'Jacobi, Toombs and Lanz, Inc.
Consl,llting Engineers
120 Bell Avenue
Clarksville, Indiana 47129
Phone 812.288.6646
Fax 812.288.6656'
MEMO
To:
Robert L. Miller
City Engineer
Jorge 1. Lanz, P.E.
Court Avenue Extension
Final Change Order (No.2)
September 22, 2003
From:
Subject:
Date:
Enclosed is the final change order which needs Board of Works approval and signatures.
The final project construction costs are as follows:
("il
Original Contract
Chan~e Orders
Final Construction Cost
$
$
$
758,899.99
75,316.81
834,216.80
The change order amount of $75,316.81 includes $54,315.81 of paving added by the City.
Please call and I'll pick the executed original.
~~