HomeMy WebLinkAbout04) Change Order #1 Gohmann Asphalt CHANGE ORDER - EXTRA WORK AGREE:MENT NO. 1 JOB NO. 9601 CE Project Name 10th STREET IMPROVEMENTS - PHASE 1 r'" i Contractor Gohmann Asphalt & Construction, Inc. You are hereby authorized to proceed with the following described change or extra work: As per attached documentation: 1. Use Plowable Fill at NE corner of Locust Street in order to fill in the undermined area under the existing concrete pavement found while installing the downstream end of Str. No. llB (2 cyd @ $100.00) = $ 200.00 r The method of payment for this change or extra work shall be: An additional amount of two hundred dollars and no cents = $200.00 Consulting Engineer: Date Owner's Approval: City of Jeffersonville Signature of Owner(s) Date Contractor's Approval: Gohmann Asphalt & Construction, Inc. r uthorized Representative Title Date