sewer 3031 LF $ 42.00 $ 127,302.00
6" Force Main 4685 LF $ 33.99 $ 159,243.15
2" Force Main 1032 LF $ 10.69 $ 11,032.08
Manhole Type '8' 19 EA $ 3,100.00 $ 58,900.00
Manhole Type 'C' 9 EA $ 2,900.00 $ 26,100.00
Manhole Type 'E' 3 EA $ 6,500.00 $ 19,500.00
Air Release Valve 2 EA $ 4,800.00 $ 9,600.00
Property Connection
12" x 6" Wye 41 EA $ 1,800.00 $ 73,800.00
8" x 6"Wye 34 EA $ 1,800.00 $ 61 ,200.00
Anti-Seep Collar 4 EA $ 720.00 $ 2,880.00
Concrete Encasement 70 LF $ 25.00 $ 1,750.00
LVB Pump Station (Two 176 gpm Pumps) 1 LS $ 188,000.00 $ 188,000.00
URR Pump Station (Two 20 gpm Pumps) 1 LS $ 45,500.00 $ 45,500.00
HMA Surface 1055 TON $ 60.00 $ 63,300.00
HMA Intermediate 256 TON $ 54.00 $ 13,824.00
DGA, No. 53 775 TON $ 30.00 $ 23,250.00
7' Chain Link Fence 4350 LF $ 13.79 $ 59,986.50
Double 8' Wide Gate 1 EA $ 1,300.33 $ 1 ,300.33
Construction Entrance 1 EA $ 1,100.00 $ 1,100.00
Stream Bank Restoration 200 SY $ 11.30 $ 2,260.00
Silt Fence 4300 LF $ 2.00 $ 8,600.00
Construction Stakeout 1 LS $ 7,000.00 $ 7,000.00
Removal of Fence 1 LS $ 6,700.00 $ 6,700.00
Removal of Poles 1 LS $ 5,800.00 $ 5,800.00
Subtotal $ 1,279,393.50
Contingency (10%) $ 127,939.35
Subtotal Construction Costs $ 1,407,332.85
Inspection/Construction Engineering $ 172,000.00
Total Project Costs $ 1,579,332.85
Less Resident Contribution to Construction $ (480,000.00)
TOTAL $ 1,099,332.85
Aaron\0642\0642 Table 1-Estimate.xls.xls{Table 1 rev}
S:\Jeffersonville PERIPER DOCUMENTSISRF PROJECT FINANCING INFORMATION-L VB.docllOl707
GRAPHIC SCALE
1.500 0
~.....,
750
I
1.500
,
3.000
I
( IN FEET )
1 inch = 1500 ft
WETLAND MAP
LONGVIEW BEACH SEWER
PRELIMINARY ENGINEERING REPORT
CITY OF JEFFERSONVILLE, INDIANA
DATE
OCT. 15, 2007
REVISED:
OCT. 29, 2007
e
~
FIGURE 3
2-944-025
.
NORTHERN PART
E
c&
""
~
I
r-..
2
C\i
0)'
C\i
8
SOUTHERN PART
q;
&
~
"tl
I
~
-
GRAPHIC SCALE
~
.-
~
~
~
~
Cl
e5
ll.:
.-
ei
ll.:
10,000 0
~-~
10,000
I
( IN FEET )
1 inch = 10,000 ft.
5,000
I
20,000
I
'"
;::::
.s
<::
o
~
~
"-'
J
Vi
~
l.;:
PRELIMINARY ENGINEERING REPORT
CITY OF JEFFERSONVILLE, INDIANA
DATE
OCT. 29, 2007
e
~
JEFFERSONVILLE WWTP . SERVICE AREA
FIGURE 5
GRAPHIC SCALE
F..-~
750
I
f~
( IN FEET )
1 inch = 1500 ft.
JEFFERSONVILLE COLLECTOR SYSTEM IMPROVEMENTS
PHOTO ORIENTATION MAP
PRELIMINARY ENGINEERING REPORT
CITY OF JEFFERSONVILLE, INDIANA
i~
DATE
OCT. 29. 2007
e
,
---
FIGURE 6
......
~ Q)
.....
.....
..... en
6"n CZl
l=l ....:I
0 '"g
....:I
OJ) ~
l=l
0 ~
~ ;:.-
Q) ~
-a I-<
8 Q)
0-
l=l 8-
.a
s Q)
Q) -S
2 ~
0
~ OJ)
s::
~ ;Q
Q) 0
-S 0
-
.....n .....n
en
en c;j
Q)
~ .~ ~
OJ)
gfo s::
.....
.u ~ ~
c;j u ~
~ c;j -<i
Q)
C'io::l
Q)
-S
S
~
Q)
.....
.....
CZl
CZl
....:I
o::l
>.g
....:1-
Q)u
-S s::
..... .8
c;j ~
gf~
;Q ~
o s::
o 0
-U
.....n Q)
en ....
Q)'+:i
~ 0
OJ).....
.s 8
~ ~
~~
- ~
~
Q)
.....
~
8
s::
.....
c;j
S
Q)
U
I-<
o
~
~
Q)
-S
~
OJ)
s:: .
:..;;;l~
o Q)
o e
-u
.....n Q)
en_
~~
~o::l
'+=ll.+-<
~ 0
o OJ)
CZl s::
OJ) .....
l=l ~
.u 8
c;j u
~ Q)
~-S
APPENDIX A
· Letter from Clark County Health Department
· Letter and forms sent to NRCS
Clark County Health Department
1320 DUNCAN A VENUE
JEFFERSONVILLE, INDIANA 47130
812-282-7521
September 25,2007
Mayor Robert L. Waiz, Jr.
500 Quartermaster Court
Jeffersonville, IN 47130
Re: Longview Beach Road
Dear Mayor Waiz:
It has come to the attention of the Clark County Health Department the properties along Longview Beach
Drive may be eligible for grant money for installation of sanitary sewers. This area was developed several
decades ago with septic system as the means of wastewater disposal. Since that time the rules and
regulations concerning residential land development has changed both with this office and the Clark
County Plan COmmission. .
The lots within this area are one quarter (0.25) of an acre which is approximately one quarter (0.25) the
size required (0.918 of an acre) by the plan commission for residential home development. This has
caused the use of septic systems very difficult to implement due to extremely small yard space left 'on
these sites for installation and practically no other areas for repairs to septic system when and if these
systems fail.
It is the policy of this office to recommend sanitary sewers for wastewater disposal whenever available.
Centralized wastewater treatment is a more viable and long term solution to areas of consolidated
population where septic system failures can create a more substantial threat to the public's health.
This department supports all efforts to provide sanitary sewer connections to all areas of Clark County. If
you have any questions about this subject, please call me at the Clark County Health Departmeat.
Respectfully,
~l('~^^, ~ ~
Kevin Burke M.D.
Clark County Health Officer
Cc: Jorge Lanz
JACOBI, TOOMBS AND LANZ, INC.
CONSULTING ENGINEERS
e
~
120 Bell Avenue
Clarksville, Indiana 47129
(812) 288-6646 (812) 288-6656 Fax
October 15,2007
Lisa Bolton
Natural Resource Conservation Service
6013 Lakeside Blvd.
Indianapolis, IN 46278
RE: City of Jeffersonville
Preliminary Engineering Report - Longview Beach Sewers
Ms. Bolton:
The City of Jeffersonville is submitting a Preliminary Engineering Report to the State Revolving
Loan Fund (SRF) to request funds for sewer construction to serve the residents ofLongview
Beach. As a part of the approval from the SRF, the City is required to complete a Farmland
Conversion Impact Rating Fonn AD-I006. As such, included with this letter is the completed
fonn and necessary soils map identifying the location of the proposed project. The majority of
work to be completed under this project will occur in previously disturbed areas.
Should you have any questions regarding this project or the contents of this letter, please do not
hesitate to contact our office.
incerely,
COBI, TOOMBS
S:\Jeffersonville PER\JeffPER - NRCS lO-12-07.doc
, J
Soil Map-Clark County, Indiana, Jefferson County, Kentucky, and Oldham County, Kentucky
(LONGVIEW BEACH PER)
616000
616800
617600
618400
619200
620000
620800
N
A
o
soo
1,000
2,000
Meters
3,000
2,000
4,000
8,000
Feet
12,000
USDA Natural Resources
~ Conservation Service
Web Soil Survey 2.0
National Cooperative Soil Survey
10/12/2007
Page 1 of 4
U.S. Department of Agriculture
PART I (To be completed by Federal Agency) Date Of Land Evaluation Request
'lame Of Project Longview Beach PER Federal Agency Involved EPA through State Revolving Fund
L
Proposed Land Use Sewer Construction County And State Clark County, Indiana
PART II (To be completed by NRCS) . Date Request Received By NRCS
Does the site contain prime, unique. statewide or local important farmland? Yes No Acres Irrigated/ Average Fann Size
(If no, the FPPA does not apply - do not complete additional paris of this form). 0 0
Major Crop(s) '- . Farmable Land In Govt. Jurisdiction Amount Of Farmland As Defined in FPPA
Acres: % Acres: %
Name Of Land Evaluation System Used Name Of Local Site Assessment System Date Land Evaluation Returned By NRCS
PART III (To be completed by Federal Agency) Alternative Site Ratina
Site A SiteS Site C Site 0
A. Total Acres To Be Converted Directly 0.2
B. Total Acres To Be Converted Indirectly 13.3
C. Total Acres In Site 13.5 0.0 0.0 0.0
PART IV (To be completed by NRCS) . Lal'ld Evaluation Information
A. Total Acres Prime And Unique Familand .., .-'c
B. Total Acres Statewide And Local Important Farmland
C. Percentage Of Fannland In County Or Local Govt. Unit To Be Converted
D. Percentage Of Farmland In Govt. Jurisdiction With Same Or Higher Relative Value
PART V (To be completed by NRCS) Land Evaluation Criterion 0 0 0 0
Relative Value Of Farmland To Be Converted (Scale of 0 to 100 Points)
PART VI (To be completed by Federal Agency) Maximum
Site Assessment Criteria (These criteria are explained in 7 CFR 658.5(b) Points
1. Area In Nonurban Use
2. Perimeter In Nonurban Use
3. Percent Of Site Being Farmed
4. Protection Provided By State And Local Government
5. Distance From Urban Builtup Area
6. Distance To Urban Support Services
7. Size Of Present Farm Unit Compared To Average
8. Creation Of Nonfarmable Farmland
9. Availability Of Farm Support Services
10. On-Farm Investments
11. Effects Of Conversion On Farm Support Services
12. Compatibility With Existing Agricultural Use
TOTAL SITE ASSESSMENT POINTS 160 0 0 0 0
PART VII (To be completed by Federal Agency)
Relative Value Of Farmland (From Part V) 100 0 0 0 0
Total Site Assessment (From Part VI above or a local 160 0 0 0 0
site assessment)
TOTAL POINTS (Total of above 2 lines) 260 0 0 0 0
I Date Of Selection Was A Local Site Assessment Used?
Site Selected: Yes 1:1 No rJI
FARMLAND CONVERSION IMPACT RATING
Reason For Selection:
(See Instructions on reverse side)
This form was electronically produced by National Production Services Staff
Form AD.1 006 (10-83)
Soil Map-Clark County, Indiana, Jefferson County, Kentucky, and Oldham County, Kentucky
(LONGVIEW BEACH PER)
616000
616800
617600
618400
619200
620000
620800
N
A
o
500
2,000
1,000
2,000
Meters
3,000
o
4,000
8,000
Feet
12,000
USDA
~
Natural Resources
Conservation Service
Web Soil Survey 2.0
National Cooperative Soil Survey
10/12/2007
Page 1 of4
~
o
:)
"E
~
>;
"E
:)
o
o
E
cu
.c
"t:l
o
"t:l
c:
cu
>;~
150::
:)w
"Ea.
~tj
~~
3m
03:
Ow
55
r!!G
~z
Q)O
-,::::!.
cO
c:
cu
'5
-=
>;
"E
:)
o
o
-t!:
cu
(3
!.
cu
~
.0
U)
z
o
i=
<(
:!!:
D:::
o
LL
~
ll.
<(
:E
cD G3
~ ~
CIlQ)o.
5:5 0
~~:::
g~m
.g ~-;j
2"~g.
~iU'E
~Eti
~ Qih m
~ > c::
o.~o
~0J!
Q).c cu
~ailil
~~m
Q)CIl.o
-;j g>~
0.; ......
cu c: c:
E.;:: 0 .
>tQ.~.!!}
Cl) -g ~ ~
2:CUQ)E
~.!!:! ~ ~
'5BJ!ijl
CIl CIl a. cu
- 0)....: Q)
~ .5: ~ E
:~ ~ :!21 g.
05l5E
21 ~
._ 0)
2: ai
Q)"t:l
U)CIl
:)
c: .
.2 11
7a C:
2: :>.
Q) Q)
CIl 2:
c: :)
o CIl
O:=z
CIlotC)
21Jl--
... Q) Q)
5 ~ g
~ iiN
o::::::~
_.ct-
~ ::l
:) ..
-...J
~ 0:: ..
::lE
>.2
'. Q) CIl
0.2:>'
cu:)U)
~U)Q)
.... -
0:= cu
21~:a
:i.o(s
~~8
Gi
.c
o
'"
f
.a
...
~~
Gl :;
C "
:::i
iii
.u
Gl
Cl.
I/J
Q)
Cl.
o
c;;
Co
Q)
.g!
I/J
1::
o
.c
I/J
'""
a..
;=
e
o
OJ
....
o
CIl
cu
cu
1ii
"t:l
"t:l
Q)
l;::
:e
21
U)
o
0::
Z
~
U)
::l
Q)
=;ii
E 0
0-
... Q)
.....0
"t:l"t:l
Q) Q)
C5U;
03=
c: ~
Q)~
O)Q)
.!l! ca
_"t:l
o c:
:) 0
"t:l ._
e ~
o.Q)
CIl >
.- Q)
.:::;
caS
Q) cu
"'0
<( cu
>'Q)
Q) ...
2:<(
:)>.
U) Q)
._ 2:
o :)
U)U)
I"-
o
CIlo
C:C\I
CIl _
'5"<t
c: 0.
:~
"E -
:)ClO
o <:
o 0
-c .~
.!!!~
o
a:
Oi
>
~
"
o
18I * . X .:
@J) -< ~ ~ @ @ >
>.
.><:
o
21"-
C:o
Q)O
~C\I
~T-h
Co
50
o C';
<: c:
g .2
G1 ~
~~
-,
.. iti
cu-
~~
<(cu
>'Q)
Q) ...
2:<(
:)>.
U)Q)
._ 2:
o :)
U)U)
Ul
CIl
i!'
<(
c:
Ol
.c
:s
'"
c:
Ol
III Q)
E 8
.s
...
Gl
lL
..
Gl
~
~tC)
00
:)0
"EC\I
Q) -
~~
->.
.?:-CIl
5:!:
o -
OM
E g
CU .-
.cr!!
"2~
o
m€1l"t:l ~
lii~~lijcu
>'~-CIl->.
Q)~CQ)Q)
2: CIl Q).- 2:
::sO~1:::::'::s
~ 2 ~ 8.~
'0 ~ ii ~ ~
~~1ii:=gj
5:Co~e
r::1UU)(/)~
gal~:gQ)
Q)o.:;:;E~
og.'E~g>
EE~:!:~
~~~5"*
"t:lQ)"t:lo.c:.
.2.o-cuE
g~~E8
.- CIl "t:l c:
::::::-.r. c: "- ...
o >. .-E =: 0
<( cu :) c:
~ E .E ~ .g
~ ~ Q) ~-
L;. Q) (I) co (\1
.!!~::JE:5
.5: ~ -g en ~
'0 ~ .!!! ~ .Q u)
co ::J 'E . E .~
*~~~~~
~ ~~~ ~5
o.c"C,-_o
>- t- CIl 0 .5: .0
j ~ ~
0::
Ul
>-
~
.c
Cl
J:
.g!
.l!l
f!!
Q)
E
Gi
~
rn
'c
c:
i!'
Q)
a..
ClO
m
m
--
0)
c:
Q) @
... .c
~ -g ~
en ::s g
.~ ~.E
-..>:: Q)
.0 lil E
CIl .0 0
a.l a.l CIl
.c ..c _h
~-E:;
o CIl
:ce~
~...cu..
c:: ~ (/) c::
o~<(~
g.'5 &~
E~cua.l
Q){lE.o
~.g~iU'
~ Ci.~ E
:S ~ ~ .~
O.!:::i 0 n;
o:s,-g-g
0:0 >.:)
o"tJ~o
..c:: c: 0..0
Q. cu .!l! ;t:
O"t:l "t:l c:
..c:: a.l ~:)
t:=a.lo.
o o.O)cu
a.l E cu E
~ 8.~ '0
Ul
'0
Ol
o
a::
Gi
.c
i5
Q)
o
.c
"'"
c:
U3
.9-
c;;
o
Q)
:Q
c;;
I"-"<t
0....
00
~C\I
C\I Q)
~Ol
o cu
--a.
>.
Q)
2:
:)
au)
c-.i'5
>.u)
~ ~
::s+:;;
U)~
.- Q)
00.
U) 0
.0 0
Q)O
3:(ij
c:
.2
1ii
z
(5
Co
I/J
u
'C
o
I/J
(5
Co
I/J
>-
c:
o
(jj
Ol
i!'
<(
.0
Co
I/J
CD
U
CIl .~
CD CD
~U)
::I l:
o 0
m;
o::~
~ CD
::I III
1a 5
zo
(5
Co
I/J
>-
c:
o
(jj
e:-
~
(5
Co
I/J
~
.I!l
'c
::J
Co
Ol
::;
'0
l/)
III
E
.s
~ '5
lLo 0;=
E
.0 10
a..
iii
'2 Zi
Cl.
I/J
Gi
.c
i5
III Ul
! :: ~
.a ..... (3
= ii
lL Co
"ii 'u
u .c ..
E ~
"0 ""
a..
[f]
(5
Co
I/J
~
Oi
>
~
"
iE
'0
c:
Ol
-'
.. iti
CIl-
a.l cu
"'0
<( CIl
>'a.l
a.l ...
2:<(
:)>.
U) Q)
._ 2:
o :)
U)U)
Ul
rn
c:
Ol
U
'0
<:
Ol
Ul
E
Ol
i!'
(jj
!!l
c 'm
:8 c::
...
1::
o
Cl.
III
C
l!!
I-
M
m
m
--
-i::i
a.l
.c
0.
~
0)
o
"0
..c::
0.
~
~
CIl
Q)
0)
CIl
.~
(ij
Qj
cu
Ul
2'
cu
o
Ul
.sl
:J
o
0::
I/J
::J
Ul
>-
~
.c
Cl
J:
Q)
m
(jj
Ul
'0
lU
o
a::
rn
u
o
-'
<> ,Q.,~
III
<;)
c
z
w
C>
W
..J
ll.
<(
:E
e .. ..
o
$
1i5
i!'
Q)
o ~
~ ~
t) ~
E <(
oS
.s
...
~ 0 ~
<( I/J
(5
Co
I/J
>-
Ol
C3
c:
o
.0;
'"
i!'
Q.
a.l
o
"0
a.l
'"
o
13
I (
;=
o
u::
Ol
>
Ol
-'
e:-
:;;
:J
o
o
Q)
c:
::E
~
.g!
~
Ul
:J
o
Q)
c:
.!!!
~
Ul
::E
Co
e
.B
:J
o
"'"
u
o
a::
(5
Co
l/)
'0
Q)
'0
e
UJ
>-
~
Q)
>
Q)
I/J
~l'
.c
f!!
Ol
::;
(5
Co
I/J
Q)
.~
rn
I/J
15
Co
I/J
>-
'0
c:
Ol
I/J
+
III
..
Soil Map-Clark County, Indiana, Jefferson County, Kentucky, and Oldham
County, Kentucky
LONGVIEW BEACH PER
Map Unit Legend
Clark County,lndiana (IN019)
Map Unit Symbol Map Unit Name Acres in AOI Percent of AOI
CcaG Caneyville-Rock outcrop 372.6 34.3%
complex, 25 to 60 percent
slopes
CspB2 Crider silt loam, 2 to 6 percent 60.8 5.6%
slopes, eroded
CxgC3 Crider-Haggatt complex, 6 to 12 38.1 3.5%
percent slopes, severely
eroded
CxhC2 Crider-Haggatt silt loams, 6 to 36.7 3.4%
12 percent slopes, eroded
CxmC2 Crider-Haggatt silt loams, karst, 1.5 0.1%
rolling, eroded
CxnC3 Crider-Haggatt complex, karst, 31.3 2.9%
rolling, severely eroded
EesA Elkinsville-Millstone silt loams, 80.8 7.4%
o to 2 percent slopes
EesB Elkinsville-Millstone silt loams, 134.5 12.4%
2 to 6 percent slopes
EesC2 Elkinsville-Millstone silt loams, 2.4 0.2%
6 to 12 percent slopes,
eroded
EesD2 Elkinsville-Millstone silt loams, 5.8 0.5%
12 to 18 percent slopes,
eroded
EesFQ Elkinsville-Millstone silt loams, 22.9 2.1%
18 to 40 percent slopes,
rarely flooded
GykD2 Grayford silt loam, karst, hilly, 0.8 0.1%
eroded
HcgAW Haymond silt loam, 0 to 2 0.0 0.0%
percent slopes, occasionally
flooded, very brief duration
HtwD2 Haggatt-Caneyville silt loams, 11.8 1.1%
12 to 25 percent slopes,
eroded
HtzD3 Haggatt-Caneyville complex, 25.5 2.3%
12 to 25 percent slopes,
severely eroded
HufAK Huntington silt loam, 0 to 2 67.3 6.2%
percent slopes, occasionally
flooded, brief duration
HuhD2 Haggatt-Caneyville silt loams, 9.2 0.8%
karst, hilly, eroded
Pml Pits, quarry 68.5 6.3%
RtcB2 Ryker silt loam, 2 to 6 percent 5.5 0.5%
slopes, eroded
USDA
=
Natural Resources
Conservation Service
Web Soil Survey 2.0
National Cooperative Soil Survey
10/12/2007
Page 3 of4
Soil Map-Clark County, Indiana, Jefferson County, Kentucky, and Oldham
County, Kentucky
LONGVIEW BEACH PER
Clark County, Indiana (IN019)
Map Unit Symbol Map Unit Name Acres in AOI Percent of AOI
RztC2 Ryker-Grayford silt loams, 6 to 12.8 1.2%
12 percent slopes, eroded
UnpA Urban land"Udarents, loamy 14.8 1.4%
substratum, complex,
terrace, 0 to 3 percent slopes
W Water 67.9 6.3%
Jefferson County, Kentucky (KY111)
Map Unit Symbol Map Unit Name Acres in AOI Percent of AOI
W Water 11.4 1.0%
Oldham County, Kentucky (KY185)
Map Unit Symbol Map Unit Name Acres in AOI Percent of AOI
W Water 2.0 0.2%
Totals for Area of Interest (AOI)
1,085.1
100.0%
USDA
=
Natural Resources
Conservation Service
Web Soil Survey 2.0
National Cooperative Soil Survey
10/12/2007
Page 4 of 4