HomeMy WebLinkAboutStrand report 060507 Sewer board meeting (2)
City of Jeffersonville
Summary of Ongoing Public Works Projects
Strand Associates, Inc.
June 5, 2007
1. Long Term CSO Control Plan Revisions & Consent Decree Negotiations (5.944.029't 030)
· Early Action Projects - EPA and IDEM concurrence with early action projects has been received.
Sewer Board should proceed with any EAP not tied to PER approval.
· Gantt Chart - EP A review/Revisions to L TCP Gantt Chart BLA is providing routine updates to
the schedule. Monthly review of Gantt chart is recommended.
· EPA/DOJ/IDEM - Meeting held 5/15. Next meeting to be scheduled.
2. Preliminary Engineering Report - IDEM review continues.
3. CMC Pump Station Final Design/Bidding/Construction
· Bids were received May 29. A separate report will be submitted on the review of bids.
· Task order for Strand is recommended for bidding and construction phase services. JTL will
provide construction observation. A recommendation will be sent bye-mail before the
meeting.
4. CSS Flow Metering Construction (5.944.031)
· Meter and telog installation is complete.
· Meter programming and start-up was complete on May 22. A separate memo was sent to
Board (attached). A few adjustments will be required.
· Telog training is scheduled for June 12.
· The new server/computer/firewall is now in place.
· The City may benefit from a short-term contract with an outside company to provide
additional training and assistance during this critical time of data collection. The above
referenced memo suggested weekly expenses of $1500 would cover a company like Hydromax
to perform that service. Duration of effort could be kept to 4-6 weeks.
5. Local Limits Evaluation (5.944.032)
· Data evaluation has begun.
· Discussing Water Quality Standards and recent change of the outfall designation with IDEM.
· On target to meet September deadline.
Respectfully Submitted,
STRAND ASSOCIATES, INC.
//vtJ
Mark A. Sneve, P.E
I have attached our [mancial progress through April 30.
Sl
STRAND
ASBOClATE-S INC.
~.~ :--..,,: .(~ ~ 1-': F: ~ ,';I: ~::
MAS:das\S~\05\90 1-950\944\024\ Wrd\Sewer Bd Exec Sum\2006\JefiSewerBdExecSum060507.doc/05/29/07
, ,'\,
S!
STRAND
AssocrATES. lNC....
ENGINEE~G
D Information Only
MEMORANDUM
~ Project Specific 5944031
D Policy Memo - File With
TO:
FROM:
DATE:
RE:
Jeffersonville Sewer Board, Jolm Hall (JTL Observer), & EMC
Jolm Herriford & Mark Sneve
May 23, 2007
City of Jeffersonville CSO Flow Meter Update
On May 22, 2007, the contractor (Aqua Utilities), Malcolm Robertson (Sigma flow meter
representative), two representatives from Hydromax USA (hired by Malcolm for support), Mike Griffin
(EMC), Michael Meyer (EMC), Jolm Hall (JTL observer), and Jolm Herriford (Strand engineer)
conducted field visits to check the installation at each of the CSO flow metering sites.
The purpose of the field visits were to
(1) set up each flow meter to begin data collection,
(2) verify the proper installation and calibration of each flow meter, and
(3) conduct training on the Sigma flow metering software.
Training on the Telog cell phone telemetry software is scheduled for June 12.
All eleven (ten eso flow meters and the 96...inch outfall flow meter) were successfully set up to begin
data collection. Set up included programming the sewer diameters, programming data collection
parameters (level, velocity, and flow rate), programming the data collection interval (5-minutes), and
turning the meters on.
Several issues were identified while verifying the proper installation and calibration of the flow meters.
. The meter on CSO 006 (Riverpointe) was offset 6 inches from the sewer invert because of
sediment in the bottom of the sewer. It was recommended that the sediment be removed and the
meter be installed at the sewer invert so that lowest measurable flows may be obtained.
. Review of the installation pictures identified several transducer/probe cables that were not
sufficiently tied off to the mounting rings. The cables should be sufficiently tied to the mounting
rings to minimize debris collection and minimize hydraulic disturbance. It was recommended all
of the cables be verified for proper tie off except where verifiable by the installation pictures.
. The meter on the 96-inch outfall (Cane Run) was measuring negative velocities and is suspected
of being installed backwards.. Unfortunately, the individual from Aqua Utilities who actually
installed the meters was not present during the field visit and therefore could not answer specific
installation questions. It was recommended that all meters be verified to be pointing in the
upstream direction. Data from the first overflow event may be necessary in order to confirm.
\\saitou I \ V 011 \SDA T A \05\901--950\944\031 \ Wrd\Field CSO FM Visit Memo 052307.doc
i
'"
Page 2
[Date]
. Aqua Utilities indicated all of the meters were calibrated to a zero depth at atmospheric pressure
prior to installation. This technique was approved by Malcolm. However, half of the meters
were measuring flow depths as high as 24 inches during initial set up, which was highly unlikely
especially given the dry conditions. These meters were recalibrated to 0 inches of flow depth
without knowledge of possible standing water. It was recommended that all meters be verified
for proper flow depth calibration.
. The meter on CSO 013 (Graham) was installed in the wrong location (downstream of a
stormwater connection). It was recommended that the meter be moved to upstream of the
stormwater cormection so only CSO flow is measured.
. The mounting of the flow meters and telemetry units could be improved upon. The flow meters
and telemetry units were tied together making changing of the batteries difficult or impossible.
Several of the flow meters and telemetry units were mounted far from the street surface making
routine maintenance more difficult. Loose wires could be found at most sites. It was
recommended that all of the flow meters and telemetry units be remounted in such a way as to
better allow for the changing of batteries.
The training of the Sigma flow metering software was attempted back at the WWTP after the field visits
using a spare flow meter brought by Hydromax~ The Sigma software was installed on the new flow
metering laptop. There was a problem with either the spare flow meter or the cOlUlection cable adaptor
and no training was given. The laptop was handed over to EMC. The Sigma flow metering training
should be rescheduled to coincide with the future Telog cell phone telemetry training
The system should be completely operational before the Telog cell phone telemetry software training
(currently scheduled for June 12) is conducted.
EMC has been trained to change the batteries and should begin changing the batteries in both the flow
meters and telemetry units every two - three weeks (Malcolm's recommendation). Expected battery
usage is 572 ($3,500) per year. Frequency can be adjusted with experience.
This system will require a dedicated effort by EMC to maintain. The quality of the data obtained from
open channel flow meters is dependent on the experience of the maintenance personnel, the persistence
of the field crews regarding the maintenance, and the quality of the maintenance. It is recommended
Confined Space entries be made at each site every week to inspect, clean, and perform additional
maintenance as necessary on each meter. Inspection frequency may be reduced over time as the system
demonstrates successful operation. The City of Jeffersonville may consider hiring experience personnel
to initially assist EMC in maintaining the meters. The City and EMC would benefit from the additional
training. If the city retained a company (like Hydromax) to assist with the transition of this system to
EMC, weekly costs would be about $1500~ Costs could be reduced based on the duration of their
assignment. Given EPA's expectation regarding collecting good flow data and updating the LTCP, it
may be money well spent.
{InitialsJ\\sailou 1 \ Voll \SDA T A \05\901--950\944\031 \ Wrd\FieId CSO FM Visit Memo 052307.doc\052307
sa.
STRAND
ASSOC!A"l"ea.INc' ~
~ I : Q ~ .'\l '" F. R ~-:;.
en
t
w
s
p::
~
r:j~
~~ ~
(/J~
~U)
~~
)-4~
u~
0)000oi
~~
<00
Ow
~j
~~
o
rn
~
~
~
~
~
~
f-4~ i=.~ t:.'$.
I.I'l tl'l o ct)
zf-l ~...... N ~
~~
~~
~O
.c.cu
~~~ Ie:;:;" CO ~ Il"l
111 9""1 o U"')
~Z~ ",C"i <oriN
T'""'" Co() r- 0
~~~ N~ 1"'-.. ~o~
Ie aNN
ZO ~ l-
O~~
u =: tA- (Ao (Ao V>
~C\ c:o L.f"l.
t'-U"') O..q--
~Q r--:~ }!:j~
("I) v
~~ ('I) r- ~ ~
-'-:N' ~
foo4~
(A. V)o. (A< c,.q.
~~~ N
I)J t C'i"l
.....:;V;,....:: ~
fJ'JU.cz=.....:i 00 rt"'l
500; N ('o.t "d" oo~
~~~~ "T""" ......
t- ~
0 (1)0 Vi' (/)- en (Ao
~ .~
E3~ ..,0 ~ o.w
It'') co N ~u
c\ ot:fo::i C\ I--l
~~ T""" ("f11"'- ~o
N C'\ \Cl .q-", >-
C 6 t"j'"
i"') r- N~
CQ~ (1)0 V) V>(I)o~
~~~ N ...... 00 .,....l P
t-C\ 000 ~
~~ 0\0
'l""""'I \:::l
OO~ ~ U"} 0'1 l.J1 b
~~O T'"""'~ N cO 0
~ E-- ~
~ (Ao (Ao ~ (I)
!~ 00 0000
T""" 00 C"I. 0-
T""" oo::tLO 0
rt'l~ N~ ~
rt'l c::o
~~ (A. bQ< (Ao U).
~f-l T'""'" ~ >.0
co N 00 ,
~S~Ci} ......:r--: u-i
u 0- ~ C\ r-
~O~~ c:o \0 I"C")
'V~ C'f 00'"
~~~~ N
(I) <no V)- (I)-
t~
~Z o r- ~o
o r-
I-c~ o "T""'" C'\o
Lri'-..6 ~O
ZO N ('I"} ~~
O~ (I) V> (Ao(Ao.
u
t
~~ %~ ~ .f
~~ ::J ::J ::J ::J
0 0 0 0
:I::I: O:::I:
0
u
~
a v.
o c c
.c:z:: 0 0
~ . t:i ".c
t::
'J:l U
"C ~ e
t; u to:: 4..."
>:.) aJ c:: v.
c:: Z o c
~ "~ '.0 0
~ Q) ~U
~ ~ ~I
~ ~ u .. -.I u..
Q "'0 l-oI
~ o t!
c:: I: ~ IU
] ~ ~~
tn U ::::
~ c::
~ 0 f-+..9
I U ~u..
~O 00
~ en en U"J
U'::I U uu
o . U"'l ~ o "T""'"
~~ N N ("("l <"'l
0 0 00
~ ~ ~~
f-lO ~ ~ ~';'
tf.l ~ U') L.O t.f'1 It'l
r-
o
~
...........
N
N
-....
U"l
~
!
1C
2-
~
~
'ti
.2.
l
I
~
I
~
i
i
.
City of JeffersonviUe
CSO L TCP and Consent Decree Negootiatjons
Strand Associates Project Status
TASK
Status as of 4/30/2007
Strand Associates
-Actual
Hours Fee
Expenses separate
Strand Associates
- Budget
Hours Fee
Strand Associates
DID of bud !;let Spent
Hours Fee
PHASE A .. L TCP REVISIONS
Revise and Supplement Public Particioation
Consideration of Sensitive Areas
Monitoring Program
Collection System Characterization and Modeling
Receiving Stream Modeling
CSOOP UJHlates (Annually)
Alternative Analysis
Implementation Schedule/Financial Capability Anah
L TCP Modifications
Early Action Proiects
Meetings
Items outside of the initial ScoDe (1)
8th & Oh io Flooding Evaluation
Ealv Action Pro.iect Information to lTL
Public notification Program
Flood PS info for EPA
SUBTOTAL PHASE A LABOR
Expenses
TOTAL PHASE A
PHASE B.. CONSENT DECREE NEGOTIATIONS
Consent Decree
labor
Expenses
TOTAL PHASE B
TOTAL:{ESrr.MA ."Ef)}:EE..~~Phiise.A :andiB.~:;: ><:
(1) Total for additional services performed
2L75
15.00
63.75
18.50
7.00
23.75
16~50
174.75
174.75
$
1 807.61
18wOO
22.00
153.00
20.00
215.00
21.00
lS2~OO
0.00
222.00
0.00
892.00
892.00
304
64
5.00
o
o
o
304.00 $ 36,177
$
6,583
340/0
42010
68DIo
DOlo
00/0
560
00/0
7.50
$
$
$
$
$
1 625.59
$
$
1,766
2081
0010
5010
00/0
290/0
200/0
19010
19 olD
. . .. .:..;.233~50:.:. ::.$22;442~41...: .~:":.":. .:.1~196~D.O :.~ :..$:;.~. :..118,856;:. "~~:;...:".:<20Plo
27010
450/0
78010
00/0
DOlo
DOlo
00/0
60/0
DOlo
290/a
210/0
160/0
130/0
150/0
...: ~:_':~~;190/o~: ~
~~~Y~ip:r9J~~lt9~fuI~~~:Q:~':uhQ~.:lh~~~~)f.i~.:.$Jp.Io~q:q~"t~~i~~~~Jij2h~~~~:~.~tY)_~~~;~~~~9.H?~~~.J~yJ6~:.~s:~w~~H~~:~.f.dXt~~.*~;~~j):~~~~j!:~~~~:~~jh~~.t~:r~:~;~p.a~~~;U~~~)}mll~~;~j~:~Hrm
788.80
0.00
0.00
0.00
0.00
$
$
122.20
1.00
0.00
$
5;
0.00
$ 6 690.93
$ 1 913.78
$ 551.83
$ 2,023.63
$ 1 474.22
$ 16,998.59
$ 1,502.35
$16,998~59
58]5 $ 4,921.88
$ 521.94
58.75 $ 5,443.82
65.75 $ 5; 963.46
$
$
$
$
$
$
$
12,968
1,992
19,042
2133
12,589
$
22,965
$
$
$
$
$ 82,679.00
$
8268
$ 82,679
$ 31,177
$ 4 000