PERIODIC PAYMENT REQUEST
NAME OF OWNER PAGE lof4
CITY OF JEFFERSONVILLE
BOARD OF PUBLIC WORKS AND SAFETY PAYMENT REQUEST
15
CONTRACTORS NAME AND ADDRESS PERIOD ENDING
FINAL PAY REQUEST
Gohmann Asphalt & Construction, Inc. DATE ESTIMATE PREPARED
P.O. Box 2428
Clarksville, IN 47131.2428 December 20, 2005
PROJECT TITLE
TENTH STREET RECONSTRUCTION
Amount of Original Contract & Change
PROJECT, PHASE 1 Orders
$1,456,466.81
BREAKDOWN OF PERIODIC COST ESTIMATE
BID QUANTITIES WORK PERFORMED TO DATE
ITEM
NO. ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE AMOUNT QUANTITY AMOUNT PERCENT
,
SEE ATTACHED BREAKDOWN
TOTAL WORK COMPLETED TO DATE $ 1,456,466.81
LESS CREDIT FOR AUXILARY BILLINGS $ (12,625.71)
LESS RETAINAGE: $ -
TOTAL EARNED LESS RETAlNAGE $ 1,443,841.10
LESS TOTAL PREVIOUSLY INVOICED $ 1,269,620.91
TOTAL DUE I $ 174,220.19 I
CERTIFICATION OF CONTRACTOR - I HEREBY CERTIFY that the work Perfonned and the materials supplied to date, as shown on this periodic cost
estimate, represent the actual value of accomplishment under the tenns of this contract in confonnity with approved plans and specifications; that the
quantities shown were properly detennined and correct; and that there has been full compliance with all labor provisions included in the contract identified
above, and in all subcontnacts made under that contract.
DATE CONTRACTOR'S NAME
December 20, 2005 Gohmann Asphalt & Construction, Inc.
BY Dennis Dixon S1G2 ~
ntle Project Engineer
.~ , '::ONCURRENCE AND CERTIFICATION OF SPONSOR'S ENGINEER -I have examined this periodic estimate, and concur in the certificate of the
~ntractor and certify that the materials used and the construction accomplished meet the requiresments of th; plans and SPicifj(~rons, as evi.d.enced by
certified test and insDectiOI) reports included in the oroiect records. . ^V I .1 f 1 ij
DATE I "Z-Iz-O/oS- ISIGNATURE, SPONSOR'S ENGINEE':?JA'J1s4r.l A,Jf j j/~, JLt ~
.-
---..
,;7
r\
./
,-
~
(ContiilUation Sheet)
Page 2 of 4
NAME OF CONTRACTOR: PROJECT TITLE:
Gohmann Asnhalt & Construction Co. 10th Street - Jeffersonville, IN ESTIMATE NO. 15
,....."- BREAKDOWN OF PERIODIC COST ESTIMATE
'1 I Total
Plan Completed $ Completed to %
Bid Item Description Quantity Units Unit Price Bid Total to Date Date Complete
1 Mobilization & Demobilization 1 LS $ 74,000.00 $ 74,000.00 1 $ 74,000.00 100%
2 Clearing Right-of-Way 1 LPS $ 20,000.00 $ 20,000.00 1 $ 20,000.00 100%
3 Surface Milling, Asphalt 566 SYS $ 5.00 $ 2,830.00 1253.01 $ 6,265.05 221%
4 Surface Milling, Portland 1247 SYS $ 6.00 $ 7,482.00 1228.42 $ 7,370.52 99%
5 Linear Grading 0.74 Mile $ 200,000.00 $ 148,000.00 0.74 $ 148,000.00 100%
6 Compacted Aggregate, 0, Size No. 53 10095 Tons $ 13.00 $ 131,235.00 11743.67 $ 152,667.71 116%
7 lIMA for Patching 513 Tons $ 70.00 $ 35,910.00 731.93 $ 51,235.10 143%
8 Portland Cement Concrete for Patching 9 SYS $ 210.00 $ 1,890.00 0 $. - 0%
9 lIMA Base 25.0 mm, Mainline 1765.4 Tons $ 29.00 $ 51,196.60 2149.8 $ 62,344.20 122%
10 lIMA Intermediate 19.0 rom, Mainline 1211.9 Tons $ 30.00 $ 36,357.00 1409.3 $ 42,279.00 116%
11 HMA Surface 9.5 rom, Mainline 1960.7 Tons $ 33.00 $ 64,703.10 1797.6 $ 59,320.80 92%
12 lIMA Wedge and Level 1890 Tons $ 34.00 $ 64,260.00 2333.05 $ 79,323.70 123%
13 lIMA for Approaches 108 Tons $ 68.00 $ 7,344.00 867.45 $ 58,986.60 803%
14 Asphalt for Tack Coat 4.2 Tons $ 200.00 $ 840.00 4.2 $ 840.00 100%
15 Curb Ramp, Concrete 503 SYS $ 46.00 $ 23,138.00 550.14 $ 25,306.44 109%
16 Sidewalk, Concrete 3204 SYS $ 29;00 $ 92,916.00 2839.6 $ 82,348.40 89%
17 Curb, Concrete 1290 LFT $ 19.00 $ 24,510.00 1641 $ 31,179.00 127%
18 Curb and Gutter, Concrete 6537 LFT $ 9.00 $ 58,833.00 8328 $ 74,952.00 127%
19 Cement Concrete Pavement for Driveways 1618 SYS $ 40.00 $ 64,720.00 1289.2 $ 51,568.00 80%
PCCP Patching, Full Depth (including Reinforcing
20 Steel) 77 SYS $ 90.00 $ 6,930.00 0 $ - 0%
21 Concrete, Class B 37.23 CYS $ 500.00 $ 18,615.00 40 $ 20,000.00 107%
22 Reinforcing Steel 2078 LBS $ 1.00 $ 2,078.00 2078 $ 2,078.00 100%
'--f.3 Concrete Modular Block Wall 605 SIT $ 22.00 $ 13,310.00 859 $ 18,898.00 142%
24 Pipe, PVC, Sanitary Sewer, 8 In., Install Only 318 LIT $ 35.00 $ 11,130.00 300.5 $ 10,517.50 94%
25 Pipe, PVc, Circlular, 12 In., Install Only 1311 LIT $ 26.00 $ 34,086.00 1427.5 $ 37,115.00 109%
26 Pipe, PVc, Circlular, 15 In., Install Only 9 LFT $ 58.00 $ 522.00 0 $ - 0%
27 Pipe, PVC, Circlular, 18 In., Install Only 113 LFT $ 32.00 $ 3,616.00 0 $ - 0%
28 Sanitary Manhole, Type "B", Install Only 2 Ea $ 1,500.00 $ 3,000.00 2 $ 3,000.00 100%
29 Casting, Adjust to Grade 59 Ea $ 200.00 $ 11,800.00 59 $ 11,800.00 100%
30 Inlet, 110, Install Only 17 Ea $ 700.00 $ 11,900.00 16 $ 11,200.00 94%
31 Inlet, MIO, Install Only 6 Ea $ 700.00 $ 4,200.00 6 $ 4,200.00 100%
32 Inlet, RI3, Install Only 2 Ea $ 700.00 $. 1,400.00 2 $ 1,400.00 100%
33 Mobilization & Demobilization for Seeding 2 Ea $ 500.00 $ 1,000.00 2 $ 1,000.00 100%
34 Fertilizer 0.72 Tons $ 550.00 $ 396.00 0.54 $ 297.00 75%
35 Seed Mixture, U 0.14 Tons $ 6,700.00 $ 938.00 0.0365 $ 244.55 26%
36 Mulching Material 3.62 Tons $ 430.00 $ 1,556.60 2.1 $ 903.00 58%
37 Water for Sod 5.6 MG $ 1.00 $ 5.60 0 $ - 0%
38 Sodding, Nursery 1477 SYS $ 4.00 $ 5,908.00 2282 $ 9,128.00 155%
39 Maintaining Traffic 1 LS $ 43,000.00 $ 43,000.00 1 $ 43,000.00 100%
40 Reset Panel Sign 1 Ea $ 900.00 $ 900.00 0 $ - 0%
41 Relocate Sheet Sign 22 Ea $ 150.00 $ 3,300.00 22 $ 3,300.00 100%
42 Sign Post, Square, 1, Reinforced Anchor Base 490.5 LIT $ 10.00 $ 4,905.00 439 $ 4,390.00 90"10
Sign, Sheet, Encapsulated Lens with Legend. 0.080
43 In. Thickness 179.33 SFT $ 30.00 $ 5,379.90 179.33 $ 5,379.90 100%
Sign, Sheet, Encapsulated Lens with Legend, 0.100
44 In. Thickness 39 SFT $ 36.00 $ 1,404.00 39 $ 1,404.00 100%
Sign, Sheet, Encapsulated Lens with Legend, 0.125
l~- 45 In. Thickness 67.5 SIT $ 14.00 $ 945.00 67.5 $ 945.00 100%
jj46 Traffic Signal Equipment, Remove, (2 locations) 2 LS $ 910.00 $ 1,820.00 2 $ 1,820.00 100%
(Continuation Sheet)
Page 3 ()f 4
NAME OF CONTRACTOR: PROJECT TITLE:
Gohmann Asnhalt & Construction Co. 10th Street - Jeffersonville, IN ESTIMATE NO. 15
.r--- BREAKDOWN OF PERIODIC COST ESTIMATE
t \ I Total
Plan Completed $ Completed to %
Bid Item Description Quantity Units Unit Price Bid Total to Date Date Complete
47 Signal Pole Support Foundation, 3 ft. X 12 ft. 7 Ea $ 1,600.00 $ 11,200.00 7 $ 11,200.00 100%
48 Handbole, Signal. 5 Ea $ 600.00 $ 3,000.00 5 $ 3,000.00 100%
Transportation of Salvageable Signa] Equipment (2
49 locations) 2 LS $ 1,100.00 $ 2,200.00 2 $ 2,200.00 100%
Pedestrian Signal Head with International Symbols,
50 18 in. 8 Ea $ 380.00 $ 3,040.00 8 $ 3,040.00 100%
51 Signal Detector Housing, Double 7 Ea $ 550.00 $ 3,850.00 7 $ 3,850.00 100%
52 Conduit, Steel, Galvanized, 2 in. 980 LFT $ 19.00 $ 18,620.00 1140 $ 21,660.00 116%
53 Handbole, Signal - Adjust to Grade 2 Ea $ 270.00 $ 540.00 2 $ 540.00 100%
,
54 Controller and Cabinet, Menu Driven, 8 Phase 2 Ea $ 8,000.00 $ 16,000.00 2 $ 16,000.00 100%
Traffic Signal Head, 3 face, 12 in. Red, Amber,
55 Green, with Red and Green - LED 13 Ea $ 500.00 $ 6,500.00 13 $ 6,500.00 100%
Traffic Signal Head, 5 face, 12 in. Red, Amber,
Green, Amber Arrow, Green Arrow with Red and
56 Green - LED 4 Ea $ 750.00 $ 3,000.00 4 $ 3,000.00 100%
57 Span, Catenary and Tether 8 Ea $ 1,200.00 $ 9,600.00 8 $ 9,600.00 100%
58 Disconnect Hanger 8 Ea $ 160.00 $ 1,280.00 8 $ 1,280.00 100%
59 Signal Service 2 Ea $ 500.00 $ 1,000.00 2 $ 1,000.00 100%
60 Signal Cable, 3C 8 Ga 126 LFT $ 1.00 $ 126.00 126 $ 126.00 100%
61 Signal Cable, Roadway Loop, IC 14 Ga 9940 LFT $ 0.25 $ 2,485.00 9880 $ 2,470.00 99%
62 Signal Cable, 5C 14 Ga 910 LFT $ 0.75 $ 682.50 2298 $ 1,723.50 253%
63 Signal Cable, 7C 14 Ga 1308 LFT $ 1.00 $ 1,308.00 2150 $ 2,150.00 164%
-- 64 Signal Cable, 2C 16 Ga 6818 LFT $ 0.70 $ 4,772.60 6686 $ 4,680.20 98%
! .
65 Signal Deetor Housing 6 Ea $ 400.00 $ 2,400.00 6 $ 2,400.00 100%
66 Saw Cut for Roadway Loop and Sealer 3165 Ea $ 8.00 $ 25,320.00 3165 $ 25,320.00 100%
67 Controller Cabinet Foundation, PI 2 Ea $ 600.00 $ 1,200.00 2 $ 1,200.00 100%
68 Pole Bands, Steel 6 Ea $ 120.00 $ no.oo 6 $ 720.00 100%
69 Signal Strain Pole, Steel, 30 ft. 7 Ea $ 2,600.00 $ 18,200.00 7 $ 18,200.00 100%
70 Loop Detector Delay Amplifier, 2 Channel 20 Ea $ 240.00 $ 4,800.00 20 $ 4,800.00 100%
71 Pedestrian Push Button and Sign 8Ea $ 100.00 $ 800.00 8 $ 800.00 100%
n Line, Thennoplastic, Broken, White, 4 In. 1900 LFT $ 0.70 $ 1,330.00 1600 $ 1,120.00 84%
73 Line, Thennoplastic, Solid, White, 4 In. 9460 LFT $ 0.70 $ 6,622.00 6904 $ 4,832.80 73%
74 Line, Thennoplastic, Broken, Yellow, 4 In. 1900 LFT $ 0.70 $ 1,330.00 820 $ 574.00 43%
75 Line, Thennoplastic, Solid, Yellow, 4 In. 7790 LFT $ 0.70 $ 5,453.00 8374 $ 5,861.80 107%
76 Line, Thennoplastic, Solid, Yellow, 8 In. 580 LFT $ 1.00 $ 580.00 618 $ . 618.00 107%
Transverse Markings, Thermoplastic, Solid,
77 Yellow, Crosshatch Line, 12 In. 80 LFT $ 6.00 $ 480.00 88 $ 528.00 110%
Transverse Markings, Thermoplastic, Stop Line, 24
78 In. 540 LFT $ 5.00 $ 2,700.00 515 $ 2,575.00 95%
Transverse Markings, Thermoplastic, Crosswalk
79 Line, 6 In. 2970 LFT $ 1.00 $ 2,970.00 2484 $ 2,484.00 84%
Pavement Message Markings, Thermoplastic, Lane
80 Indication Arrow 36 Ea $ 72.00 $ 2,592.00 36 $ 2,592.00 100%
81 Pavement Message Markings, Thermoplastic, Word 23 Ea $ 100.00 $ 2,300.00 23 $ 2,300.00 100%
82 Pavement Message Markings, Thermoplastic, Word 4Ea $ 260.00 $ 1,040.00 4 $ 1,040.00 100%
Relocate 8' Chain Link Fence with 3 Strands
83 Barbed Wire 133 LFT $ 25.00 $ 3,325.00 0 $ - 0%
84 Construction Engineering 1 LS $ 40,000.00 $ 40,000.00 1 $ 40,000.00 100%
\ i
(
Subtotals - Original Contract Items
$ 1,317,575.90
(et-c>)
$ 1,431,991.77
(Continuation Sheet)
Page 4 of 4
NAME OF CONTRACTOR: PROJECT TITLE:
Gohmann Asphalt & Construction Co. 10th Street - Jeffersonville, IN ESTIMATE NO. 15
--, BREAKDOWN OF PE'RIODIC COST ESTIMATE
Total
Plan Completed $ Completed to %
Bid Item Description Quantity Units Unit Price Bid Total to Date Date Complete
CHANGE ORDERS
CO# 1 IFlowable Fill at Near Locust Street 2 CY 1$ 100.00 $ 200.00 21 $ 200.00 100%
Subtotals for Change Order #1
$
200.00
$
200.00
Pedestrian Signal Head with International Symbol
CO #2.1 (Install Only) 10 Ea $ 340.00 $ 3,400.00 10 $ 3,400.00 100%
CO #2.2 Signal Oedestal, 10' (Install Only) lEa $ 465.00 $ 465.00 1 $ 465.00 100%
CO #2.3 Pedestrian Push Button and Sign (Install Only) 10 Ea $ 80.00 $ 800.00 10 $ 800.00 100%
CO #2.4 Signal Cable 3C #14 225 LFT $ 1.55 $ 348.75 225 $ 348.75 100%
CO #2.5 Pedestal Foundation Type A 1 Ea $ 685.00 $ 685.00 1 $ 685.00 100%
CO #2.6 Yellow Pinat for Overhead Signs 1 Gal $ 1,200.00 $ 1,200.00 1 $ 1,200.00 100%
CO #2.7 Green Paint for Overhead Signs 1 Gal $ 1,200.00 $ 1,200.00 1 $ 1,200.00 100%
Subtotals for Change Order #2
CO #3.1 Deduct for curb ramp coloring
CO #3.2 Added Inlet at Wall Street
Subtotals for Change Order #3
I CO #2A I Curb Ramp Coloring
Subtotals for- Change Order #2A
$
550.14~$
$
-22.95 $
4,364.38 $
$
22.95 I $
$
8098.75 $ 8,098.75
(813.81) $ (813.81)
4,364.38 $ 4,364.38
3,550.57 $ 3,550.57
12,625.71 I 550.141 $ 12,625.71 I 100%1
12,625.71 $ 12,625.71
Credit for money paid under auxiliary billings
1 Is
$ (12,625.71) $ (12,625.71)
$ (12,625.71)
r-,
~ .'
Subtotal- Change Order Items
$
11,849.33
$
11,849.33
Totals - Original Contract Items + Change Order Items
$/ 1,329,425.23
+ 'f 1\"1 J r.t 15'". 9'1- .,.
~ !/ilf3 I~ql. I~
$ 1,443,841.10
-r c.~O'\.je. Or-d.e.i Nt.. 9
f'"
......
/lIJ/I
r\
Gohmann Asphalt and Construction Inc.
p.o. Box 2428
Clarksville,lN 47131-2428
Phone (812) 282-1349
FAX (812) 288-2168
www.gohmannasphalt.com
July28, 2004
Jeffersonville Board of Pubic Works and Safety
City-County Building
501 East Court Avenue
Jeffersonville, IN 47130
Attn: 1'vfr. Bob Miller
Re: Tenth Street Reconstruction Project, Phase 1
Auxiliary Billing for Colored Sidewalk Ramps, Estimate #10
Billing #2
Gohmann Job Number: 10352
Dear Mr. Miller:
r\ This is an auxiliary billing for the colored sidewalk ramps on the above referenced
project. Per your request, Gohmann Asphalt & Construction, Inc. is billing you directly
for the price difference between the colored & non-colored ramps. The bid price for the
non-colored ramps was $46.00/sy, the price for the red colored ramps is $68.95/sy, for a
difference of$22.95/sy. This billing is through Estimate tHO, the previous biH was
through Estimate #5.
Units
Units Units completed
completed Previously under this Total due
Description Unit Unit Cost to date billed billing this billing
Additional cost of colored sidewalk ramps sy $ 22.95 346.2 222 124.2 $ 2,850.39
If you have any questions or need further information please do not hesitate to call me at
366-9485 or 552-7498.
Thank/ou,
rL,~
Dennis P. Dixon
Project Engineer
cc : Tom Schellenburg
",_01,.
---
i
EQUAL OPPORTUNITY EMPLOYER
~.,~..
. jSllr"~
-"1'1>
PRIKY
PUIr.11 ..PIlLI .....'If If IfUIIU
MEMBER
NAPA
....tffi\.....
.....\$'....
NATIONAL A$PNALT
PAVUoIENT ASSOCIATION
. ......vvIlLJl.:U uy -.:>ldltJ l>OWU 01 Accounts
ACCOUNTS PAYABLE VOUCHER
CITY OF JEFFERSONVILLE, INDIANA 47130
An invoice or bill to be properly itemized must show: kind of service, where performed, dates service rendered, by
whom, rates per day, number of hours, rate per hour, number of units, price per unit, etc.
City Form No. 201 (Rev. 1995)
Purchase Order No.
Terms
Date Due
Invoice
Date
Invoice
Number
J -1 ~-cNl *2.- --
Description
(or note attached invoice(s) or bill(s))
Amount
-c2t
(:C~cf,
Total
I hereby certify that the attached invoice(s), or bill(s), is (are) true and correct and that the materials or services
itemized thereon for which charge is made were ordered and received except
Date
~-~
, 20 .Q:i
/.?".IM' /" .ntlk.-' CcL{C,rv> .
Signature T tIe d
I hereby certify that the attached invoice(s), or bill(s), is (are) true and correct and I have audited same in accordance
with Ie 5-11-10-1.6.
Date
,20_
- Clerk - Treasurer